Case Summary (G.R. No. 86695)
Trial Court Proceedings and Injunctive Relief
On Dec 12, petitioners sued PBAC members in RTC‐Iloilo, alleging wrongful exclusion from bidding and sought to reset the bid and enjoin any award. Judge Lebaquin issued a restraining order to halt bidding. Respondents moved to lift, invoking P.D. 1818’s ban on injunctions in government infrastructure projects and mootness due to late service of the order.
Application of P.D. 1818 and Preliminary Injunction
P.D. 1818 prohibits courts from issuing restraining or mandatory injunctions against any government infrastructure or public utility project. The trial court held the Micro Laboratory Building was an infrastructure project of a state college, hence within P.D. 1818’s coverage. It lifted the injunction also on grounds that PBAC had already conducted the bidding before service and that the ISCOF President held final award authority not before the court.
Petitioners’ Contentions on Irregularities
Petitioners argued:
- ISCOF’s autonomous charter placed it outside “national government” projects under P.D. 1818.
- The project was tainted by anomalies:
a. Published deadlines omitted time, yet PBAC unilaterally applied a 10:00 a.m. cut-off.
b. Bid opening advertised for 3:00 p.m. was held at 10:00 a.m.
c. Invitation to Bid forms lacked required project particulars and proper Bill of Quantities.
d. Materials-type bid form was used for a construction project. - The bidding had not been finally awarded, keeping injunctive relief viable.
- Failure to issue plans and specifications thirty days prior breached P.D. 1594 rules.
Respondents’ Counter-Arguments
Respondents maintained that ISCOF is a government instrumentality under P.D. 1523 and the GAA, thus covered by P.D. 1818. They asserted that a bulletin-board notice fixed 10:00 a.m. and 1:00 p.m. deadlines, that petitioners filed only letters of intent by 10:00 a.m. Dec 2, and that late-stamped documents were rightly disqualified. They added that petitioners waited to challenge disqualification until after bidding, waiving relief. They denied procedural defects, citing expired petitioner licenses and timely posting of schedules.
Supreme Court’s Analysis on Government Instrumentality
Invoking the 1987 Administrative Code, the Court classified ISCOF as a “chartered institution” and government instrumentality. Its creation under a state policy, ex officio Treasurer, COA audit, and GAA funding confirmed public character. Nonetheless, P.D. 1818’s injunction ban, patterned after P.D. 605, did not shield purely legal or procedural questions from judicial review. Injunctions may issue when administrative bodies violate substantive or procedural law.
Supreme Court’s Findings on Bidding Irregularities
The Court identified two fatal breaches of P.D. 1594 implementing rules:
- PBAC unilaterally changed published deadlines without notifying all prospective bidders, undermining fair competition and the requirement of public advertisement.
- Plans, specifications, and proposal forms for a P1 M–P5 M project were issued only ten days before bidding instead of thirty.
These lapses destroyed the integrity of the competitive process—notice, competition, and exact comp
Case Syllabus (G.R. No. 86695)
Procedural Context
- Petitioners sought a restraining order and preliminary injunction from the Regional Trial Court of Iloilo to reset bidding and accept their pre-qualification documents.
- RTC issued a restraining order on December 12, 1988, after the PBAC had already commenced and closed the bidding.
- Defendants moved to lift the restraining order, invoking P.D. 1818's prohibition against injunctions in government infrastructure projects.
- RTC granted the motion on January 2, 1989, lifted the restraining order, and denied the petition for preliminary injunction.
- Petitioners elevated the case to the Supreme Court via petition (G.R. No. 86695) questioning applicability of P.D. 1818 and alleging bid irregularities.
Facts
- ISCOF published an Invitation to Bid on November 25, 26, 28, 1988 for construction of a Micro Laboratory Building.
- Original notice set December 2, 1988 as the deadline for PRE-C1 submissions and December 12, 1988 at 3:00 p.m. for bid opening.
- Petitioners Málaga and Najarro filed PRE-C1 on December 2 at 2:00 p.m.; Occena on December 5.
- PBAC refused late submissions after a cut‐off time of 10:00 a.m. on December 2, 1988.
- Petitioners filed suit; RTC’s restraining order arrived at PBAC at 2:00 p.m. on December 12, after bidding closed at 11:30 a.m.
- PBAC conducted bidding and recommended award to a contractor; ISCOF president’s approval pending.
Issues Presented
- Whether P.D. 1818 prohibits issuance of preliminary injunctions or restraining orders in infrastructure cases involving a state college.
- Whether ISCOF is a government instrumentality subject to P.D. 1818.
- Whether procedural irregularities in bidding (notice changes, late issuance of plans, use of incorrect invitation form) justify injunctive relief.
- Whether the petition is moot or academic given completion status and de facto award.
Applicable Law
- Presidential Decree No. 1818: bars courts from issuing restraining/preliminary injunctions in government infrastructure projects.
- Implementing Rules of P.D. 1594: require published invitation, fixed deadlines, issuance of plans/specifications 30 days before bidding for p