Title
Source: Supreme Court
Prudential Guarantee and Assurance, Inc. vs. Equinox Land Corp.
Case
G.R. No. 152505-06
Decision Date
Sep 13, 2007
Equinox terminated J'Marc's construction contract due to delays and underperformance. Prudential, as surety, was held solidarily liable with J'Marc for damages, affirmed by the Supreme Court. CIAC jurisdiction applied.

Case Summary (G.R. No. 152505-06)

Background Facts

In 1996, Equinox decided to expand its building and invited bids from contractors. J'Marc was awarded the contract, with a total consideration of P37,000,000. Upon acceptance of the contract on February 22, 1997, J'Marc submitted two bonds issued by Prudential: a surety bond of P9,250,000.00 and a performance bond of P7,400,000.00. Following various performance issues, including delayed work and improper handling of materials, Equinox terminated the contract on July 10, 1997, and subsequently claimed damages from both J'Marc and Prudential.

Procedural History

Equinox initiated legal proceedings against J'Marc and Prudential in the Regional Trial Court (RTC), which led to Prudential filing a motion to dismiss, asserting lack of jurisdiction on the RTC's part based on Executive Order No. 1008, which designates the Construction Industry Arbitration Commission (CIAC) as the appropriate forum for construction disputes. The RTC granted Prudential’s motion to dismiss on February 12, 1999, which resulted in Equinox filing a request for arbitration before the CIAC.

CIAC Decision

The CIAC ruled in favor of Equinox on December 21, 1999, affirming the termination of the contract based on J'Marc’s failure to meet its obligations. Equinox’s claims for direct payments made on behalf of J'Marc were upheld, with J'Marc held liable for P4,639,285.34. Prudential's liability was also addressed, determining that it owed amounts under both the surety and performance bonds.

Court of Appeals Review

Prudential challenged the CIAC's decision before the Court of Appeals, asserting it should not be bound by the construction contract conditions and is not solidarily liable with J'Marc. The Court of Appeals confirmed the CIAC’s jurisdiction and found Prudential solidarily liable alongside J'Marc for damages due to the suretyship implications established in their contracts.

Key Legal Issues

  1. Jurisdiction: The assertion that the CIAC held exclusive original jurisdiction over construction contracts according to Executive Order No. 1008 was upheld. The Court established that Prudential, having earlier invoked CIAC jurisdiction, was estopped from contesting it later.

  2. Liability of Surety: The nature of Prudential's obligation as a surety was affirme

...continue reading

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources.