Title
Pro Builders, Inc. vs. TG Universal Business Ventures, Inc.
Case
G.R. No. 194960
Decision Date
Feb 3, 2016
Construction dispute between TG and Pro Builders over delays, payment issues, and material delivery; both parties found in breach; CIAC award reinstated, denying most claims and counterclaims.

Case Summary (G.R. No. 194960)

Factual Background

TG and Pro Builders executed the Owner-Contractor Agreement on 29 May 2007, with TG obligated to pay the 30% down payment. Upon signing, Pro Builders posted a performance bond obtained from Prudential Guarantee and Assurance, Inc. and the Notice of Award was issued on 15 May 2007. The project site was turned over to Pro Builders on 22 May 2007, and construction was set to begin on 1 June 2007.

Pro Builders received the first down payment only on 19 June 2007, amounting to P21,000,000.00. The project did not progress satisfactorily. TG then took over the project, hired another contractor to finish the work, and demanded the balance of what TG treated as an overpayment. When the parties failed to settle, TG filed a Request for Arbitration with the CIAC seeking payment of the cost to complete the project, which TG computed at P13,489,807.48. The claimed excess was broken down into an unconsumed down payment component, additional expenses incurred by engaging another contractor, and miscellaneous expenses. TG further claimed litigation expenses and attorney’s fees in its bond-related claim.

In response, Pro Builders denied TG’s theory of entitlement and asserted that TG caused delay by late delivery of owner-supplied materials, especially rebars, and by delayed release of down payment. Pro Builders also insisted that TG’s performance evaluation should be reckoned within seven days upon receipt of the down payment. Pro Builders counterclaimed for unpaid accomplishment, various compensatory and exemplary damages, rental deposit for forms and scaffoldings, surety and insurance costs, and litigation expenses and attorney’s fees, among others.

Arbitration Issues and the Arbitral Tribunal’s Decision

The Arbitral Tribunal limited the issues to determining which party failed to comply with the contract terms; whether Pro Builders was in delay and whether TG itself was in delay in releasing down payment and delivering owner-supplied materials; whether TG was entitled to various components of its claims, including the unliquidated down payment, cost to complete, and miscellaneous expenses; whether Pro Builders was entitled to its counterclaims; and whether the surety company was solidarily liable, together with issues on possible expiration, waiver, or legal obligations of third-party respondents to indemnify the surety if liability were imposed.

On 1 October 2008, the Arbitral Tribunal ruled in favor of Pro Builders to a limited extent. It ordered TG to pay Pro Builders P2,104,642.11 for unpaid accomplishment and awarded Pro Builders P58,333.34 as reimbursement for the staging area rental paid by TG in advance. After offsetting these amounts, the Arbitral Tribunal ordered that TG pay Pro Builders P2,046,308.77. It denied TG’s claims for the unliquidated down payment balance, cost to complete, most miscellaneous expenses, exemplary damages, litigation expenses, and attorney’s fees for lack of merit. It also denied Pro Builders’ counterclaims for damages, rental deposit, costs of bonds, litigation expenses, exemplary damages, and attorney’s fees.

The Arbitral Tribunal’s factual findings were that both parties failed to comply with their respective obligations. It held that Pro Builders failed to meet milestones due to inability to deploy required manpower and equipment and committed violations of concrete protocol. For TG’s part, it found that TG made the down payment only on 19 June 2007 rather than upon execution of the agreement, did not pay progress billings and change orders, and caused delay in delivering owner-supplied rebars. On TG’s claim for cost to complete, the Arbitral Tribunal reasoned that the value could only be determined after completion of the project. It also denied Pro Builders’ claim for unprovisioned items and held no contractual basis for reimbursement of bonding costs.

Proceedings Before the Court of Appeals

Pro Builders challenged only portions of the Arbitral Tribunal’s decision. The Court of Appeals, in a Decision dated 13 October 2010, granted TG’s petition in part and modified the CIAC ruling. It ordered Pro Builders to pay TG the balance of the unspent down payment (P5,582,921.10), TG’s cost to complete (P7,771,553.04), additional miscellaneous expenses (P77,200.00), and attorney’s fees and litigation expenses (P500,000.00), while declaring TG not entitled to cost of rectification and exemplary damages. It also deleted the Arbitral Tribunal award of P2,104,642.11 to Pro Builders. In all other respects, it affirmed the CIAC decision. The Court of Appeals denied Pro Builders’ reconsideration in a Resolution dated 16 December 2010.

The Court of Appeals held that inadequate performance was attributable to Pro Builders alone. It found that TG did not delay the release of the P21,000,000.00 down payment, reasoning that its release on 19 June 2007 coincided with Pro Builders’ posting of the surety bond. It sustained TG’s claim for P5,582,921.10 by subtracting Pro Builders’ accomplishments valued at P15,417,078.90 from the down payment. It credited TG’s documentary support for that accomplishment value, including its evaluation materials and related documentation, and held that TG’s receipt of Pro Builders’ progress billings did not estop TG from disputing the real amount of Pro Builders’ undertakings.

On TG’s cost-to-complete claim, the Court of Appeals ruled that TG was entitled to P7,771,553.04 based on supporting documents allegedly disregarded by the Arbitral Tribunal. It also awarded additional miscellaneous expenses and attorney’s fees because it found TG was compelled to initiate the proceedings before the Arbitral Tribunal.

Petition to the Supreme Court and the Procedural Issue

Pro Builders initially invoked the Court’s power to delve into facts, arguing that the Court of Appeals and the Arbitral Tribunal produced conflicting findings. Pro Builders contended that the Court of Appeals erred in determining that its accomplishments were worth only P15,417,078.90. It argued that the joint evaluation used by the Court of Appeals was allegedly one-sided because it was prepared solely by TG’s project manager and submitted long after the contract termination. Pro Builders also relied on the Arbitral Tribunal’s preference for its progress billings as more accurate and reliable.

Pro Builders further argued that the cost overrun could not be computed because the project had not been finished when submitted to the Arbitral Tribunal, and it challenged the award of attorney’s fees and litigation expenses. It also asserted that TG availed of the wrong remedy by filing a petition for partial review before the Court of Appeals, reasoning that the CIAC award should be appealable on questions of law to the Supreme Court.

The Supreme Court first addressed the procedural question concerning the proper forum and mode of review. It explained that Executive Order No. 1008 vested in CIAC original and exclusive jurisdiction over disputes arising from or connected with construction contracts in the Philippines, and that Section 19 of E.O. No. 1008 declared CIAC awards final and unappealable except on questions of law, appealable to the Supreme Court. However, the Court recognized that amendments introduced by R.A. No. 7902 and the effect of the 1997 Rules of Civil Procedure as amended brought the CIAC within the enumeration of quasi-judicial agencies whose decisions or awards may be appealed to the Court of Appeals via a Rule 43 petition for review, with review potentially involving questions of fact, law, or both. It also noted the CIAC Revised Rules of Procedure on petitions for review and held that, applying these rules, the Court of Appeals correctly took cognizance of TG’s appeal.

Substantive Issues and Standards for Review

On the merits, the Supreme Court treated the issues raised by Pro Builders as questions of fact. It reiterated that a question of fact exists when the issue pertains to the truth or falsity of alleged facts and that re-evaluation of credibility and surrounding circumstances are factual matters. It further acknowledged the general rule that the Court of Appeals’ factual findings are conclusive, but it enumerated recognized exceptions, including when the findings of the Court of Appeals and the court or tribunal below are contradictory, when the findings are conflicting, when conclusions are made without specific evidentiary citation, or when findings are premised on misapprehension of facts.

Given that the Court of Appeals’ factual findings conflicted with those of the Arbitral Tribunal, the Supreme Court proceeded to review the evidence on record.

Valuation of Pro Builders’ Accomplished Works

The principal controversy centered on the monetary value of Pro Builders’ accomplished works. Pro Builders computed its accomplishments based on its progress billings, arriving at P22,482,934.34 broken down by billing periods and including a change order, for a total of P23,104,642.11. By deducting TG’s P21,000,000.00 down payment and adding the change order amount of P621,598.77, Pro Builders claimed an additional collectible amount of P2,104,642.11.

TG computed Pro Builders’ accomplishment at P15,417,078.90, allegedly supported by documentation such as a “joint evaluation,” photographs showing suspended slabs at the second floor, a letter recognizing a joint inspection, a summary of additive and deductive works, and Pro Builders’ own written computation. TG then argued that Pro Builders must return the excess portion of P5,582,921.10 from the down payment.

The Supreme Court held that Pro Builders’ valuation of accomplished works was more accurate. It reasoned that a joint evaluation had been agreed upon by the parties and that Pro Builders had initially demanded a joint assessment, while TG responded as amenable and claimed that a joint assessment had already been completed. The Court, however, agreed with the Arbitral Tribunal’s conclusion that the alle

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.