Title
Philippine Economic Zone Authority vs. Carantes
Case
G.R. No. 181274
Decision Date
Jun 23, 2010
Respondents claimed land via CALC, built structures; PEZA contested authority, demanded demolition. SC ruled PEZA has exclusive permit authority, ordered demolition.

Case Summary (G.R. No. 181274)

Factual Background

Respondents were in possession of a 30,368-square meter parcel of land located in Loakan Road, Baguio City. On June 20, 1997, they obtained Certificate of Ancestral Land Claim (CALC) No. CAR-CALC-022 from the Department of Environment and Natural Resources (DENR). On the strength of this CALC, respondents secured a building permit and a fencing permit from Baguio City Building Official Teodoro G. Barrozo. Respondents thereafter fenced the premises and began constructing a residential building.

On February 9, 1999, respondents received a letter from Digna D. Torres, Zone Administrator of PEZA, informing them that the house they built had overlapped PEZA’s territorial boundary. Torres advised respondents to demolish the structure within sixty (60) days from notice. The letter warned that, upon failure, PEZA would undertake demolition at respondents’ expense.

Without responding to the PEZA notice, respondents filed a petition for injunction before the RTC of Baguio City, seeking a temporary restraining order (TRO) and a writ of preliminary injunction. The RTC issued a TRO on April 8, 1999, directing PEZA to cease and desist from threatening demolition before respondents’ application for a writ of preliminary injunction could be heard. On September 19, 2001, the RTC ordered the parties to maintain the status quo pending resolution. On October 2, 2001, the RTC granted the petition for injunction and ordered the issuance of a writ enjoining PEZA from dispossessing or disturbing respondents’ peaceful possession and occupation of the land.

RTC’s Ruling Granting Injunction

The RTC held that respondents were entitled to possess, occupy, and cultivate the subject lots based on their CALC. It reasoned that, by definition under R.A. No. 8371, ancestral land is segregated from lands of the public domain, such that respondents’ rights over the land were already vested and could not be disturbed by Proclamation No. 1825, which included the area within an export processing zone.

Court of Appeals Proceedings and Decision

On appeal, the Court of Appeals affirmed the RTC ruling in a Decision dated October 26, 2007. The appellate court echoed the trial court’s declaration that the lots were set aside from the lands of the public domain and that respondents were entitled to protection against PEZA’s threatened action.

Issues Raised by Petitioner PEZA

PEZA challenged the CA decision on two issues. First, it questioned whether PEZA or the City Engineer/City Building Official of Baguio City had legal authority to issue building and fencing permits for constructions within the PEZA-BCEZ. Second, it questioned whether respondents’ CALC was sufficient to disregard the provisions of the National Building Code of the Philippines.

The Court framed the essential inquiry as whether PEZA could require respondents to demolish the structures they had built within the territory of PEZA-BCEZ despite respondents’ possession of permits and a CALC.

Procedural Lapse on the Timeliness of the Petition

Before the Court addressed the merits, the Office of the Solicitor General (OSG) for PEZA explained the delay in filing the petition. It stated that it received the CA decision on November 7, 2007, but filed the petition only on February 1, 2008, or almost three (3) months later. The OSG attributed the delay to the inadvertence of a temporarily designated OIC, who allegedly noted receipt but did not realize the decision was adverse to PEZA, and to the scarcity of lawyers in its division.

The Court reiterated that an appeal must be perfected within the reglementary period, and that a Rule 45 petition must be filed within fifteen (15) days from notice of the judgment or final order. It recognized that government counsel should act with promptness and utmost diligence and that such neglect generally binds a party. Nonetheless, the Court decided to overlook the procedural lapse because substantial justice required it, especially where an unchecked decision would effectively sanction a violation of substantive law.

Governing Standards for Injunction

The Court discussed that injunction directs a party to either do a particular act (mandatory injunction) or refrain from doing it (prohibitory injunction). As a main action, injunction seeks a permanent restraint through a final injunction in the judgment. Under Section 9, Rule 58 of the 1997 Rules of Civil Procedure, two requisites had to concur for injunction: (1) a right to be protected, and (2) acts violative of that right. In actions involving realty, the plaintiff generally had to establish title or right for preliminary relief, and injunction would not issue to protect a right not in esse.

PEZA’s Authority vs. Respondents’ Reliance on CALC

The Court held that the RTC and CA misapplied the nature and extent of rights conferred by a CALC. The Court emphasized that PEZA did not assert an adverse claim over the subject land and did not dispute that respondents held building and fencing permits. The question was whether respondents could build within PEZA-BCEZ based on their CALC and the permits.

The Court relied on PEZA v. Borreta (G.R. No. 142669, March 15, 2006), where CAR-CALC-022 had been invoked by Benedicto Carantes to construct structures in a case involving the same CALC. There, the Court refused to recall a writ of demolition and held that the applicant for a certificate of ownership of ancestral land had not acquired a vested right as owner sufficient to exclude land from PEZA areas. The Court found no reason to depart from that ruling and treated respondents as similarly situated because, as holders of a CALC, they possessed no greater rights than those recognized under DENR Department Administrative Order (DAO) No. 02, Series of 1993, particularly Section 2 on the Rights and Responsibilities of Ancestral Land Claimants.

The Court explained that Section 2 grants only limited rights, including the right to peacefully occupy and cultivate the land and to utilize natural resources subject to existing laws, rules, and regulations. It contrasted ancestral land claimants’ rights with those of ancestral domain claimants who, under DENR DAO No. 02, Series of 1993 and Par. 1, Section 1 of Article VII, may have broader rights that include residing peacefully within the domain. The Court concluded that Section 2 did not authorize ancestral land claimants to build permanent structures, an act of ownership that pertains to a recognized right arising from a certificate of ancestral land title.

Even assuming respondents established ownership, the Court further held that they could not fence or build without complying with applicable laws and regulations, particularly the National Building Code.

Necessity of Building and Fencing Permits Under the National Building Code

The Court cited Section 301 of P.D. No. 1096, which required any person, including government agencies, to obtain a building permit before erecting, constructing, altering, repairing, moving, converting, or demolishing any building or structure. It also required that a fencing permit be secured from the Building Official concerned before fences may be installed.

The Court then addressed PEZA’s insistence that its own building officials, not the local building officials of Baguio City, administered the National Building Code provisions in areas owned and administered by PEZA. It relied on Section 205 of P.D. No. 1096 on the general responsibility of Building Officials and recognized that the law allowed designation by the Secretary due to service exigencies. However, the Court explained that PEZA’s specialized regime governed the administration and enforcement of the National Building Code within its areas, as this was maintained and not repealed.

The Court traced the legal framework: P.D. No. 1716 amended P.D. No. 66, and R.A. No. 7916 evolved EPZA into PEZA. The Court referenced Executive Order No. 282 of October 30, 1995, which assumed EPZA functions by PEZA insofar as consistent with PEZA’s powers. Among those functions was the administration and enforcement of the National Building Code in zones and areas owned or administered by EPZA, expressly provided in Section 6 of P.D. No. 1716. The Court quoted Section 6, holding that administration and enforcement of P.D. No. 1096 in all zones and areas owned or administered by the Authority vested in the Administrator or his duly authorized representative, who would appoint EPZA-qualified personnel as Building Officials charged with issuing building permits, and that the fees collected would accrue to the Authority.

Complementing this, the Court invoked Section 14(i) of R.A. No. 7916, which empowered the Director General to require owners to remove or demolish houses, buildings, or structures constructed without the necessary permit. The provision authorized removal or demolition at the expense of the owner upon failure to act within sixty (60) days.

Fencing Permits on Ancestral Lands Within PEZA Areas

The Court recognized that fencing permits on ancestral lands generally depended on DENR rules, specifically DENR-Circular No. 03-90. It noted that the circular provided, in Section 12, that the Special Task Force could recommend to the City/Municipal Mayor’s Office issuance of a fencing permit over areas actually occupied at the time of filing. The Court treated this as the general rule.

However, the Court held that within the premises of PEZA, fencing and building permits had to align with the Authority’s building-permit administration. It

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.