Title
Linear Construction Corp. vs. Dolmar Property Ventures, Inc.
Case
G.R. No. 212327
Decision Date
Nov 17, 2021
Dolmar withheld retention money from Linear, claiming offset for Marilao Project defects. SC ruled in Linear's favor, stating Dolmar's claim was unliquidated; legal compensation inapplicable.

Case Summary (G.R. No. 212327)

Background and Contractual Engagements

Dolmar engaged Linear to perform construction works on two distinct projects. In 1998 Linear was contracted for the drainage system works of the Marilao Project under several agreements (Phases 1 and 2). In 2003 Linear was contracted for works in the Sta. Maria Project, covered by a horizontal construction agreement and two supplemental agreements, with contract price for Sta. Maria set at Php40,820,000.00 and payments structured on progress billings less an 8% retention.

Contractual Terms on Retention and Final Payment

The Sta. Maria Contracts expressly provided that the 8% retention would be released within forty-five (45) days from Dolmar’s final written acceptance following submission of proof of payment of all project-related debts and the as-built plans. The final certificate of acceptance issuance was conditioned on those submissions.

Inspection, Alleged Defects, and Rectification Efforts

Dolmar engaged R.S. Caparros and Associates to manage construction for the Marilao Project and conducted joint inspections which Linear did not attend. R.S. Caparros reported numerous defects and irregularities in the Marilao drainage works (missing pipes, discrepancies from as-built drawings). Dolmar communicated defects to Linear; Linear undertook some rectifications that Dolmar deemed insufficient. R.S. Caparros prepared cost estimates for corrective works totaling Php6,379,935.00, and Dolmar engaged Mr. Elpidio D. Agapito for drainage rehabilitation.

Correspondence, Withholding of Retention, and Reciprocal Claims

After Linear completed the Sta. Maria Project, it demanded release of retention money (originally Php3,766,292.12, later adjusted to Php3,823,997.96). Dolmar required submission of requisite documents (proofs of non-indebtedness and as-built plans), which Linear furnished. Simultaneously, Dolmar demanded Php6,379,935.00 from Linear for rectification costs in Marilao and announced it would withhold Linear’s retention money, asserting legal compensation that left an alleged balance owed by Linear of Php2,613,642.88. Linear denied liability and litigated for collection.

Trial Court (RTC) Ruling

The Regional Trial Court (Branch 213, Mandaluyong City) rendered judgment for Linear on 22 January 2013. The RTC ordered Dolmar to pay Linear Php3,823,997.96 (unpaid retention) with 12% interest per annum from filing of the complaint, awarded amounts for acceptance and appearance fees, attorney’s fees (Php956,000.00), exemplary damages (Php20,000.00), and costs of suit. The RTC found that legal compensation could not apply because Dolmar had not established that Linear owed it a demandable, liquidated debt; Dolmar’s proofs addressed only liabilities from the Marilao Project while Linear’s cause of action concerned Sta. Maria. The RTC further found Dolmar acted in bad faith in refusing to issue a certificate of acceptance for Sta. Maria.

Court of Appeals (CA) Ruling

On appeal, the CA reversed the RTC. The CA concluded Dolmar sufficiently proved Linear’s obligation for the Marilao rectification costs (Php6,379,935.00), found Linear failed to rebut such liability, and held all requisites of legal compensation were present such that Dolmar’s rectification-cost claim extinguished Linear’s retention claim by offset. The CA ordered Linear to pay Dolmar Php2,555,937.04 (balance after offset) with 6% interest from filing of the complaint, awarded exemplary damages (Php100,000.00), attorney’s fees and litigation expenses (Php1,200,000.00), and costs. The CA also found Linear acted in bad faith and refused to award moral damages to the juridical person.

Issues Presented to the Supreme Court

(1) Whether the petition should be dismissed for Linear’s procedural lapses in filing the petition for review (defective attachments, undated affidavit of service, proof of corporate authority, and initially no soft copy). (2) Whether Linear’s claim for retention money was extinguished ipso jure by legal compensation in light of Dolmar’s counterclaim for rectification costs.

Supreme Court on Procedural Compliance

The Supreme Court acknowledged several procedural defects but exercised discretion to resolve the petition on the merits. Linear cured most deficiencies shortly after filing, submitted relevant records and the soft copy, and both the CA and Dolmar received and fully litigated the issues. The Court emphasized that rules are tools to attain justice and that strict procedural technicalities should not frustrate substantial justice. One remaining procedural lapse (a duly dated affidavit of service) was mitigated by submission of proof of service and the registry return card. Given these circumstances, the Court proceeded to the merits.

Scope of Review Under Rule 45 and Exceptions Invoked

Although Rule 45 appeals are generally confined to questions of law, the Court recognized an exception where appellate factual findings are unsupported by evidence or the judgment rests on a misapprehension of facts. The Court found that exception applicable here and therefore entertained review of the factual basis for the CA’s conclusion that Linear owed Php6,379,935.00.

Legal Compensation: Requisites and Applicable Law

The Court set out the requisites for legal compensation under the Civil Code: (1) each party is principal debtor and principal creditor of the other; (2) the debts are sums of money or consumable things of same kind and quality; (3) both debts are due; (4) the debts are liquidated and demandable; and (5) there is no retention or controversy by third persons properly communicated. These requirements (Arts. 1278–1279) govern ipso jure extinction of mutual obligations.

Supreme Court Findings on Liquidation and Demandability of Dolmar’s Claim

The Court concluded that Dolmar’s claimed rectification cost (Php6,379,935.00) was neither liquidated nor demandable. Linear consistently disputed liability; the claimed amount was a unilateral estimate by R.S. Caparros and not supported by receipts or evidence of actual expenditures. Documentary evidence indicated only approximately Php700,000.00 in actual payments and did not establish that Dolmar had disbursed the estimated amount at the time it withheld retention. Because the amount was disputed and unliquidated, and because defenses (e.g., completion, expiration of warranty or prescription) could bar Dolmar’s recovery, Dolmar’s claim was not a demandable, liquidated debt that could operate as legal compensation.

Legal vs. Judicial Compensation and the Court’s Refusal to Adjudicate the Marilao Claim

The Court explained the distinction: legal compensation operates ipso jure upon concurrence of requisites; judicial compensation arises when an unliquidated counterclaim is liquidated by judgment (Art. 1283). Although Dolmar pleaded its rectification costs as a compulsory counterclaim, the Court declined to resolve its merits for several reasons: (1) the primary issue before the Court was legal, not judicial compensation; (2) the Marilao and Sta. Maria projects are separate transactions involving different factual and procedural requirements, so liquidation of the Marilao claim would amount to treating a compulsory counterclaim as a permissive one and would implicate procedural rul

    ...continue reading

    Analyze Cases Smarter, Faster
    Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.