Case Summary (G.R. No. L-47851)
Factual Background
The Philippine Bar Association (PBA) constructed an office building on its 840-square-meter lot at the corner of Aduana and Arzobispo Streets, Intramuros, Manila. The building was designed by Juan F. Nakpil & Sons and constructed on an "administration" basis by United Construction Co., Inc. on the suggestion of its president, Juan J. Carlos. The building was completed in June, 1966. On August 2, 1968, an unusually strong earthquake caused major damage: several front columns buckled and the structure tilted forward, prompting tenants to vacate. United Construction Co., Inc. performed temporary shoring at a cost of P13,661.28. Subsequent earthquakes in April, 1970 caused further damage and the building was ultimately demolished.
Procedural History in the Trial Court
On November 29, 1968 the PBA sued United Construction Co., Inc. and Juan J. Carlos for damages arising from the partial collapse. Defendants filed third-party complaints against Juan F. Nakpil & Sons and Juan F. Nakpil, and the PBA’s president Roman Ozaeta was impleaded as a third-party defendant. By stipulation of March 3, 1969 the parties agreed that, should the trial show that the contractors were not liable but the plans or the architects were, judgment could be rendered against the Nakpils as if they had been formally made defendants. The trial court referred technical issues to Commissioner Andres O. Hizon, and tried the nontechnical issues itself. The Commissioner was charged to determine causation, apportion contribution of factors, and the cost or feasibility of repair. The trial court, agreeing generally with the Commissioner’s report, rendered judgment on September 21, 1971 ordering United Construction Co., Inc. and the third-party defendants, except Roman Ozaeta, to pay the PBA P989,335.68 with legal interest from November 29, 1968, dismissed claims against Juan J. Carlos, dismissed the third-party complaint, and dismissed counterclaims.
Referral to Commissioner and Technical Findings
The Commissioner conducted a detailed technical inquiry and on September 25, 1970 reported that the August 2, 1968 earthquake was the direct cause of the damage but that the collapse was also substantially attributable to defects in the plans and specifications prepared by the Nakpils, deviations from those plans by the contractor, poor workmanship, and failures of supervision by architects, contractor, and owner. The Commissioner catalogued specific design and construction shortcomings: deficiencies in detailing against torsion, overloaded ground floor columns, inadequate placement and splicing of reinforcement, omitted or improperly spaced spirals and ties in columns, cavities and honeycombing in concrete, contraband construction joints, and eccentric reinforcement assemblies. The Commissioner found that these defects diminished ductility and earthquake-resistance and that the construction defects aggravated the weaknesses in the design.
Trial Court’s Application of the Commissioner’s Report
The trial court adopted the Commissioner's conclusions except insofar as it held that the owner must exercise full-time supervision of construction, which the court found had no contractual or legal basis. The trial court found that the building was not initially a total loss and awarded the PBA P900,000 as the cost of repair together with other incidental relief noted in its decision and order.
Court of Appeals’ Review and Modification
On appeal the Court of Appeals affirmed the trial court’s factual findings that defects in design and deviations in construction contributed to the building’s failure and rejected the defendants’ contention that the earthquake was an excusing act of God. The Court of Appeals modified the trial court judgment by awarding an additional P200,000 in favor of the PBA to cover damage resulting from a subsequent earthquake of April 7, 1970, and ordered that the award be paid jointly and severally by the defendant and third-party defendants, except Roman Ozaeta; in other respects the trial court’s judgment stood affirmed with costs assigned as stated in the appellate disposition.
Issues Presented on Certiorari
The petitions to this Court raised, inter alia, whether the August 2, 1968 earthquake constituted a fortuitous event that excused liability of architect and contractor; whether the findings that defects in plans and departures in construction were proven should be disturbed; whether the additional award of P200,000 was proper; whether United Construction Co., Inc. was entitled to reimbursement for shoring expenses of P13,661.28; whether the Nakpils could properly be held jointly and solidarily liable with the contractor; and whether the measure of damages should be the total value of the building as claimed by the PBA.
Standards on Act of God and Concurrent Negligence
The Court set forth the governing principles: Art. 1723, New Civil Code imposes architect and contractor liability where a building collapses within fifteen years due to defects in plans or defects in construction, and Art. 1174, New Civil Code articulates the general rule on fortuitous events. To invoke the act-of-God exemption under Art. 1174, four requisites must concur: the cause must be independent of the debtor's will; the event must be unforeseeable or unavoidable; the event must render performance impossible in a normal manner; and the debtor must be free from any participation in or aggravation of the injury. The Court reiterated the well-established proposition that where negligence concurs with a fortuitous event in producing loss, the negligent party cannot escape liability.
Application of Law to the Record: Liability Established
Applying the standards, the Court observed that both the trial court and the Court of Appeals had found, on ample evidence and on the uncontradicted Commissioner's technical report, that the Nakpils’ designs contained deficiencies and that the contractor committed substantial deviations and poor workmanship. The Court affirmed that these defects and deviations were proximate causes that rendered the PBA building unable to withstand the earthquake forces and therefore precluded an act-of-God exculpation. The Court emphasized that many other structures in the same area withstood the same earthquake, and that the record supported a conclusion that human negligence, not a purely natural phenomenon, accounted for the collapse.
Assessment of Damages
The Court recounted the trial court’s award based on the Commissioner’s estimate that repair to tenantable condition would cost P900,000 and that unrealized rentals were allowed for a limited period. The Court of Appeals’ addition of P200,000 for subsequent earthquake damage was noted. The PBA sought a larger measure, namely P1,830,000 representing the building’s total value, and also urged continuing recovery of unrealized rentals until satisfaction of judgment. The defendants contested the additional award and the imposition of solidary liability. The Court accepted the finding that the building was initially repairable but that later tremors occasioned further loss; it concluded that liability attached to the Nakpils and to the contractor for the resulting damage.
Allocation of Fault and Solidary Liability
The Court accepted
...continue reading
Case Syllabus (G.R. No. L-47851)
Parties and Procedural Posture
- Philippine Bar Association was the plaintiff below and one of the petitioners in the consolidated appeals seeking recovery for damage to its building.
- United Construction Co., Inc. and Juan J. Carlos were defendants in the principal action and were petitioners in a related certiorari proceeding.
- Juan F. Nakpil & Sons and Juan F. Nakpil were third-party defendants as architects and were petitioners in a related certiorari proceeding.
- The case arose from Civil Case No. 74958 in the Court of First Instance of Manila and was appealed to the Court of Appeals, which rendered a modified judgment on November 28, 1977.
- The petitions before the Supreme Court were consolidated and presented as petitions for review on certiorari from the decision of the Court of Appeals.
Key Factual Allegations
- Philippine Bar Association contracted the construction of an office building on its 840 square meter lot in Intramuros, Manila, with plans prepared by Juan F. Nakpil & Sons and construction undertaken by United Construction Co., Inc. on an administration basis.
- The building was completed in June 1966 and sustained major damage in the unusually strong earthquake of August 2, 1968, with front columns buckling and the structure tilting forward.
- United Construction Co., Inc. performed temporary shoring at its expense in the amount of P13,661.28, and subsequent tremors in April 1970 caused further damage that led to authorization for demolition.
- The plaintiff alleged defects in construction, deviations from plans and specifications, and contractual violations, while defendants filed a third-party complaint against the architects alleging defects in the plans and specifications.
Procedural History
- Technical engineering issues were referred by agreement to a Commissioner, Mr. Andres O. Hizon, who submitted a detailed report after hearings.
- The trial court accepted the Commissioner’s findings in large measure and rendered judgment on September 21, 1971, which was modified by order dated December 8, 1971 and then by the Court of Appeals on November 28, 1977.
- The Court of Appeals affirmed most of the trial court’s findings but added an award of P200,000.00 to Philippine Bar Association for subsequent earthquake damage and affirmed joint and several liability of defendant and third-party defendants except for Roman Ozaeta.
- The consolidated petitions for review on certiorari were taken to the Supreme Court where amici curiae in architecture and engineering were permitted to intervene and to submit position papers.
Issues Presented
- Whether the partial and eventual collapse of the PBA building caused by the August 2, 1968 earthquake constituted an excusing act of God that absolved the contractor and architects from liability.
- Whether the findings of defects in plans and specifications and in construction and workmanship were supported by the evidence and justified imposition of liability.
- The appropriate measure and quantum of damages recoverable by Philippine Bar Association, including repair costs, loss of rentals, additional damage from later earthquakes, and attorney’s fees.
- Whether the Court of Appeals erred in imposing joint and several liability and in awarding an additional P200,000.00 to Philippine Bar Association.
Relevant Law
- Article 1723, New Civil Code governed architects’ and contractors’ liability for collapse of buildings within fifteen years from completion due to defects in plans, specifications, construction, or materials.
- Article 1174, New Civil Code imported the general rule on fortuitous events and acts of God relieving liability when the event is unforeseeable, unavoidable, and the obligor is free from participation in the loss.
- The Court applied settled Philippine precedents that a fortuitous event does not excuse liability when negligence or misconduct of the parties concurs to produce the loss, including Tucker v. Milan and authorities cited in the opinion.
Findings of Fact
- The Commissioner found that the August 2, 1968 earthquake was the direct cause of the damage but that defects and deficiencies in the design and plans prepared by the third-party defendants contributed to the building’s inability to resist seismic forces.
- The Commissioner found substanti