Title
Mackay vs. Spouses Caswell
Case
G.R. No. 183872
Decision Date
Nov 17, 2014
Contractor's defective electrical work led to rectification costs; Caswells reimbursed P46,205 after offsetting unpaid balance. Owen liable for breach, acquittal irrelevant.

Case Summary (G.R. No. 191479)

Applicable Law and Legal Framework

Primary Civil Code provisions applied: Article 1715 (contractor’s obligation to execute work without defects and employer’s right to require removal or correction; employer may have defect corrected at contractor’s cost if contractor fails), Article 1167 (obligation to do something — execution at debtor’s cost if he fails), and Article 2199 (measure of damages). Penal provision relevant to antecedent criminal prosecution: Article 315 (estafa) of the Revised Penal Code. Evidentiary principles invoked: actual damages must be supported by competent proof (receipts/invoices); the demand to rectify need not be in any particular form; substantial compliance with Article 1715 may suffice.

Procedural History

Owen sued the Caswells for collection of P23,000 (unpaid contract balance) plus damages in MTC Civil Case No. 538. The MTC (June 29, 2006) dismissed Owen’s claims and ordered him to pay P46,205 representing rectification costs (after offsetting the P23,000). Owen appealed to the RTC, which reversed (October 31, 2006) and awarded him P23,000 plus moral and exemplary damages, attorney’s fees, and costs. The Caswells petitioned to the CA, which reinstated the MTC decision (April 30, 2008) and denied reconsideration (July 24, 2008). Owen filed a petition for review on certiorari to the Supreme Court, which denied the petition and affirmed the CA (final disposition).

Factual Background and Sequence of Events

The Caswells sought electrical installation for their newly built home. Zameco II quoted P456,000 for service connection; Owen offered to complete the installation for P250,000. Owen, with assistants, purportedly completed installation by August 1998; the Caswells paid P227,000. On inspection requested by the Caswells, Zameco II (through Engr. Pulangco) identified numerous defects and deficiencies in the installation that prevented energization, including improper materials and installations for pole construction, grounding defects, lack of required tapping/fuse cut‑out with lightning arrester, incorrect transformer distance from the neutral line, absence of required clamps, locknuts, and grounding rods, among other faults. Zameco II refused to energize until corrections and required documents/testing were provided. The Caswells thereafter engaged Zameco II to correct the work and obtain energization; energization occurred only after the distribution system was completed to Zameco II standards in January 1999.

Criminal Proceedings and Related Allegations

The Caswells executed a Joint Affidavit (September 4, 1998) alleging that Owen and his group misrepresented themselves (claiming to be from NAPOCOR) and thus swindled the Caswells of P227,000. An estafa case (Criminal Case No. RTC‑2533‑I) was filed but Owen was acquitted on the ground of reasonable doubt (May 15, 2003). The Supreme Court noted that statements in the criminal judgment suggesting delay might have been due to Zameco II employees’ resentment were obiter and not a basis to resolve the civil dispute.

Evidence Presented in the Civil Case

Caswells’ evidence included: Engr. Pulangco’s handwritten receipt for P15,400 (partial payment for materials used in correction); Sales Invoice No. 2029 from Peter A. Eduria Enterprises listing materials totalling P53,805; and a detailed list of materials with unit prices, labor costs and totals. Testimony of the Caswells recounted unsuccessful attempts to reach Owen and deficiencies identified by Zameco II. Owen and Badua testified that they rectified all discrepancies and that they informed Engr. Pulangco and the Caswells the installation was ready; Owen also claimed securing of permits was the Caswells’ responsibility.

MTC Ruling and Rationale

The MTC treated the contract as one for a piece of work and applied Article 1715. It concluded that the installation suffered defects impairing its fitness and value; Owen failed to remove the defects or to be available for rectification. Relying on Article 1167, the MTC held that the Caswells were entitled to have the defects corrected at Owen’s cost. The court accepted the Caswells’ proof of rectification expenses (total P69,205) and deducted the P23,000 Owen sought, entering judgment for the Caswells for P46,205 and dismissing Owen’s claim.

RTC Ruling and Rationale

The RTC reversed the MTC. It held that the Caswells should have instituted an action for specific performance (or otherwise afforded Owen a judicial opportunity to establish quality and acceptability of his work) before hiring Zameco II to effect corrections. The RTC relied in part on testimony suggesting Owen had completed work and on Engr. Pulangco’s remark that electricity could still flow without certain replacements. The RTC concluded Owen had complied with his obligations and therefore awarded him the unpaid balance (P23,000) with legal interest, moral damages (P25,000), exemplary damages (P20,000), attorney’s fees (P30,000), and costs.

Court of Appeals Ruling and Rationale

The CA reinstated the MTC decision. It found that the Caswells’ repeated efforts to communicate with Owen, their request that he secure permits and submit the transformer for testing, and Owen’s refusal to comply or even to be available for rectification amounted to a substantial compliance with the demand required under Article 1715. The CA concluded that Owen’s subsequent filing of a collection suit evidenced his belief that his work was complete and indicated futility in further demands for rectification. The CA invoked res ipsa loquitur to observe that the circumstances and the defective nature of the work spoke for themselves. On damages, the CA accepted Engr. Pulangco’s handwritten receipt and Sales Invoice No. 2029 as competent proof of actual rectification expenses, rejecting Owen’s attacks on the invoice’s admissibility and on the supplier’s registration. The CA ordered Owen to reimburse rectification costs but permitted set‑off of the unpaid P23,000 against the Caswells’ monetary claims, resulting in the same net amount ordered by the MTC.

Supreme Court Ruling and Rationale

The Supreme Court denied Owen’s petition and affirmed the CA’s decision in toto. The Court held that Owen failed to execute the contract in a manner free of defects which would not destroy or lessen the work’s fitness for its intended use (Article 1715). The Court found the Caswells’ Joint Affidavit and other trial evidence sufficient to show that they exer

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.