Title
National Power Corp. vs. Vda. de Capin
Case
G.R. No. 175176
Decision Date
Oct 17, 2008
NAPOCOR expropriated 3,199 sqm of land for a power project, paying below market rates. SC upheld summary judgment, ruling P448.33/sqm as just compensation, rejecting easement fees as inadequate.
A

Case Summary (G.R. No. 175176)

Properties, Permits, and Construction

Respondent Santa Loro’s lot: 16,193 sq. m. (Tax Declaration No. 15-22196, 1994). Respondent Spouses Quimco’s lot: 3,298 sq. m. (Tax Declaration No. 31376, 1996). NAPOCOR obtained written “Permission to Enter for Construction of Transmission Line Project” from respondents (14 June 1994 and 11 December 1996) after representing that it would pay just compensation. Construction proceeded and was completed in 1996; the combined area of respondents’ land affected by the project was agreed to be 3,199 sq. m.

Restrictions Imposed and Economic Impact on Respondents

After construction, NAPOCOR imposed restrictions (e.g., prohibition on planting or erecting structures higher than three meters beneath the lines) and barred quarry operations near towers. These restrictions curtailed respondents’ use of the affected land and reduced income, particularly impacting the Quimcos’ small-scale quarry business.

Initial Compensation Paid by Petitioner

NAPOCOR paid nominal amounts as easement fees: P8,015.90 to Santa Loro and P5,350.49 to the Spouses Quimco. Respondents later learned that other landowners whose properties were similarly affected and who resisted or litigated received payments in the range of P448.30–P450.00 per square meter.

Procedural History — Trial Court and Parties’ Positions

Respondents filed a Complaint for rescission of agreement, recovery of possession, removal of towers and lines, damages and other reliefs (Civil Case No. DNA-547). NAPOCOR answered, asserting that Section 3-A of its Charter limits compensation for right-of-way easements to not more than 10% of market value (as declared or as assessed). At pre-trial the parties conceded that only the amount of just compensation for the 3,199 sq. m. was in dispute; respondents moved for summary judgment.

Trial Court Orders, Summary Judgment Process, and Petitioner’s Inaction

The RTC ordered respondents to file a motion for summary judgment and gave NAPOCOR opportunities to oppose and to verify the area taken. NAPOCOR sought, and received, extensions but ultimately did not file opposition or submit the results of its verification. The RTC deemed the motion submitted and, on 16 April 2001, rendered judgment awarding P448.33 per sq. m. (total P1,434,207.67) with interest, later modified by order of 24 August 2001 to reduce interest to 6% per annum from filing and 12% per annum post-judgment.

Appellate Proceedings and Supreme Court Review

The Court of Appeals affirmed the RTC decision (21 April 2006) and denied reconsideration (27 October 2006). NAPOCOR filed a Rule 45 petition to the Supreme Court, raising four primary issues: (1) whether summary judgment was proper for determining just compensation; (2) whether the 3,199 sq. m. area finding was correctly affirmed; (3) whether reliance on an earlier RTC decision (Civil Case No. DNA-379, based on DNA-373) provided a sufficient basis for the P448.33 per sq. m. valuation; and (4) whether Section 3-A of R.A. No. 6395 limits respondents to easement fees only.

Legal Standard for Summary Judgment and Its Application Here

Under Rule 35 (Sections 1 and 3) of the Revised Rules of Civil Procedure, summary judgment requires that (a) no genuine issue as to any material fact exists except as to the amount of damages, and (b) the movant is entitled to judgment as a matter of law. The Court emphasizes that the transition to summary judgment is appropriate where affidavits, admissions, and documents show that factual disputes are not genuine. Here, NAPOCOR admitted taking portions of respondents’ lands but contested only compensation and purportedly the exact area; it failed to present opposition or evidence to create a genuine factual issue despite multiple extensions. The Supreme Court therefore found the RTC’s resort to summary judgment proper because, except for the quantum of damages, no genuine issue of material fact remained.

Area of Land Affected and Timeliness of Contest

The Court held NAPOCOR’s belated contest of the 3,199 sq. m. area was procedurally defective. NAPOCOR had ample opportunity to verify and submit contrary evidence but remained silent. Documents proffered by respondents (including sketch plans) were unrebutted; petitioner’s late contentions and unsigned plans lacked credibility. The Court endorsed the appellate court’s finding that petitioner’s inaction constituted a dilatory tactic and precluded relitigation of the area issue at this stage.

Reliance on Prior RTC Decisions to Fix Valuation

The RTC fixed P448.33 per sq. m. based on an earlier RTC decision in Civil Case No. DNA-379, which itself adopted the Commissioners’ Report in DNA-373 that had recommended P448.333 per sq. m. The Supreme Court accepted that the prior RTC decision, involving adjacent and similarly situated lots affected at roughly the same time, constituted a logical and reasonable evidentiary basis for fixing fair market value in the present case, especially since the valuation was presented to and relied upon by the trial court and petitioner failed to controvert it.

Nature of Taking — Easement vs. Expropriation and Constitutional Just Compensation

Although NAPOCOR argued it acquired only a right-of-way easement and thus was limited by Section 3-A of its Charter to pay up to 10% of market value, the Court treated the right-of-way easement as a taking under the power of eminent domain because the imposed restrictions (indefinite prohibition on certain uses, risk to life and limb, and ongoing tax burden on respondents) effectively and perpetually deprived respondents of ordinary use of the affected land. Citing established jurisprudence, the Court held that such an easement may amount to an expropriation and that constitutional protections under the 1987 Constitution (applicable to this decision) require payment of just compensation equal to the owner’s loss, not merely

    ...continue reading

    Analyze Cases Smarter, Faster
    Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.