Title
Municipality of Dasmarinas vs. Campos
Case
G.R. No. 232675
Decision Date
Jul 17, 2019
Dr. Campos donated land to NHA, conditional on constructing a 36m road. NHA built only 20m, then donated land to Dasmariñas without notice. Courts revoked donation, citing NHA's noncompliance and bad faith.

Case Summary (G.R. No. 232675)

Factual Background

Dr. Paulo C. Campos was the registered owner of parcels of land in Dasmarinas, Cavite, covered by several Transfer Certificates of Title. On July 28, 1976, he executed a Deed of Donation in favor of the NHA conveying in donation parcels totaling 12,798 square meters on condition that the NHA construct a 36-meter-wide access road from Highway 17 to the Dasmarinas Resettlement Project. The deed expressly stipulated that should the donee fail to use the area for the 36-meter road or delay development, the donor reserved the right to use the property until the donee could use it. The NHA constructed instead a 20-meter-wide access road, claiming reservation of the remaining 16 meters for future widening and citing traffic volume as justification. Without notice to Dr. Campos, the NHA executed a second Deed of Donation and Acceptance on June 13, 1993, transferring the roadworks to the Municipality of Dasmarinas and invoking Section 31 of P.D. No. 957 as authority.

Trial Court Proceedings

On November 13, 2001, Dr. Campos filed an action for Revocation of Donation alleging breach of the condition to construct the 36-meter road and improper subsequent donation of the property to the Municipality of Dasmarinas. The complaint was answered by both petitioners. The case was re-raffled; Dr. Campos died during litigation and his heirs were substituted. On March 16, 2011, RTC, Branch 22, issued a Decision partially granting revocation: it declared the 1976 Deed of Donation partially revoked to the extent of the area not included in the 20-meter road, declared the 1993 Deed of Donation and Acceptance without legal effect to that same extent, adjudged reconveyance of the unused portion to Dr. Campos’ heirs, and ordered turnover of possession. Claims for moral damages and attorney’s fees were denied. The NHA’s motion for reconsideration was denied on August 12, 2011.

Court of Appeals Decision

The NHA and the Municipality of Dasmarinas appealed to the CA. On November 10, 2016, the CA affirmed the RTC Decision. The CA agreed that the 1976 donation was onerous, governed by the law on contracts and subject to the ten-year prescriptive period under Article 1144. The CA held that the respondents’ right of action accrued upon the NHA’s 1993 donation to the Municipality of Dasmarinas, and that the action filed in 2001 was timely. The CA also found that the NHA failed to fulfill the obligation to build a 36-meter road, that the 20-meter construction over more than 25 years constituted a substantial breach, and that invocation of P.D. No. 957, Sec. 31 was unjustified because the Dasmarinas Resettlement Project was not shown to be a subdivision or condominium project. The CA denied the petitioners’ appeal. Motions for reconsideration were denied by CA Resolution dated July 3, 2017.

Issues Presented

The consolidated petitions to the Supreme Court raised two principal issues. First, whether the action to revoke the Deed of Donation had prescribed or was barred by laches. Second, whether the CA erred in affirming the RTC’s factual finding of breach by the NHA and in authorizing partial revocation and reconveyance of the unused 16-meter portion, and whether the petitioners established any legal infirmity warranting reversal.

Petitioners’ Contentions

The petitioners contended that the cause of action accrued when Dr. Campos discovered the NHA had built only a 20-meter road, and thus the action filed in 2001 had long prescribed under Article 1144. They alternatively invoked laches, alleging that Dr. Campos slept on his rights for a quarter century. On the merits, petitioners argued substantial compliance: actual construction of a 20-meter road with the 16-meter portion reserved for future widening meant the condition was effectively met; any delay was contemplated by the 1976 deed which permitted the donor to reserve use of the property until the donee could use it. Petitioners also relied on P.D. No. 957, Sec. 31 to justify the 1993 donation as mandatory upon completion of subdivision or condominium projects.

Respondents’ Contentions

The respondents-heirs maintained that the donation was onerous and governed by contract law; accordingly the ten-year prescriptive period under Article 1144 ran from the 1993 transfer to the Municipality of Dasmarinas, rendering the 2001 complaint timely. They insisted the NHA materially breached the 1976 deed by building only a 20-meter road and by subsequently donating the property, which eliminated any realistic possibility for the NHA to complete the 36-meter road or for the donor to exercise the reserved right. The respondents also argued that the post-1976 transfer omitted the protective reservation clause and thus rendered the original condition impossible to fulfill, justifying revocation and reconveyance.

The Supreme Court’s Disposition

The Court denied the consolidated petitions for lack of merit and affirmed the CA and RTC rulings. The Court held that the 1976 deed was an onerous donation governed by contract law; under Article 1144 the ten-year prescriptive period for actions upon a written contract applies and the respondents’ right of action accrued upon the NHA’s 1993 donation to the Municipality of Dasmarinas. The Court found the 2001 filing within that ten-year period and therefore not prescribed. The Court also ruled that laches did not bar the action because the delay was within the prescriptive period, the donor had permitted the NHA time to perform, and the equitable prerequisites for laches were not satisfied.

Legal Basis and Reasoning on Merits

The Court treated the factual findings of the RTC and CA as binding absent a showing that those tribunals overlooked or misconstrued material facts. The Court agreed that the dispositive object of the 1976 agreement was the construction of a 36-meter-wide access road, repeatedly stipulated in the deed. The Court found a substantial breach when the NHA constructed only a 20-meter road and left 16 meters unused for the stated purpose over a prolonged period. The Court rejected the NHA’s assertion of compliance by reservation of the remaining 16 meters because the deed’s language required actual use for the 36-meter road and because the NHA’s subsequent donation to the Municipality of Dasmarinas removed any practical capacity to complete the condition. The Court further determined that P.D. No. 957, Sec. 31 did not justify the 1993 transfer because the petitioners failed to prove that the Dasmarinas Resettlement Project constituted a subdivision or condominium project as defined in that decree. Thus the second donation could not be excused as mandatory under that statute.

Doctrine on Prescription, Laches, and Substantial Breach

The Court reaffirmed that onerous donations are governed by contract law and that prescription under Article 1144 begins to run when the right to litigate becomes enforceable, which in this case was when the NHA transferred the property to the Municipality of Dasmarinas. The Court reiterated that laches is an equitable defense requiring established elements of unjustified delay and resulting prejudice, and that delay within the pre

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.