Title
National Power Corp. vs. Court of Appeals
Case
G.R. No. L-47379
Decision Date
May 16, 1988
NPC negligently opened spillway gates during Typhoon Welming, causing damage to ECI's equipment. SC upheld liability, reduced damages, and eliminated unrealized bonus and exemplary damages.

Case Summary (G.R. No. 161083)

Key Dates and Contractual Background

  • Contract executed by ECI as successful bidder with National Waterworks and Sewerage Authority (NAWASA) on August 4, 1964, to construct the 2nd Ipo-Bicti Tunnel and appurtenant works, with an 800-calendar-day completion period measured from notice to proceed.
  • By September 1967, ECI had completed the tunnel excavation phase; some outworks at the Bicti site remained under construction.
  • Typhoon “Welming” struck the area on November 4, 1967, producing heavy rains and a rapid rise in the Angat reservoir.

Factual Sequence Leading to the Dispute

  • During the typhoon the reservoir level rose at an observed rate of approximately 60 centimeters per hour and reached a danger height; NPC opened the Angat Dam spillway gates to prevent overflow.
  • ECI’s stockpiles, camp facilities, equipment, materials, and certain structures at the Ipo site were washed away, lost, or destroyed following the release of an extraordinary volume of water from the spillway.
  • ECI submitted itemized proofs of damages and supporting vouchers; NPC did not present documentary evidence to rebut those specific items.

Procedural Posture and Relief Sought

  • Trial court awarded damages to ECI. On appeal, the Court of Appeals (CA) affirmed liability of NPC but reduced certain damage items (notably consequential damages and attorney’s fees) and eliminated exemplary damages.
  • Both parties filed petitions to the Supreme Court: NPC contested liability (arguing force majeure), and ECI contested the CA’s reductions/elimination of certain damages and fees.

Legal Issue(s) Presented

  • Primary legal issue: Whether the losses to ECI were attributable to force majeure (exonerating NPC) or to NPC’s negligent operation of the spillway gates (making NPC liable).
  • Secondary issues: Whether the awards for actual/compensatory damages, consequential damages (including alleged crane rental and lost bonus), exemplary damages, and counsel fees were properly computed and supported.

Court of Appeals and Trial Court Findings on Negligence

  • Both trial court and CA found preponderant evidence that NPC opened the spillway gates in a negligent manner — specifically, that the gates were opened only when the typhoon was at its height even though NPC had prior notice of the typhoon and could have opened the gates earlier and more gradually.
  • The CA concluded NPC’s method of opening the gates (late and not in a regulated manner) caused an extraordinary discharge that struck ECI’s installations with exceptional force.

Supreme Court’s Treatment of Force Majeure versus Contributory Human Agency

  • The Supreme Court applied settled law that an act of God (force majeure) exonerates only where the event is exclusively caused by natural forces and no human negligence contributes to the loss. If human negligence concurs with an act of God in producing the damage, the human actor remains liable.
  • Citing prior jurisprudence (including Nakpil), the Court held that because NPC’s operational choices (delayed and abrupt opening of spillway gates) contributed to the loss, the event was “humanized” and could not be treated as pure force majeure; NPC therefore remained liable.

Standard of Review and Evidentiary Weight

  • The Court reaffirmed that factual findings of the Court of Appeals are generally final and will not be disturbed unless clearly unfounded. A finding supported by substantial evidence — defined as relevant evidence a reasonable mind might accept as adequate to support the conclusion — will be respected.
  • Given the CA and trial court findings on negligence were supported by the record (including the chronology of events and knowledge of the impending typhoon), the Supreme Court declined to overturn the liability determination.

Compensatory Damages: Award and Basis

  • The CA’s award of actual or compensatory damages in the amount of P675,785.31 (itemized into camp facilities, equipment/parts/plant, materials, and permanent structures/accessories) was found to be supported by documentary vouchers submitted by ECI and untraversed by NPC.
  • The Supreme Court affirmed the compensatory damages award, finding no error in the CA’s acceptance of the evidentiary proofs.

Consequential Damages: Reduction and Rationale

  • The trial court had awarded P333,200.00 as consequential damages, which included alleged long-term crane rental expenses (P213,200.00) and an alleged unrealized one-month bonus from NAWASA (P120,000.00).
  • The CA reduced consequential damages substantially after examining the record: it identified a sales contract showing ECI ordered a new crawler-type crane shortly after the flood (purchase price ~P106,336.75 with delivery within 60 days), and evidence that the damaged crane had been repaired at a cost of P77,000.00 and was reactivated. The CA concluded ECI would not have rationally rented a replacement crane for the entire year at P4,000.00 per day given the sale of a new crane and the repair of the old one; consequently the CA limited consequential crane-related damages to the reasonable rental cost for only one month — computed in the record as P19,200.00.
  • The Supreme Court sustained the CA’s reasoning and affirmed the substantial reduction of consequential damages (the Supreme Court text records the reduced consequential damages at approximately P19,000.00), reasoning that to award the larger amount would produce unjust enrichment where the record supported acquisition/repair of equipment and a short actual work stoppage.
  • The Supreme Court likewise rejected the P120,000.00 “bonus” award: the damage occurred long after the contract’s completion period (the incident happened w

    ...continue reading

    Analyze Cases Smarter, Faster
    Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.