Title
MCMP Construction Corp. vs. Monark Equipment Corp.
Case
G.R. No. 201001
Decision Date
Nov 10, 2014
MCMP leased equipment from Monark, defaulted on payments, and was sued. Courts upheld Monark's claim but reduced excessive interest, penalties, and attorney’s fees. Secondary evidence of the contract was allowed.

Case Summary (G.R. No. 201001)

Factual Background

Monark Equipment Corp. leased five pieces of heavy equipment to MCMP Construction Corp. under a Rental Equipment Contract in 2000. Delivery to MCMP project sites in Tanay, Rizal and Llavac, Quezon was evidenced by invoices and Document Acknowledgment Receipts Nos. 04667 and 5706, signed by MCMP representatives Jorge Samonte on December 5, 2000 and Rose Takahashi on January 29, 2001. The invoices contained payment and penalty stipulations including payment within thirty days, interest at 24% per annum, a collection fee of 1% compounded monthly, a 2% per month penalty for late payment, and stipulated attorney’s fees equal to 25% of any amount due. MCMP failed to pay within the thirty-day period and made partial payments of PhP100,000.00 on April 15, 2001 and PhP100,000.00 on August 15, 2001. As of April 30, 2002, the unpaid balance claimed by Monark totaled PhP1,282,481.83.

Trial Court Proceedings

On June 18, 2002, Monark Equipment Corp. filed a suit for sum of money against MCMP Construction Corp. in the RTC. MCMP answered and alleged premature suit and asserted an oral agreement limiting charges to actual equipment usage, an agreement not reflected in the written Contract. At trial, Monark presented Reynaldo Peregrino, its Senior Account Manager, who testified that one original copy of the Contract retained by Monark was lost and that a photocopy was offered. MCMP objected to secondary evidence but failed to produce its own copy of the Contract despite a court directive. On November 20, 2007, the RTC rendered judgment for Monark in the amount of PhP1,282,481.83 inclusive of interests, and awarded attorney’s fees equal to 25% of the total amount plus costs. By Order dated April 28, 2008, the RTC clarified that interest, charges, and fees accruing after April 30, 2002 should be computed in accordance with the invoice stipulations.

Appellate Proceedings

MCMP Construction Corp. appealed to the Court of Appeals. The CA, by Decision dated October 14, 2011, affirmed the RTC Decision and Order in toto. MCMP’s motion for reconsideration before the CA was denied in a Resolution dated March 9, 2012. Thereafter MCMP filed the petition for review under Rule 45 before the Supreme Court.

Issues Presented

The principal issue was whether the CA erred in admitting secondary evidence in lieu of the original Contract under the Best Evidence Rule as embodied in Rule 130, Sec. 3, 5, and 6. Ancillary issues included whether the equipment had been delivered to MCMP and whether the contractual stipulations on interest, penalty, collection fee, and attorney’s fees were unconscionable and subject to judicial reduction.

Petitioner's Contentions

MCMP Construction Corp. contended that the CA should have excluded the photocopied Contract under the Best Evidence Rule because Monark failed to show diligent search for the original. MCMP alleged that Monark did not present the document’s custodian, did not report the loss to management or the police, and only searched for the original for purposes of litigation. MCMP further disputed delivery of the equipment and denied that the Contract presented was the one it entered into.

Respondent's Position

Monark Equipment Corp. maintained that its original copy of the Contract was lost despite diligent efforts to locate it and that it properly presented a photocopy and other records to prove the transaction. Monark relied on the testimony of its witness Peregrino and on the invoices and receipts. Monark also stressed that MCMP failed to produce its own copy of the Contract despite the court’s directive.

Court's Findings on the Admissibility of Secondary Evidence

The Court applied Rule 130, Sec. 3, 5, and 6, and the requisites articulated in Country Bankers Insurance Corporation v. Lagman for the admissibility of secondary evidence. The requisites are proof of the existence or due execution of the original, proof of loss or valid reason for non-production, and lack of bad faith by the offeror. The Court found that the RTC and the CA properly credited Peregrino’s uncontroverted testimony that Monark’s original Contract was lost and that diligent efforts to locate it were futile. The Court declined to disturb the trial court’s credibility findings, observing that assessment of witness credibility is primarily for the trial court.

Court's Assessment of MCMP's Failure to Produce Its Copy and the Resulting Presumption

The Court noted that MCMP did not produce its copy of the Contract despite a trial court order. The Court held that MCMP’s failure not only justified Monark’s presentation of secondary evidence under Rule 130, Sec. 6, but also gave rise to the disputable presumption adverse to MCMP under Rule 131, Sec. 3(e) that willfully suppressed evidence would be unfavorable to the suppressing party.

Court's Assessment of Delivery of the Equipment

The Court observed that MCMP’s own witnesses, Jorge Samonte and Engr. Horacio A. Martinez, Sr., acknowledged delivery of the equipment to the project sites. The Court concluded that MCMP’s denial of delivery was false and that the factual findings of the trial court on delivery were supported by the record.

Court's Assessment of Interest, Penalty, Collection Fee, and Attorney's Fees

The Court recognized that the invoice stipulations resulted in an effective interest and penalty burden of approximately 60% per annum together with attorney’s fees of 25% of the total debt. The Court found these rates to be exorbitant and unconscionable. Citing Macalinao v. Bank of the Philippine Islands and Pentacapital Investment Corporation v. Mahinay, the Court applied equitable reduction principles under Art. 1229 and Art. 2227 of the Civil Code. The Court reduced the stipulated interest from 24% per annum to 12% per annum. The Court reduced the combined penalty and collection charge from 3% per month (36% per annum) to 6% per annum. The Court reduced attorney’s fees from 25% to 5%. Interest and the reduced penalty and collection charge were ordered to be computed from March 1, 2001, thirty days after receipt of the second set of invoices.

Disposition

The petition was denied for lack of merit with modification of the RTC’s dispositive portion. The modified judgment ordered MCMP Construction Corp. to pay: PhP765,380.33 representing the unpaid rental fees; interest of 12% per annum on the unpaid rental fees from March 1, 2001 until payment; penalty and coll

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.