Case Summary (G.R. No. 121484)
Factual Background
On July 15, 1982, MEA entered into a construction contract with Capital Resources Corporation (CRC) for the building of housing units in Multinational Village for P39,256,880, payable in cash and negotiable securities, the cash portion to be paid by ninety-day stand-by letters of credit. On August 11, 1982, MEA, CRC and private respondent METROBANK executed a tripartite agreement under which Metrobank would issue stand-by letters of credit to cover the cash portion subject to specified conditions, including certification of completion by contractor and acceptance by owner or owner’s representative, Metrobank representative and the Home Financing Corporation (HFC); minimum letter of credit amounts; domestic, assignable, divisible and irrevocable ninety-day letters of credit; and HFC guarantee secured by real estate mortgages. The construction contract was amended the same day to increase the contract price to P45,552,950.
Related Contracts and Financing
In parallel transactions, Metrobank communicated willingness to finance up to P190 million by letters of credit. MEA asked Metrobank whether letters of credit could issue without the HFC guarantee; Metrobank replied that issuance required the HFC guarantee and was confined to completed units. On January 14, 1983, MEA and CRC executed a separate contract for horizontal development for P7,755,000, excluding filling materials to be advanced by MEA. HFC issued a resolution approving a P120,000,000 cash guarantee on February 11, 1983.
Advances, Promissory Notes and Certificates of Completion
On March 1, 1983, MEA obtained a P3,000,000 advance from Metrobank, secured by a promissory note and a continuing suretyship executed by petitioners Llave, Yu and Yuanlian on March 3, 1983. MEA later completed several housing units and became entitled to P3,330,277.60, which Metrobank applied: P1,500,000 to partially liquidate the advance, P1,253,511.14 to other accounts, and P576,716.45 to MEA’s account, resulting in a new promissory note for the remaining P1,500,000. By May 10, 1983, MEA finished forty-five single detached units supported by certificates of completion signed by CRC, MEA, Metrobank and HFC. On November 4, 1983, MEA suspended operations and Metrobank paid P3,274,263.22 for the forty-five finished units through an irrevocable domestic letter of credit and cash, as evidenced by a certificate of full payment.
Suspension, Demand and Litigation
MEA resumed work on January 31, 1984, but Metrobank advised on February 9, 1984, that construction should be held until CRC sold a substantial number of units to reduce exposure. MEA protested on June 11, 1984, and demanded payment. MEA defaulted on the P1.5 million promissory note due February 6, 1984. On September 25, 1984, Metrobank filed Civil Case No. 8532 in the Regional Trial Court for recovery of the promissory note amount with interest, claiming P1,800,840.
Trial Court Proceedings and Counterclaim
In its answer and compulsory counterclaim, MEA and the other petitioners admitted the promissory note and continuing suretyship but denied liability on the theory that the parties’ real agreement was not a simple loan but an advance-payment scheme tied to the construction agreements and the tripartite arrangement with Metrobank. The trial court on July 18, 1991 accepted the counterclaim and rendered judgment for the defendants: it awarded P18,200,000 as the fair market value of construction work performed by MEA including cost of filling materials, less P1.5 million; P9,000,000 as actual and consequential damages up to April 1984; three percent per month on sums due from May 1984 until full payment; ten percent of all amounts due; and dismissed the plaintiff’s complaint.
Court of Appeals Decision
On appeal, the Court of Appeals reduced the award. The appellate court found that the trial court over-computed the P18,200,000 figure and that Metrobank’s obligation was limited by the tripartite agreement to payment upon completed units certified in accordance with the agreement. The CA relied on the Progress Report dated January 18, 1983 to conclude that one hundred twenty units were built and that Metrobank had already paid for forty-five of those units in the amount of P3,274,263.82 (Exh. M). The CA also held that Metrobank was not liable for the horizontal project P7,755,000 because Metrobank was a stranger to that agreement, and that the cost of filling materials was chargeable to CRC. The CA therefore directed Metrobank to pay MEA P6,308,484.54 representing the value of the units in Exh. 20 less P3,274,263.22 and less the P1.5 million promissory note, the latter to bear twenty-six percent per annum interest and twelve percent per annum penalty, and awarded costs against the appellants. The CA deleted the P9,000,000 compensatory damages and denied attorney’s fees. The CA denied reconsideration on August 11, 1995.
Issues Presented in the Petition for Review
Petitioners raised three principal assignments of error: that the Court of Appeals misapprehended documentary evidence and erred in fixing the value of work at P6,308,484.54 and in denying actual and compensatory damages; that the CA erred in denying attorney’s fees despite litigating to protect rights against Metrobank’s action; and that the CA erred in allowing Metrobank interest and penalty charges on the promissory note. Petitioners sought review under Rule 45.
Standard of Review and Exceptions
The Supreme Court noted that under Rule 45 it may review only questions of law and generally cannot reweigh factual findings of the trial court or the Court of Appeals. The Court recalled recognized exceptions permitting review of appellate factual findings when, among other grounds, such findings are contradictory to the trial court, rest on speculation, are manifestly mistaken, or when the judgment is premised on a misapprehension of facts, citing the jurisprudence set out in the petition record.
Supreme Court Analysis of the Factual Findings
The Supreme Court found that the Court of Appeals’ factual findings had a sufficient basis in the record and that no exception to the limitation on reexamination of facts obtained. The Court agreed with the Court of Appeals that Metrobank’s obligation was confined to the terms of the tripartite agreement and that issuance of letters of credit depended on certification of completed units by the contractor and acceptance by the owner or owner’s representative, Metrobank representative and HFC. The Court observed that the Progre
...continue reading
Case Syllabus (G.R. No. 121484)
Parties and Posture
- MEA Builders, Inc., Vicente Llave, Ernesto Yu, and Angel Yuanlian filed a petition for review under Rule 45 from the decision of the Court of Appeals in CA-G.R. No. 40146.
- Metropolitan Bank and Trust Company was the private respondent and plaintiff below in Civil Case No. 8532 before the Makati Regional Trial Court, Branch 147.
- The trial court rendered judgment for the defendants on counterclaim on July 18, 1991, and the Court of Appeals modified that judgment on August 30, 1994.
- The petitioners assailed the Court of Appeals' reduction of the counterclaim award and its denial of compensatory damages and attorney's fees, and contested the imposition of interest and penalties on the promissory note.
Key Facts
- MEA Builders, Inc. executed a July 15, 1982 construction contract with Capital Resources Corporation for P39,256,880 payable in cash and negotiable securities, with the cash portion payable by 90-day stand-by letters of credit.
- On August 11, 1982, MEA, CRC, and Metrobank entered into a tripartite agreement conditioning issuance of letters of credit on completion of houses/townhouses/duplexes as attested by a Certificate of Completion and requiring an HFC guarantee.
- The July 15, 1982 contract was amended on August 11, 1982 to increase the contract price to P45,552,950.
- On January 14, 1983, MEA and CRC executed a separate horizontal development contract for P7,755,000 with filling materials to be advanced by MEA and reimbursed by CRC.
- HFC approved a P120,000,000 cash guarantee by resolution dated February 11, 1983.
- Metrobank advanced MEA P3,000,000 on March 1, 1983, secured by a promissory note and a suretyship executed by petitioners Llave, Yu, and Yuanlian.
- By May 10, 1983, MEA completed 45 single detached units and Metrobank paid P3,274,263.22 for those units by letter of credit and cash.
- MEA suspended operations on November 4, 1983, resumed on January 31, 1984, and Metrobank advised suspension on February 9, 1984 to reduce exposure.
- MEA defaulted on the P1,500,000 promissory note matured February 6, 1984, and Metrobank filed Civil Case No. 8532 on September 25, 1984 to recover the loaned amount and interest.
Contracts and Documents
- The July 15, 1982 construction contract and its August 11, 1982 amendment are central contractual documents in the dispute.
- The August 11, 1982 tripartite agreement among MEA, CRC, and Metrobank imposed explicit conditions for issuance and payment under the letters of credit.
- Progress Reports dated January 18 and January 20, 1983 documented work accomplished and formed the basis of the valuation of constructed units.
- The P3,000,000 advance was evidenced by a promissory note and a suretyship agreement executed by petitioners.
- Exhibit M (certificate of full payment) evidenced Metrobank's payment of P3,274,263.22 for 45 units and was relied upon by the appellate court.
Trial Court Ruling
- The trial court held that the promissory note for P1,500,000 was not a simple loan but part of the advance-payment scheme and found for the defendants on counterclaim.
- The trial court awarded P18,200,000 as the fair market value of construction work performed including cost of filling materials, less the P1,500,000 promissory note.
- The trial court awarded P9,000,000 as actual and consequential damages up to April 1984.
- The trial court awarded three percent per month interest on the sums