Title
National Housing Authority vs. 1st United Constructors Corporation
Case
G.R. No. 176535
Decision Date
Sep 7, 2011
NHA sought to reverse the CA's decision affirming CIAC's award in favor of FUCC for project delays, idle equipment, and costs, but the Supreme Court denied their appeal, ruling the termination was unilateral and upheld the awards.

Case Summary (G.R. No. 176535)

Contractual Background and Implementation

FUCC was awarded the contract for Phase I of the FVR Project after winning a public bidding process on February 26, 1998. Initially, the project aimed to develop 300 hectares into residential lots. Various delays and issues arose, including changes in project scope that required multiple variation orders, ultimately reducing the originally planned home lots and leading to several granted time extensions for FUCC’s completion of the contract. Despite these extensions, by March 15, 1999, the original contract duration, the project remained unfinished, prompting the NHA to terminate the contract, citing a reclassification of the project and underlying issues impacting feasibility.

Claims and Arbitration

Following the termination of the contract, FUCC filed a complaint with the Construction Industry Arbitration Commission (CIAC) on July 17, 2003, seeking payment for several claims including accomplished works not yet billed, idle equipment, price escalation, and disengagement costs. The CIAC issued its decision on January 7, 2004, awarded numerous claims to FUCC, and concluded that the NHA was liable for the delays and suspensions caused by its administrative actions.

Procedural Outcomes

The NHA challenged the CIAC’s decision through an appeal to the Court of Appeals (CA). The appellate court affirmed the CIAC's decision with modifications on August 1, 2006, including adjustments to claims and granting of interests. The NHA subsequently sought a higher review before the Supreme Court, arguing that the CA ignored key facts which could have altered the decision.

Legal Analysis of The Issues Raised

  1. Condition Precedent - Payment Guarantee Bond: The court deliberated whether the absence of a performance bond barred FUCC’s claims. The appellate court concluded that while a bond is a requirement,FUCC’s excuse for not posting was valid given the circumstances surrounding bond issuance which NHA tacitly accepted.

  2. Progress Billing Discrepancies: NHA alleged that the award for Progress Billing No. 6 should only reflect an amount of P6,496,926.29, however, the Court upheld CIAC's award of P7,384,534.22 based on the documentation submitted by FUCC demonstrating the comprehensive work accomplished.

  3. Cost of Materials and Facilities: The CA supported FUCC’s claims for unreimbursed costs associated with materials and facilities instigated by the termination of the contract, representing costs that were reasonable under the conditions of the contract.

  4. Idleness of Equipment: The CIAC's ruling acknowledging the costs associated with idle equipment was maintained as the cessation of work was validated by testimony and concurrent documentation affirming that work could not proceed due to administrative decisions.

  5. Disengagement Costs: The awards for foregone profits stemming from the termination of the contract were found to be justifiable and aligned with construction industry norms, as supported by precedential case law affirming claims for business losses resulting from contract termination.

  6. Nature of Contract Termination: The court concluded that the contract was unilaterally terminated by NHA without the involvement or consent of FUCC, thereby solidifying FUCC’s claims due to the nature of the termination which was entirely within NHA's control based on subsequent i

...continue reading

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources.