Title
Osmena vs. Commission on Audit
Case
G.R. No. 98355
Decision Date
Mar 2, 1994
A 1985 abattoir contract between Cebu City and HFCCI was declared void by COA for exceeding appropriated funds. A compromise agreement was ruled invalid, holding the responsible officer personally liable. SC upheld COA's decision.

Case Summary (G.R. No. 193897)

Petitioner, Respondent, and Procedural Posture

Petitioner (Mayor Tomas R. Osmena) sought relief from COA rulings that (1) a prior COA indorsement had declared void the abattoir contract and (2) the compromise payment and court judgment based on that contract could not be enforced against the City because the underlying contract was void, making the expenditure the personal liability of the officer who incurred it. HFCCI had sued the City for recovery of work value; the City, after COA’s initial voidance, entered a compromise in favor of HFCCI which the trial court approved and which was executed by garnishment. COA later indorsed that the contract and the compromise were void and personal liability attached to the responsible officer, and denied reconsideration, prompting the present petition.

Key Dates and Chronology

  • April 30, 1985: City Treasurer certified availability of P5,419,180 for the abattoir.
  • Contract executed for P8,368,920 (sum materially exceeding the certified funds).
  • March 13, 1986: Project suspended and contract sent to COA for review.
  • April 24, 1986: HFCCI claimed P2,142,964.29 as value of work done.
  • September 4, 1986: COA 2nd Indorsement declared the abattoir contract void.
  • May 21, 1987: HFCCI filed civil action for recovery.
  • December 15, 1988: City entered a court‑approved compromise paying P1,500,000 to HFCCI.
  • March 8, 1989: Execution and garnishment effected.
  • May 2, 1989 & January 23, 1991: COA issued further indorsements upholding voidness and denying reconsideration.

Applicable Law and Legal Standards

Primary constitutional and statutory bases relied upon by the Court: the COA’s constitutional power to examine, audit and settle public accounts (Art. IX, Sec. 2 of the 1987 Constitution); the Government Auditing Code (P.D. No. 1445), specifically Sec. 85 (no contract involving public funds without appropriation), Sec. 86 (requirement of certification by the proper accounting official as to availability of funds), Sec. 87 (contracts entered in violation are void), and Sec. 103 (personal liability of officers responsible for illegal expenditures). Rules on finality of COA decisions and appeal periods (P.D. 1445 and Administrative Code provisions) and civil law principle that compromises based on illegal antecedent claims are invalid (citing Art. 1422 Civil Code conceptually) were also applied.

Factual Foundation: Fund Certification and Contract Terms

The City Treasurer issued a certificate dated April 30, 1985 stating funds of P5,419,180 were available “for the construction of Cebu City Abattoir.” The contract ultimately executed with HFCCI fixed the total contract cost at P8,368,920 and provided for staggered installments, with only an initial installment expressly certified within the certified availability. The actual agreed contract sum thus exceeded the certified available appropriation by a substantial amount.

COA Determination That the Contract Was Void

COA’s 2nd Indorsement (Sept. 4, 1986) declared the abattoir contract void because the contract’s total cost significantly exceeded the funds certified as available and because the statutory safeguards of P.D. 1445 were not observed. The Court accepted COA’s reasoning: Sec. 85 of P.D. 1445 expressly requires an appropriation before entering contracts involving public funds, and Sec. 86 requires certification by the proper accounting officer that funds are available. Contracts contravening these requirements are void under Sec. 87. The Court emphasized the mandatory nature of the provision and the settled principle that fund availability is indispensable to government contractual liability.

Finality of the COA Ruling and Petitioner's Failure to Appeal

The Court noted that neither the petitioner nor HFCCI appealed the COA ruling within the applicable statutory period, so the COA decision became final and executory pursuant to the procedural provisions of P.D. 1445 and the Administrative Code. The petitioner nonetheless later relied on the COA adjudication in the City’s defense in the civil action, invoking that ruling as an affirmative defense; the Court held that a party who has invoked an adjudicative body’s jurisdiction and favorable rulings cannot later repudiate that jurisdiction to escape consequences, and that petitioner could not now assert lack of jurisdiction or gravely abuse discretion as a ground to invalidate the COA judgment.

Compromise Agreement and Trial Court Judgment

Despite COA’s prior declaration of voidness, the City, through Mayor Tomas Osmena, entered into a compromise agreement with HFCCI (approved by the trial court) for P1,500,000 as full settlement of HFCCI’s claim. Execution was had against City funds. COA subsequently reviewed the compromise and found it to be a derivative of the void contract.

COA’s Rationale That the Compromise Was Void and Ensuing Legal Effect

COA held that a compromise based on an antecedent claim that is unlawful or illegal is itself invalid for illegality and lack of consideration. Because the compromise was rooted in a contract that COA had already declared void and which had become final, the compromise could not give rise to a valid obligation of the City. The COA further observed that allowing the compromise to stand would circumvent constitutional and statutory safeguards and the specific remedy of appealing COA decisions to the Supreme Court within the prescribed period.

Supreme Court’s Analysis: Validity of Compromise and Enforceability

The Court agreed with COA that the trial court’s judgment predicated on the compromise could not ratify or validate an obligation that was void ab initio. A court judgment based on a compromise that has as its antecedent an invalid public contract does not convert an illegal obligation into a valid one insofar as public funds and municipal liability are concerned. Consequentl

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.