Title
Ramel vs. Aquino
Case
G.R. No. 133208
Decision Date
Jul 31, 2006
Daniel Aquino mortgaged land to DBP; petitioners agreed to buy part, assumed mortgage, but breached by late payments and restructuring loan without consent. Rescission upheld; offsetting claims denied due to lack of evidence.

Case Summary (G.R. No. 133208)

Factual Background: Oral Sale, Payments, and Loan Restructuring

The agreement was not reduced into writing. Petitioners gave earnest money of P5,000.00 on August 7, 1983. They later paid P15,000.00 on September 7, 1983 and P4,800.00 on February 12, 1984, and these payments were receipted by respondents. Petitioners also paid DBP directly: P10,000.00 on September 7, 1983, P3,097.00 on November 18, 1983, and P10,000.00 on April 2, 1984, totaling P23,097.00. Respondents likewise sold petitioners a 2,484-square-meter portion of the southern part for P2,700.00, and petitioners paid the full amount on September 7, 1983. On the same date as the initial acceptance, respondents allowed petitioners to take possession of the sold parcels, after which petitioners allegedly introduced improvements such as rice paddies, drainage canal, fence, and a house.

In November 1983, petitioners applied to DBP for restructuring of the mortgage loan for ten years, allegedly with respondents’ conformity. DBP approved the restructuring under a schedule of semi-annual amortizations: P8,634.15 beginning May 21, 1984 for five years, and thereafter P4,904.60 for the 6th to the 10th year. Petitioners went to DBP on October 1, 1984 to pay an amortization and discovered that respondents had paid DBP an amount of P72,703.06. Petitioners offered to return that sum, but respondents refused, asserting instead they would return what they paid for the land and threatening to withdraw the certificate of title from the bank. The DBP manager treated respondents’ payment as a deposit and granted time for the parties to settle, but no settlement resulted. Petitioners filed their case on October 9, 1984 for Specific Performance with Preliminary Injunction and Damages. On October 12, 1984, the trial court restrained respondents from withdrawing the certificate of title and from the bank releasing the Release of Mortgage. Despite this restraint, respondents withdrew the P72,703.06 on the same day.

During the pendency of the case, petitioners later fully settled the mortgage loan with DBP, paying P30,000.00 on November 29, 1984, P50,000.00 on April 30, 1986, and P5,118.42 on May 2, 1986, for a total of about P108,216.00. DBP then deposited the Release of Mortgage with the Clerk of Court.

Respondents’ Version: Alleged Contract Terms, Default, and Rescission

Respondents claimed the sale terms differed from petitioners’ account. They alleged that petitioners agreed to pay P35,000.00, not P25,000.00. They further alleged that petitioners agreed to assume in full the remaining mortgage loan with DBP and to withdraw the certificate of title by December 31, 1983, which was necessary for respondents to claim the area allegedly taken by the NIA for an irrigation canal. Respondents asserted that petitioners defaulted by failing to pay DBP within the agreed period and by restructuring the loan without respondents’ consent. Upon learning of petitioners’ restructuring, respondents allegedly decided to revoke the sale, sold part of Lot No. 2080, and tendered P72,703.06 from the proceeds to DBP in full settlement on October 1, 1984.

Respondents-intervenors, Benjamin Aquino and Virginia Aquino, invoked their position as co-owners and participated in the proceedings. An amicable settlement between respondents and intervenors was reached on March 2, 1985.

Trial Court Proceedings and the June 28, 1990 Decision

The trial court conducted a pre-trial conference and issued an order on March 11, 1986 on the material stipulations of facts. It noted, among others, that the 8.2030-hectare riceland covered by TCT No. 36937 was in Daniel Aquino’s name. It also identified the payments made by Rene Lemar R. Ramel that were duly receipted, including P4,800.00 dated February 12, 1983, P5,000.00 on August 7, 1983, P15,000.00 on September 7, 1983, and P2,700.00 on September 7, 1983.

On June 28, 1990, the trial court granted rescission and ordered mutual restitution. It directed respondents to execute a deed of sale over the 2,484-square-meter portion in favor of Rene Lemar Ramel. It declared the oral contract of sale between Rene Lemar Ramel and the Aquino spouses rescinded. It ordered respondents to pay Rene Lemar Ramel P29,800.00 representing amounts received for the land, plus P108,216.00 representing amounts paid by petitioners to the bank. It further ordered petitioners to return peaceful possession to respondents after payment. As to intervenors, it directed them to reimburse Daniel Aquino their one-third share of P138,016.00 that he paid to the plaintiff, and it declared intervenors to be co-owners of the 8.2030-hectare southern portion in equal shares.

Appeals and the Petition for Review

Petitioners appealed to the Court of Appeals, which affirmed the trial court’s decision and denied the motion for reconsideration. Petitioners then filed the present Petition for Review on Certiorari. They challenged the factual findings and argued that: (a) they substantially complied with their obligations and that any breach was not substantial; (b) respondents had no legal ground to rescind because there was no proper demand within the contemplation of Art. 1592, Civil Code; and (c) the trial court’s and appellate court’s decision to offset their improvements against respondents’ fruits was erroneous.

The Court’s Core Issues and Analysis

The Court treated as hinge issues: (1) whether petitioners substantially breached their obligation warranting rescission, and (2) whether there was legal ground to order the offsetting of petitioners’ claim for improvements against respondents’ claim for fruits derived from the land.

On the first issue, the Court examined the total remaining mortgage obligation that petitioners were to assume. It considered DBP’s official receipt dated September 7, 1983, which showed that the remaining mortgage obligation of respondents as of September 7, 1983 was P75,544.92, after petitioners had already paid DBP P10,000.00 on the same date. From that, the Court reasoned that the remaining mortgage obligation as of July 31, 1983 that petitioners were to assume amounted to P85,544.92, and therefore the balance to be paid to respondents was about P25,000.00, not P35,000.00. The Court found that the courts a quo had erred in concluding petitioners paid respondents a total of P29,800.00, explaining that, by the parties’ own stipulations, petitioners paid a total of P27,500.00, which included the P2,700.00 for the additional 2,484-square-meter portion purchased from respondents. After deducting the P2,700.00 purchase payment, petitioners had paid P24,800.00 of the about P25,000.00 balance. The Court held that this minor discrepancy could not justify rescission.

However, the Court then evaluated whether petitioners failed to pay the mortgage balance within the contract’s agreed period. It found that when petitioners filed the case on October 9, 1984, they had paid only P23,097.00 of the outstanding P85,544.92 mortgage obligation. It observed that instead of paying within the period ending December 31, 1983, petitioners sought restructuring for ten years in November 1983 without respondents’ consent, and it found petitioners’ contrary claim unsubstantiated. The Court noted that respondents later paid P72,703.06 to DBP after learning of the restructuring, but that respondents’ later withdrawal of the deposit did not defeat their position because the trial court had enjoined withdrawal of the certificate of title and prevented the bank from releasing the same. It also stressed that the property was facing foreclosure in December 1983 and that respondents’ offer to sell was precisely meant to avoid foreclosure; it was not reasonable, in the Court’s view, to expect that respondents would be left without any definite timeframe for petitioners to complete payment, especially when foreclosure loomed.

Although petitioners eventually fully settled the mortgage loan in May 1986—two years and five months after December 1983 and one and one-half years after filing the case—the Court emphasized that petitioners reneged on their obligation to pay within the agreed period. It held that petitioners could have requested a grace period but did not. The Court addressed petitioners’ reliance on a Notice of Loan Approval dated November 24, 1983 addressed to respondent Aquino and rejected it as proof of respondents’ authorization to restructure, reasoning that the notice was authored by petitioners, was only a notice, did not show receipt by respondents, and was followed by respondents’ actions to sell another portion of the land to pay the remaining obligation. It further held that respondents’ later withdrawal was attributable to the restraining order, not to any waiver of the right to rescind.

Based on these findings, the Court held that petitioners committed a substantial breach that justified rescission under Art. 1191, Civil Code. It reasoned that the purpose of the parties’ reciprocal undertaking was for the mortgage obligation to be paid, freeing respondents from encumbrances, and that petitioners’ failure to pay the mortgage until after one and one-half years from the filing of the case was substantial. Petitioners’ argument that the breach was casual or slight was rejected. The Court also considered the fact that, not merely the sold 8.2030-hectare portion but the broader property remained encumbered beyond the agreed deadline, thereby restricting the owners’ rights.

Demand for Rescission Under Article 1592

Petitioners further invoked Art. 1592, Civil Code, arguing that respondents were not entitled to rescind because no demand for rescission was made either judicially or by notarial act prior to the filing of the case. The Court rejected this argument. It relied on its rulings in Luzon Brokerage Co., Inc. v. Maritime Building Co., Inc. (G.R. No. L-25885, January 31, 1972) and Iringan v. Court of Appeals (G.R. No. 129107, September 26, 2001) to hold that a judicial demand may be satisfied even by a

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.