Title
KT Construction Supply, Inc. vs. Philippine Savings Bank
Case
G.R. No. 228435
Decision Date
Jun 21, 2017
KT Construction defaulted on a P2.5M loan; SC upheld acceleration clause, attorney's fees, but absolved Go and Go-Tan due to lack of jurisdiction.
A

Case Summary (G.R. No. 228435)

Key Dates and Applicable Law

  • Loan and promissory note executed: October 12, 2006; repayment term stated as sixty (60) months (November 12, 2006 to October 12, 2011).
  • Demand letter from PSBank: record references include January 3, 2011 (in the factual narrative) and a demand letter dated February 3, 2011 as cited by the Court.
  • Controlling legal principles applied: validity and effect of acceleration clauses; burden of proof on payment once indebtedness is established; admissibility and effect of adhesion contracts; enforceability of stipulations for attorney’s fees; jurisdictional limits of judgments (binding only on parties properly before the court) under due process.

Facts

  • KT Construction obtained a P2.5 million loan from PSBank evidenced by a promissory note signed by the corporate officers both in representative and personal capacities.
  • The promissory note contained an acceleration clause making the entire obligation immediately due upon default in any installment, and it contained a stipulation for attorney’s fees in the event of litigation.
  • PSBank sent a demand for payment in early 2011 and subsequently filed a complaint for sum of money for alleged unpaid indebtedness in the amount of P725,438.81 (excluding interest, penalties, legal fees, and other charges).

Procedural History

  • RTC (June 11, 2014): ruled for PSBank, found acceleration clause effective, declared KT Construction, Go and Go‑Tan solidarily liable, ordered payment of P725,438.81 with 12% interest per annum from January 13, 2011 until fully paid, and awarded Php50,000 as attorney’s fees.
  • Court of Appeals (April 22, 2016): affirmed the RTC with modification — legal interest set at 6% per annum from finality of the CA decision until full payment; CA upheld award of attorney’s fees and the application of the acceleration clause; CA directed assessment of additional docket fees per Rule 141, Section 2. Reconsideration denied (November 23, 2016).
  • Supreme Court (G.R. No. 228435): resolved issues on appeal and modified the judgment as to the parties bound by it.

Issues Presented

  1. Whether William Go and Nancy Go‑Tan can be held jointly and severally liable with KT Construction for the judgment award.
  2. Whether PSBank’s complaint was prematurely filed.
  3. Whether the promissory note is a contract of adhesion and thus void.
  4. Whether the award of attorney’s fees was proper.

Court’s Analysis — Acceleration Clause and Prematurity

  • The Court reaffirmed that acceleration clauses are valid and effective to make the entire indebtedness due upon default in any installment. (Premiere Development Bank precedent cited in the decision.)
  • Given the clause in the promissory note, KT Construction’s loan obligation became due and demandable upon failure to pay an installment; PSBank’s filing was therefore not premature.
  • The Court also observed PSBank’s demand letter in early 2011; in any event, the parties had waived the necessity of demand in the promissory note, so absence of receipt of a demand notice would not prevent acceleration and suit. (Spouses Agner precedent cited.)

Court’s Analysis — Burden of Proof on Payments

  • The Court applied the established rule that once indebtedness is established by the creditor, the burden shifts to the debtor to prove payment or discharge of the obligation. (Bognot v. RRI Lending Corp. precedent cited.)
  • KT Construction admitted obtaining the loan and alleged regular payments but failed to produce documentary evidence (deposit slips, receipts) to prove payment; thus it did not discharge the burden to show payments that would reduce or extinguish the indebtedness.

Court’s Analysis — Contract of Adhesion

  • The Court rejected the argument that the promissory note was void as a contract of adhesion. It noted that adhesion contracts are not void per se; a party is free to reject a standard form, and acceptance constitutes consent. (Norton Resources precedent cited.)
  • Accordingly, the promissory note’s terms, including the acceleration clause and other stipulations, were not invalid merely because they were in a standard form.

Court’s Analysis — Attorney’s Fees

  • The promissory note expressly provided for payment of attorney’s fees in case of default. The Court treated that stipulation as a valid penal clause incorporated in the parties’ contract. (Baron Marketing precedent cited.)
  • Article 2208 of the Civil Code (referenced by KT Construction) was inapplicable because that provision governs the allowance of attorney’s fees where there is no contractual stipulation; here the parties did stipulate attorney’s fees.

Court’s Analysis — Jurisdiction and Liability of Co‑makers (Go and Go‑Tan)

  • The Supreme Court found error in the RTC and CA insofar as they declared Go and Go‑Tan solidarily liable. Go and Go‑Tan were not impleaded as defendants in the
...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.