Title
R-II Builders Inc. vs. Construction Industry Arbitration Commission
Case
G.R. No. 152545
Decision Date
Nov 15, 2005
R-II Builders subcontracted Mivan for construction; delays, additional costs, and disputes arose. CIAC awarded Mivan P50M for variations, increased costs, and VAT. SC upheld rulings, rejecting R-II's claims.
A

Case Summary (G.R. No. 152545)

Factual Background

On September 3, 1997, R-II and BCDA executed an agreement for the construction, on the specified Fort Bonifacio area, of the Philippine Army Officer’s Quarters Project. Under the agreement, R-II undertook, for P788,973,413.00 inclusive of taxes and fees, the site planning and development and the design/construction of twenty-eight (28) four-storey medium-rise buildings in accordance with architectural and engineering plans and specifications prepared by R-II and approved by BCDA.

Even prior to signing of the main R-II–BCDA agreement, R-II had initiated negotiations for a subcontracting arrangement with Mivan. R-II provided Mivan with advance copies of the drawing plans submitted to BCDA. On August 25, 1997, R-II issued to Mivan the contract drawings and specifications to support Mivan’s estimate and tender of the subcontract price amounting to P459,000,000.00. A “Notice to Proceed” dated September 6, 1997 followed, fixing a one-hundred eighty (180)-day completion period from September 8, 1997 until March 6, 1998. Mivan mobilized and established its labor camp at the job site. By September 26, 1997, its formworks were arriving at the port of Manila.

Mivan’s subcontract award was influenced by its aluminum framework system. That method avoided hollow blocks by utilizing pre-fabricated aluminum formworks into which concrete was poured while multiple floors could be formed if appropriate. The system also permitted multiple reuse, allegedly reducing construction time and costs.

On October 3, 1997, R-II and Mivan executed the formal subcontract agreement (the R-II Mivan Agreement). Under its terms, R-II undertook to pay Mivan a fixed lump sum of P459,000,000.00, plus applicable Value Added Tax (VAT) based on R-II’s contract drawings issued on August 25, 1997. Mivan’s scope included structural, electrical, and finishing works necessary to complete the buildings according to R-II’s plans and specifications. The subcontract divided the project into two categories: (a) twenty (20) M120 Buildings and (b) eight (8) M180 Buildings, differentiated by apartment size and number of apartments per floor.

The subcontract further contained provisions on price escalation/adjustment and allowed variations/alteration orders. It incorporated, by express reference, the provisions of Presidential Decree (P.D.) No. 1594, titled “Prescribing Policies, Guidelines, Rules and Regulations for Government Infrastructure Contracts.” Despite the apparent comprehensiveness of the subcontract, R-II later subcontracted part of the original works—specifically, the supply and erection of formworks for buildings sixteen (16), seventeen (17), and twenty-one (21)—to Rigid Systems, Inc. (RSI). Mivan was then forced either to rework RSI’s defective output or to complete RSI’s unfinished sub-contracted works.

In the course of implementation, R-II, responding to BCDA’s request, asked Mivan to fast-track the completion of five (5) buildings. The original November 1997 deadline was later moved to January 1998. These developments—RSI’s inability to perform, the employment of additional hired hands, acceleration of turnover, and deviations from original plans/specifications—disrupted schedules and increased costs. Mivan nonetheless completed its undertakings, but forty-nine (49) days beyond the original completion date and only after incurring additional costs which Mivan attributed to overhead costs and events causing disruptions/delays, including variations to contract drawings, other change orders, requirements for early completion of certain buildings, repairs of works done by others, and the introduction of other formwork systems into the superstructures.

Because of these circumstances, Mivan demanded additional and/or differential payments itemized as follows: variation claims of P58,477,320.27; escalation claims of P11,027,204.00; disruption claims of P48,273,305.22; for a subtotal of P117,747,829.49, plus ten percent (10%) VAT amounting to P11,774,782.95, for a grand total of P129,522,612.44.

R-II acknowledged liability for variation costs but only up to P15,095,597.20, and for escalation costs amounting to P747,585.82. R-II insisted that P15,095,597.20 was the amount reached after joint quantification and costing of the as-built drawings and contract drawings on December 2–4, 1998, facilitated with BCDA intercession to resolve the quantification issue concerning variation or additional work on substructures and superstructures.

Resort to CIAC and the CIAC Award

When the parties failed to settle the dispute, TECHPIL intervened. In its report dated December 14, 1998 to BCDA, TECHPIL evaluated the quantifying results based on Mivan’s detailed computation and determined that P40,719,802.41—out of Mivan’s P58,477,320.27 variation claim—was valid and legitimate. TECHPIL accordingly recommended that R-II be ordered to pay P40,719,802.41.

R-II refused. Mivan therefore pursued its claims before the CIAC under par. 14.1, Article XIV of the subcontract agreement. The case was docketed as CIAC Case No. 22-99. On November 12, 1999, CIAC Sole Arbitrator Alfredo F. Tadiar rendered a decision awarding Mivan monetary relief as follows: P39,000,000.00 for variation claims; P3,198,170.00 for increased costs of labor, materials, and equipment arising from the accelerated schedule of turnover of five buildings; P3,099,089.76 for reimbursement of an amount overcharged for an additional labor force supplied by R-II; P747,585.82 for escalation claims; and P4,294,575.58 for VAT computed at 10% of the awarded amounts except for reimbursement. The CIAC also imposed interest: six percent (6%) per annum on P46,044,845.58 excluding VAT from the date of decision, and after finality, twelve percent (12%) per annum until full payment, citing Eastern Shipping Lines, Inc. v. Court of Appeals and other authorities.

Appellate Proceedings in the Court of Appeals

R-II sought review in the Court of Appeals via a petition for review under Rule 43, docketed as CA G.R. No. SP No. 56142. Mivan also filed a similar recourse but withdrew it with the appellate court’s approval. On October 26, 2001, the Court of Appeals denied R-II’s petition and affirmed the CIAC award in toto, dismissing the application for injunctive relief. R-II moved for reconsideration, but the Court of Appeals denied the motion on March 6, 2002.

The Execution Dispute and CA G.R. SP No. 68178

Before the Court of Appeals could resolve the Rule 43 petition, Mivan moved for execution of the CIAC decision dated November 23, 1999. Sole Arbitrator Tadiar denied execution by Orders dated July 9, 2001 and October 15, 2001. Mivan then challenged the denial orders before the Court of Appeals through a petition for certiorari and mandamus under Rule 65, docketed as CA G.R. SP No. 68178.

In a decision dated June 14, 2004, the Court of Appeals granted the petition. It annulled the July 9, 2001 and October 15, 2001 orders and directed the public respondent to issue a writ of execution of the CIAC decision dated November 23, 1999 in CIAC Case No. 22-99. The Court of Appeals denied R-II’s motion for reconsideration through a Resolution dated September 28, 2004.

Supreme Court Petitions and Consolidation

Following the Court of Appeals denial of reconsideration, R-II filed the present Supreme Court petition G.R. No. 165687, later consolidated with G.R. No. 152545. Meanwhile, after the Court of Appeals ruling on execution, the Sole Arbitrator changed course and directed on August 23, 2004 the issuance of a writ of execution conditioned upon Mivan’s posting of a bond. Mivan posted the bond on December 17, 2004, and the Sole Arbitrator approved it on January 11, 2005, then ordered the writ of execution to issue. On R-II’s motion, CIAC stayed release of the writ upon R-II’s posting of a counter-bond within ten days, which R-II eventually did.

The developments effectively rendered moot and academic the execution issue raised in G.R. No. 165687, namely, whether a CIAC arbitral award is immediately executory. Mivan emphasized in its comment dated March 21, 2005 that no writ had been issued as of that date, and R-II sought to arrest execution. Nonetheless, the Supreme Court observed that the stay sought in G.R. No. 165687 had already been granted through CIAC’s subsequent action. Accordingly, only G.R. No. 152545 remained for resolution.

The Parties’ Contentions in G.R. No. 152545

R-II’s remaining challenge in G.R. No. 152545 attacked the CIAC and Court of Appeals determinations on three fronts. First, it contested the variation claims awarded to Mivan, insisting that its liability should be limited to P15,095,597.20, consistent with its position on the proper quantification of variations. Second, it argued that Mivan’s other monetary claims were barred by provisions in the subcontract, particularly those requiring written notice and cost impact submission under par. 7.4 and those stating that no contract price adjustment would be valid unless ordered in writing, under par. 4.2. Third, it assailed the award of VAT, contending that VAT was not within the issues agreed upon during the preliminary arbitral conference and thus not included in the Terms of Reference (TOR).

Legal Basis and Reasoning

On the variation claims, the Supreme Court stressed that R-II’s arguments were directed to a factual determination made by the Court of Appeals and affirmed from CIAC. The Court reiterated the settled rule that, in a petition for review on certiorari, the Supreme Court generally does not entertain factual matters except for recognized exceptions, such as when the findings are drawn from a vacuum, are arbitrarily reached, are based on speculation or conjecture, or are manifestly mistaken or absurd. The Court found no compelling reason to depart from the appellate court’s factual conclusions.

The Court noted that the Court of Appeals had specifically referenced Mivan’s detailed documentation of variation costs and the TECHPIL report’s quantificat

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.