Title
National Electrification Administration vs. Mendoza
Case
G.R. No. L-62038
Decision Date
Sep 25, 1985
ORMECO I’s electricity rate hike was contested by IBP, but Supreme Court ruled exclusive jurisdiction over rate approvals rests solely with NEA.
A

Case Summary (G.R. No. L-62038)

Facts and Initiation of the Injunction Suit

On February 20, 1981, ORMECO I sent notices to its electric consumers in Oriental Mindoro stating that, effective March 1, 1981, it would implement increased electricity rates that had been authorized by NEA on February 4, 1981. Responding to the planned implementation, the IBP Oriental Mindoro Chapter, through its officers, filed on March 17, 1981 a petition for injunction docketed as Civil Case No. R-3326 in the Court of First Instance of Oriental Mindoro. The petition sought to prevent the implementation of the increased electric rates.

On the same date, respondent Judge issued a restraining order directing ORMECO I to refrain from enforcing the increased rates.

Trial Court Proceedings and the Shifting of Restraining Orders

On March 26, 1981, ORMECO I filed its Answer, seeking dismissal for insufficient cause of action and/or want of jurisdiction and praying for the lifting or dissolution of the restraining order earlier issued. On April 10, 1981, respondent Judge lifted the restraining order and dismissed the injunction petition.

However, upon the private respondent IBP’s Motion for Reconsideration, respondent Judge reinstated the restraining order previously issued.

On September 4, 1981, NEA filed a Motion for Intervention, which respondent Judge granted on October 23, 1981. NEA then filed a Motion to Dismiss the injunction suit, asserting that the Court of First Instance had no jurisdiction over the subject matter, because the matter related to electricity rates charged by a cooperative and was allegedly reserved to NEA’s exclusive jurisdiction.

On December 17, 1981, respondent Judge denied NEA’s Motion to Dismiss. The trial court ruled that it could restrain the implementation of the rates because there had been no public hearing on the proposed rates to be collected from the cooperative’s consumers.

Orders Assailed Through Further Proceedings

After these developments, and upon motion of IBP Oriental Mindoro Chapter, respondent Judge issued additional orders: one dated March 3, 1982 directing the Provincial Auditor to assist in examining the records of ORMECO I to determine whether the cooperative was losing, with findings to be submitted to the court; and another dated March 10, 1982 fixing the rate at P1.72/kwh. These actions culminated in the filing of the petition for certiorari before the Supreme Court, questioning the trial court’s jurisdiction and the validity of the challenged orders.

Parties’ Contentions Before the Supreme Court

The petitioners argued that the trial court had no jurisdiction at all to act on the case and issued orders in excess of its authority. The private respondents maintained that the Court of First Instance possessed jurisdiction over the injunction suit because the consumers allegedly suffered denial of due process owing to the absence of any public hearing conducted regarding the reasonableness of the proposed increases in electric light rates.

Administrative Exhaustion and the President’s Supervisory Power over NEA

The Supreme Court ruled that merit existed in the petition. It held first that IBP should have exhausted the administrative remedies still available by appealing the challenged order of NEA approving the increased rates to the President of the Philippines, who exercised supervisory power over NEA. The Court relied on Section 13 of the Organic Law of NEA, as found in P.D. No. 269, which provides that NEA is under the supervision of the Office of the President and that all orders, rules and regulations promulgated by NEA are subject to the approval of the Office of the President.

Because the President had power to review, on appeal, the acts or orders of NEA, the Court held that the private respondent’s failure to take such an appeal barred it from resorting to a judicial suit. The Court cited Tan vs. Director of Forestry, 125 SCRA 205, for the rule that administrative remedies must be exhausted before resort can be had to the courts.

The Court Rejected the Due Process/Public Hearing Argument as Unavailing

The Court also rejected the private respondents’ theory that P.D. No. 269 did not empower NEA to approve a cooperative’s rate increases without public hearing. It reasoned that the consumers were members of ORMECO I, a non-profit organization, and that the consumers or members were already represented by the Board of Directors elected by them. On that basis, the Court viewed the necessity of a public hearing as absent.

The Court further found significant that ORMECO I itself solicited NEA approval to adjust rates upward and that NEA granted the adjustment as necessary for ORMECO I’s continued financial viability. The Court noted that it was undisputed that NEA was the creditor of the electric cooperative, which had obtained a huge loan from NEA on March 27, 1973, and that it was stipulated between NEA and ORMECO I that rates and charges affecting the cooperative would be subject to approval by NEA’s Board of Administrators. Consequently, the Court concluded that the Court of First Instance could not review the rate power independently.

Lack of Jurisdiction of the Trial Court to Review NEA-Approved Rates

The Supreme Court held that the Court of First Instance could not “usurp” for itself the power to review the rate charges of ORMECO I that had been approved by NEA. The Court stated that competence to address such matters had been lodged by law in NEA and not in any other agency or tribunal at that level.

The Court drew support from Pineda vs. Lantin, 6 SCRA 757, 763, where it had ruled that a Court of First Instance could not interfere with an order of a regulatory commission because it could not substitute its judgment for that of the commission. The Court also cited Philippine Pacific Fishing Company, Inc. versus Luna, 112 SCRA 604 (1982), for the proposition that “nowhere does the law empower any Court of First Instance to interfere with the orders of the Commission, not even on grounds of due process and jurisdiction.” It added that the regulatory commission in such contexts, at the very least, was a coequal body with the Court of First Instance, and co-eq

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.