Title
Rizal Commercial Banking Corporation vs. Court of Appeals
Case
G.R. No. 133107
Decision Date
Mar 25, 1999
A vehicle purchase with an unsigned check led to RCBC's claim of default; SC ruled no default, citing inadvertence, and awarded damages due to RCBC's lack of good faith.
A

Case Summary (G.R. No. 133107)

Factual Background

The record recounted that private respondent Felipe Lustre purchased a Toyota Corolla from Toyota Shaw, Inc. and made a down payment of P164,620.00. He executed a promissory note and a contract of chattel mortgage to secure the balance, and issued twenty-four postdated checks for P14,976.00 each. Paragraph eleven of the chattel mortgage contained an acceleration clause making the whole unpaid balance due upon default in any installment and adding a twenty-five percent liquidated damages charge. Toyota Shaw assigned its rights under the chattel mortgage to Rizal Commercial Banking Corporation on March 14, 1991. The bank encashed and debited the borrower’s account for the checks dated April 10, 1991 through January 10, 1993, except for one representing the August 10, 1991 installment which was unsigned. That amount had been debited earlier but was later recalled and re-credited to the borrower’s account. After the recall, the bank ceased presenting the last two checks dated February 10, 1993 and March 10, 1993, allegedly pursuant to an internal procedure applicable when an account was forwarded to an account representative.

Procedural History

Petitioner Rizal Commercial Banking Corporation sent a demand letter dated January 21, 1993 asserting default because of the unsigned August 10, 1991 check and demanding payment of the entire balance plus liquidated damages. When the borrower refused, the bank filed a complaint for replevin and damages in the Pasay City RTC. Private respondent answered and filed a counterclaim for damages. The RTC dismissed the bank’s complaint for lack of cause of action and granted the counterclaim, directing the bank to accept payment equivalent to three checks totaling P44,938.00 and to release the mortgage upon such payment, awarding moral damages, exemplary damages, attorney’s fees, and costs. The Court of Appeals affirmed the RTC. Petitioner elevated the case to the Supreme Court.

Issues Presented

The principal issues were whether petitioner was justified in treating the whole indebtedness as immediately due and demandable under the acceleration clause because of an unsigned check, whether private respondent’s omission in respect of that check constituted default warranting damages and liquidated damages, and whether the bank’s conduct in encashing other postdated checks, recalling and re-crediting the amount for the unsigned check, and delaying action for over a year rendered it liable for damages.

Parties’ Contentions

Petitioner contended that paragraph eleven of the chattel mortgage was clear and unambiguous and entitled it to accelerate the obligation upon any failure to pay an installment; the unsigned check meant the August installment was unpaid and thus the bank properly demanded payment of the entire balance and liquidated damages. Private respondent maintained that the omission of his signature on the single check was inadvertent, that the amount had at one point been debited and then re-credited to his account, that subsequent checks were honored, and that the bank never notified him of any problem for more than sixteen months; he therefore denied culpable delay and counterclaimed for moral, exemplary damages and attorney’s fees because of the bank’s conduct.

Trial Court Findings

The Regional Trial Court found that the complaint lacked cause of action and dismissed it. The court ordered the bank to accept payment equal to three checks totaling P44,938.00 and to release or cancel the mortgage upon such payment. On the counterclaim the RTC awarded moral damages of P200,000.00, exemplary damages of P100,000.00, and attorney’s fees of P50,000.00, in addition to costs of suit.

Court of Appeals Ruling

The Court of Appeals concurred with the trial court and treated the chattel mortgage as a contract of adhesion, to be strictly construed against the drafter where stipulations were obscure or ambiguous, invoking Article 1377, Civil Code. The appellate court held that paragraph eleven should be read to cover deliberate and advertent failure to pay. It found that the bank’s assertion of default rested solely on the unsigned August 10, 1991 check, which the bank had initially debited and later re-credited; that the bank encashed subsequent checks; and that the bank failed to notify or summon the mortgagor for sixteen months. The Court of Appeals characterized the omission as inadvertence and the bank’s conduct as remiss and mercenary, and it affirmed the RTC’s dismissal and the awards granted on the counterclaim.

Supreme Court Ruling

The Supreme Court accepted the outcome reached by the courts below but qualified and adjusted certain reasoning and awards. The Court observed that although contracts of adhesion are binding, ambiguity alone justifies construction against the drafter and that where terms are clear the literal meaning controls. The Court examined paragraph eleven and recognized that its language was clear and, on its face, permitted acceleration upon failure to pay any installment. Nevertheless, the Court found that petitioner’s mechanical reliance on the clause was unwarranted in the circumstances. The Court held that there was no evidence of malice or negligence on the part of private respondent in failing to sign the check; testimony showed the omission to be inadvertent and that the seller’s own representatives had observed and sought to correct unsigned checks at the time of the sale. The Court also noted that the bank had debited the amount, later re-credited it, encashed later checks, and failed to notify the mortgagor of the issue for an extended period. In view of the bank’s remiss and mercenary conduct and the mortgagor’s lack of culpable delay, the Court affirmed the dismissal of the complaint and sustained liability of the bank for damages. The Court, however, reduced the amounts awarded as excessive.

Legal Basis and Reasoning

The Court applied the rule that ambiguities in instruments prepared by one party are construed against the drafter, citing Article 1377, Civil Code, but stressed the corollary that where contractual terms are clear no construction is necessary. The Court examined Article 1170, Civil Code, to explain that liability for delay requires malice or negligence, and found no such culpability in the mortgagor’s inadvertent omission. The Court invoked Article 19, Civil Code as embodying the duty to observe honesty and good faith, and held that the bank’s failure to communicate and its selective encashment and re-creditin

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.