Case Summary (G.R. No. 239315)
Factual Background — Contract Performance and Downpayment
DPCC completed Phase 1 without issue. CCP paid DPCC a downpayment of P14,880,000.00 (12% of Phase 2’s P124,000,000.00) by check dated March 14, 2002. By July and November 2003, Phase 2 progress lagged: CCP’s audits showed 47% completion by July 25, 2003 and about 51% by November 6, 2003, well behind schedule. CCP sent notice letters (October 29, 2003 and November 6, 2003) informing DPCC (and PCIC) of breach/default and advising it would claim on the construction bonds. CCP later terminated DPCC’s contract in a November 21, 2003 letter and proceeded to engage another contractor.
Procedural History — Arbitration and Judicial Review
CCP filed a complaint with request for arbitration before CIAC on October 28, 2004, seeking enforcement of the three bonds for a total of P13,924,351.47 plus interest and attorney’s fees. CIAC rendered an award on June 3, 2005 in favor of CCP, finding DPCC and PCIC jointly and severally liable for P13,924,351.47 but also awarding DPCC P4,232,264.12 for materials and equipment left at the site; net award to CCP was P9,692,087.37. All parties appealed to the Court of Appeals, which consolidated the appeals and, on June 29, 2007, affirmed CIAC with modification: it deleted the award in favor of DPCC for materials and equipment and ordered PCIC and DPCC jointly and severally to pay CCP P13,924,351.47 with prescribed interest. PCIC filed a motion for reconsideration which the CA denied; PCIC then brought a petition for review on certiorari under Rule 45 to the Supreme Court.
Issues Presented by Petitioner (PCIC)
PCIC framed three principal issues: (1) whether the CA erred in sustaining CIAC’s award finding PCIC liable under the performance and surety bonds; (2) whether the CA erred in upholding CCP’s right to terminate the contract; and (3) whether the CA erred in deleting DPCC’s counterclaim for materials, equipment, formworks and scaffoldings and in denying PCIC any benefit from that counterclaim.
Judicial Admission and Bond PCIC‑46172
PCIC argued that Performance Bond PCIC‑46172 (P692,890.74) had been satisfied and should not be collectible. The record of the CIAC hearing contains a clear verbal statement by CCP’s president that CCP was "no longer interested" in collecting on Bond 46172 because the works covered by that bond had been completed and a Certificate of Acceptance existed. The Tribunal treated this as a judicial admission under Section 4, Rule 129 of the Rules of Court. The Supreme Court accepted that CCP’s express waiver before the arbitral tribunal constituted a binding judicial admission, precluding CCP from later pursuing payment under Bond 46172. Consequently, CCP’s claim was confined to Surety Bond PCIC‑45542 and Performance Bond PCIC‑45541, and the amount collectible from PCIC was reduced accordingly.
Accrual of Cause of Action and Notice Requirement under the Bonds
PCIC contended DPCC’s default occurred as early as September 4, 2003 and that CCP’s notice (October 29, 2003 and November 6, 2003) was untimely vis‑à‑vis bond provisions requiring claims in writing within ten (or fifteen) days from expiration or from occurrence of default. The Court applied Article 1169 of the New Civil Code: delay (default) commences from the time the obligee judicially or extrajudicially demands performance. The Court held DPCC’s culpable delay did not accrue simply by lapse of time but began when CCP extrajudicially demanded fulfillment of the obligation by written notice — here, the October 29, 2003 letter. Thus CCP’s November 6, 2003 written notice complied with the bonds’ claim provisions. The subsequent December 5, 2003 extension approved by PCIC was communicated after CCP’s October 29, 2003 notice and therefore did not defeat CCP’s timely claim.
Nature and Operation of Surety Liability
The Court reiterated established principles of suretyship: a surety’s undertaking is accessory to the principal obligation but, upon the principal’s default, the surety is directly and solidarily liable with the principal (Art. 2047, New Civil Code). The surety’s liability is triggered by the obligor’s default and, where bonds are callable on demand, the surety must perform as agreed once default and proper claim notice occur. The Court therefore affirmed PCIC’s duty to respond under the remaining enforceable bonds for DPCC’s default, subject to the contractual and procedural limitations expressly contained in the bond instruments and the parties’ admissions.
CCP’s Termination of the Contract
The Court upheld the CA’s conclusion that CCP was legally justified in terminating the contract. The parties’ contract expressly granted the owner the right to terminate after fifteen days’ written notice for substantial failure of the contractor to fulfill its obligations (Article 16). Given DPCC’s inexcusable delay and the record of partial completion (around 51% as of November 2003), CCP’s declaration of default and termination fell within the contractual termination clause and was legally effective.
Deletion of DPCC’s Counterclaim for Materials and Equipment
CIAC had awarded DPCC P4,232,264.12 for materials and equipment allegedly left at the site; the CA deleted this award for insufficient proof. The Court affirmed deletion. It explained that actual or compensatory damages must be pleaded and proved with a reasonable degree of certainty using competent evidence (receipts, delivery vouchers, etc.). Although DPCC presented supplier receipts, it failed to establish that those items corresponded to the materials and equipment left at the work site. Self‑serving statements without corrobo
Case Syllabus (G.R. No. 239315)
Case Caption, Procedural Posture and Relief Sought
- Case citation: 682 Phil. 507, THIRD DIVISION, G.R. Nos. 180631-33, February 22, 2012.
- Nature of proceedings: Petition for review on certiorari under Rule 45 of the 1997 Rules of Civil Procedure, challenging the June 29, 2007 Decision and November 19, 2007 Resolution of the Court of Appeals in consolidated CA-G.R. SP Nos. 90361, 90383 and 90384.
- Parties: Philippine Charter Insurance Corporation (PCIC) — petitioner; Central Colleges of the Philippines (CCP) and Dynamic Planners and Construction Corporation (DPCC) — respondents.
- Relief sought by petitioner (PCIC): Review and reversal of CA ruling which affirmed and modified the CIAC award finding PCIC liable under certain surety and performance bonds and upholding CCP’s termination of the contract; relief also sought regarding deletion by the CA of DPCC’s counterclaim and non-recognition by PCIC of benefit from that counterclaim.
Facts — Contract, Scope of Work, and Bonds Posted
- On May 16, 2000, CCP contracted DPCC as general contractor for a five-storey school building (No. 39 Aurora Boulevard, Quezon City) with total contract price of P248,000,000.00; construction to be done in two phases, each phase valued at P124,000,000.00.
- DPCC posted three bonds issued by PCIC to guarantee fulfillment: (1) Surety Bond No. PCIC-45542 dated June 25, 2003 in the amount of P7,031,460.74; (2) Performance Bond No. PCIC-45541 in the amount of P2,929,775.31 which was later increased to P6,199,999.99 by Bond Endorsement No. E-2003/12527; (3) Performance Bond No. PCIC-46172 for P692,890.74.
- All three bonds were callable on demand and set to expire on October 30, 2003.
Facts — Performance, Downpayment, Delays, and Termination
- Phase 1 of the project was completed without issue.
- CCP paid DPCC P14,880,000.00 (12% of P124,000,000.00) by check dated March 14, 2002 as downpayment for Phase 2.
- Phase 2 experienced numerous delays; CCP audit on July 25, 2003 found only 47% of work completed. CCP later reported 51% completion on November 6, 2003.
- CCP notified DPCC and PCIC by letter dated October 29, 2003 of breach and its plan to claim on the construction bonds, and on November 21, 2003 formally terminated the contract for DPCC’s inability to complete the project on time and demanded remittance of bond proceeds.
- PCIC approved DPCC’s request for extension of the bonds by letter of December 5, 2003; however, extension was communicated after CCP’s October 29, 2003 Notice of Default.
- Negotiations failed and CCP hired another contractor; on August 13, 2004 CCP made a final demand to PCIC for P13,924,351.47 as indicated in the bonds. PCIC denied CCP’s claims on August 20, 2004.
CIAC Proceedings — Complaint, Claims, and Counterclaims
- On October 28, 2004, CCP filed a complaint with request for arbitration before the Construction Industry Arbitration Commission (CIAC) against DPCC and PCIC.
- CCP sought: (1) P7,031,460.74 under Surety Bond No. 45542 plus legal interest from date of demand; (2) P6,892,890.73 under Performance Bond Nos. PCIC-45541 (as endorsed) and PCIC-46172 plus legal interest; and (3) Php100,000.00 attorney’s fees.
- DPCC and PCIC denied liability and counterclaimed that CCP unlawfully withheld materials, equipment, formworks and scaffoldings left at the premises amounting to P4,232,264.12.
CIAC Decision (June 3, 2005) — Findings and Award
- CIAC findings:
- CCP was legally justified in terminating the contract.
- No record that DPCC protested certain claimed delays or sought contractual adjustments; reduction of downpayment was acquiesced by DPCC.
- DPCC’s percentage of accomplishment at termination was computed at 57.33% (P71,089,200).
- Adjusted contract price after Variation Order No. 2 was P137,857,814.87; after deductions CIAC found an overpayment to DPCC of P27,779,022.00 but limited CCP’s award to amounts claimed in complaint/terms of reference.
- DPCC failed to prove non-payment of Phase 1 balance.
- PCIC as surety was liable to indemnify CCP for unrecouped downpayment not exceeding P7,031,460.74 (Surety Bond) and not more than P6,892,890.73 (Performance Bonds).
- PCIC could seek indemnity from DPCC for amounts it paid.
- Claims were not time-barred; estoppel did not bar PCIC; bond extensions had no adverse legal effect on parties’ rights and obligations; contractual time-bar in bonds valid and binding.
- DPCC was entitled to P1,732,264.12 for materials and P2,500,000.00 for equipment/formworks/scaffoldings left at the site.
- Claims for moral, exemplary and temperate damages and attorney’s fees denied; parties to bear their own costs of arbitration.
- CIAC award (fallo): Joint and several liability of DPCC and PCIC to pay CCP P7,031,460.74 (Surety Bond) and P6,892,890.73 (Performance Bond) totaling P13,924,351.47; CCP ordered to pay DPCC P4,232,264.12; net amount of P9,692,087.37 payable by DPCC to CCP with interest (6% from date of award, 12% from finality) and joint and several liability of PCIC accordingly reduced to P9,692,087.37; indemnity rights and 21% interest on indemnity under indemnity agreement referenced; other claims denied.
Appeals to the Court of Appeals and Consolidation
- All parties appealed the CIAC decision to the Court of Appeals: PCIC’s appeal docketed as CA-G.R. SP No. 90361, CCP’s as CA-G.R. SP No. 90383, DPCC’s as CA-G.R. SP No. 90384; the cases were consolidated.
- The Court of Appeals rendered a decision on J