Title
Pan Pacific Service Contractors, Inc. vs. Equitable PCI Bank
Case
G.R. No. 169975
Decision Date
Mar 18, 2010
Pan Pacific sued Equitable PCI Bank for unpaid price adjustments and damages after project completion; Supreme Court upheld 18% interest rate per contract, reversing CA's 12% decision.
A

Case Summary (G.R. No. 169975)

Parties, Contract Setting, and Applicable Legal Provisions

Pan Pacific was engaged in contracting mechanical works on airconditioning systems. On 24 November 1989, Pan Pacific, through its President Del Rosario, entered into a contract of mechanical works with respondent for P20,688,800. The parties further agreed on nine change orders totaling P2,622,610.30, making the total consideration for the project P23,311,410.30. The contract provided for a price adjustment in case of increase in labor costs and prices of materials under paragraphs 70.1 and 70.2 of the contract’s “General Conditions for the Construction of PCIB Tower II Extension” (the escalation clause).

Factual Background: Escalation Claim and the Promissory Note

Pan Pacific commenced the mechanical works at the PCIB Tower II extension site in Makati City. The project was completed in June 1992 and was accepted by respondent on 9 July 1992. In 1990, labor costs and material prices escalated beyond prior levels. On 5 April 1991, in accordance with the escalation clause, Pan Pacific claimed a price adjustment of P5,165,945.52. Respondent’s project engineer, TCGI Engineers, asked for a reduction. As an act of goodwill, Pan Pacific reduced its claim to P4,858,548.67.

On 28 April 1992, TCGI Engineers recommended that the price adjustment be pegged at P3,730,957.07, basing the evaluation on labor indices of the Department of Labor and Employment, a National Statistics Office price index, PD 1594 and its implementing rules as amended on 15 March 1991, shipping documents submitted by PPSCI, and sub-clause 70.1 of the general conditions. Pan Pacific argued that with that recommendation respondent was estopped from disclaiming liability of at least P3,730,957.07 under the escalation clause. Despite repeated demands, respondent withheld payment of the price adjustment.

Faced with a lack of operational capital due to extraordinary increases in labor and materials, Pan Pacific agreed—against its will and based on respondent’s promise that the price adjustment would be released soon—to execute a promissory note for a P1.8 million loan, and to post a surety bond. The P1.8 million was released directly to laborers and suppliers, and none was given to Pan Pacific. As Pan Pacific demanded the release of the price adjustment, respondent continued to promise release but did not do so, while the loan matured and respondent demanded payment plus interest and penalty. Pan Pacific refused to pay the loan, contending that it would not have incurred it if respondent had released the price adjustment on time. It also asserted that the promissory note did not express the true agreement of the parties; it maintained that the P1.8 million should be considered an advance payment on the price adjustment, so there was no consideration for the promissory note and it was therefore null and void from the beginning.

Dispute Before Suit: Offset and Refusal of Extrajudicial Settlement

Respondent maintained it would not release any portion of the price adjustment to Pan Pacific but would instead offset the price adjustment against Pan Pacific’s outstanding balance of P3,226,186.01, representing the loan, interests, penalties, and collection charges. Pan Pacific refused the offsetting. Still, Pan Pacific agreed to an extrajudicial settlement by receiving the reduced amount of P3,730,957.07 recommended by TCGI Engineers, less P1.8 million and P414,942 as advance payments.

Trial Court Proceedings: RTC Declaration of Nullity and Monetary Awards

On 6 May 1994, petitioners filed a complaint for declaration of nullity/annulment of the promissory note, sum of money, and damages before the Regional Trial Court of Makati City, Branch 59 (RTC). On 12 April 1999, the RTC ruled in favor of petitioners. It declared the promissory note (Exhibit “B”) null and void. It ordered respondent to pay: P1,389,111.10 as the unpaid balance of the adjustment price, with interest at the legal rate of twelve percent (12%) per annum starting 6 May 1994 (the date of filing) until fully paid; P100,000.00 as moral damages; P50,000.00 as exemplary damages; and P50,000.00 as attorney’s fees. The RTC dismissed respondent’s counterclaim for lack of merit.

Appeals to the CA: Interest Rate and Damages Issues

Both parties appealed. Petitioners partially appealed on the issues of the RTC’s deduction of P126,903.97 from the balance of the adjusted price and the RTC’s award of only 12% interest instead of the bank loan rate of 18% compounded annually beginning September 1992. Respondent appealed the entire RTC decision, arguing that it was contrary to law and evidence, specifically challenging (a) the declaration that the promissory note was void, (b) the award of moral and exemplary damages and attorney’s fees, and (c) the dismissal of its counterclaim.

In the CA Decision dated 30 June 2005, the CA modified the RTC decision only as to the principal amount due. It removed the deduction of P126,903.97, finding it represented the final payment on the basic contract price. Accordingly, the CA ordered respondent to pay petitioners P1,516,015.07, with interest at the legal rate of 12% per annum starting 6 May 1994. Both petitions for reconsideration were denied in a CA Resolution dated 5 October 2005.

The Issue Before the Supreme Court

Petitioners elevated the matter to the Supreme Court, raising a single issue: whether the CA erred in fixing the interest rate at 12% instead of the 18% bank lending rate.

Supreme Court Disposition: No Challenge to the Principal, but Interest Rate Was Erroneously Limited

The Court granted the petition. It noted that respondent did not appeal the CA decision. Consequently, there was no longer any issue as to the principal amount of the unpaid balance of the price adjustment, which the CA correctly computed as P1,516,015.07. The Court therefore treated the only remaining controversy as the interest rate applicable to respondent’s delay in paying the balance.

The Court examined the CA’s reasoning for maintaining 12% interest. The CA held that although the contract provided for interest at the current bank lending rate in case of delay in payment by the owner, the proviso did not authorize petitioners to unilaterally raise the interest rate without respondent’s consent. The CA reasoned that petitioners never informed or sought approval for the imposition of the 18% interest on the adjusted price. It further reasoned that mutuality of contracts would be violated if the interest rate were unilaterally increased. The CA thus maintained the legal rate of 12% per annum from the date of judicial demand.

Petitioners’ Contractual Basis for 18% Bank Lending Rate

Petitioners argued that the contract consisted of two parts, the Agreement and the General Conditions, both of which provided for interest at the bank lending rate on any unpaid amount due under the contract. They emphasized that nothing required respondent’s consent as a condition to charging that interest.

Petitioners specifically invoked Agreement Section 2.5, which stated that if any payment was delayed, the contractor may charge interest at the current bank lending rates, without prejudice to the owner’s recourse to other remedies. They also invoked General Conditions Section 60.10, which stated that upon the owner’s failure to pay within the contract’s periods, the owner shall pay interest at the rate based on banking loan rates prevailing at the time of signing on all sums unpaid from the date by which they should have been paid.

Petitioners contended that, once their entitlement to the price adjustment was established, the bank lending interest rate necessarily followed due to respondent’s delay.

Respondent’s Position: Consultation Required for Adjusted Costs and Imposition of Interest

Respondent, in contrast, argued that under General Conditions 70.1 and 70.2, additional cost due to labor and material escalation would be determined by the engineer and added to the contract price only after due consultation with the owner. Respondent asserted that because there was no prior consultation regarding imposition of the 18% compounded annual interest on the adjusted price, respondent was never consulted or informed of that rate. The CA had adopted this distinction by treating respondent’s consent to the price adjustment liability as different from any consent required for the higher interest rate.

Supreme Court’s Ruling on Contract Interpretation and the Need for Consent

The Supreme Court disagreed with the CA’s added requirement of respondent’s separate consent for the bank lending interest rate. The Court reiterated that the written contract is the formal expression of the parties’ rights, duties, and obligations, and it contains all terms agreed upon. Courts cannot alter a contract by construction or supply stipulations that the parties did not include. Construction is proper only when the contract is vague or ambiguous.

The Court read the escalation clause together with Agreement Section 2.5 and General Conditions Section 60.10, both of which pertained to time of payment and interest upon delay. It stressed that the CA had already settled that petitioners had consulted respondent on the price adjustment and had held respondent liable for the balance of P1,516,015.07. Respondent, having not appealed from that CA determination, was estopped from contesting that factual and legal finding. However, the CA erred by requiring separate consent before respondent could be held liable for interest at the current bank lending rate.

The Supreme Court found that the contract language did not require respondent’s consent for interest at the bank lending rate to attach upon delay. Once the parties agreed to the price adjustment through due consultation in compliance with the escalation clause provisions, the agreement operated as an amendment to the original contract as to the adjusted costs. That amendment generated respondent’s obligation to pay the adjusted costs w

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.