Title
Ka Kuen Chua, doing business under the name and style Ka Kuen Chua Architectural vs. Colorite Marketing Corporation
Case
G.R. No. 193969-193970
Decision Date
Jul 5, 2017
KKCA and Colorite disputed project delays and costs after a Hold Order, leading to shared liability and modified settlement.

Case Summary (G.R. No. 193969-193970)

Contractual Agreement and Scope

Colorite and KKCA entered into a construction contract whereby KKCA was to build a four-storey residential/commercial building for Php33,000,000.00. Key provisions included: commencement within seven days after notice to proceed, completion within 365 days from 7 days after down payment, liquidated damages of Php10,000/day for delay, and a maximum permissible slippage of 20% (73 days). Colorite had the right to terminate after excessive delay and to take over the project, deducting costs from payments to KKCA. Addenda broadened project details, specifying excavation and soil protection works. Although excavation initially handled by subcontractor WE Construction Company (WCC), Addendum #01 transferred responsibility for excavation and soil protection to KKCA.

Incident of Erosion and Resultant Delay

Excavation began January 10, 2004, but erosion damaged adjacent Hontiveros family property by January 17, 2004. Makati City issued a Hold Order on January 22, 2004 halting excavation until repair and the Hontiveros’ quitclaim were secured. Restoration concluded October 2005, yet construction remained suspended due to the outstanding quitclaim. The project suffered an 878-day delay, prompting Colorite to demand liquidated damages. KKCA denied liability, arguing suspension of the completion period due to the Hold Order and dispute over costs for soil protection and restoration.

Claims and Counterclaims

Colorite sought liquidated damages (Php8,780,000 plus Php10,000 daily until completion), loss of rental income (Php13,345,481), attorney’s fees and litigation expenses. KKCA denied liability for excavation defects caused by subcontractor WCC, claimed suspension of the construction period, and counterclaimed for costs related to soil protection, design fees, restoration, maintenance, moral and exemplary damages, and attorney’s fees.

Rulings of CIAC and Court of Appeals

CIAC apportioned fault equally, awarding Colorite 50% of liquidated damages (Php4,390,000), denied loss of rental income and attorney's fees, and allowed KKCA partial recovery for soil protection and design fees but disallowed others. The CA affirmed with modification, confirming Colorite’s partial entitlement to liquidated damages, denying rental losses and attorney’s fees, clarifying that soil protection and excavation fell within KKCA’s scope, and ordering Colorite to reimburse certain payments by KKCA. The CA also ordered KKCA to complete the project and secure necessary legal clearances, rejecting claims for moral and exemplary damages for both parties.

Supreme Court’s Findings: Liability for the Erosion

The Court found KKCA primarily liable for the erosion damaging the Hontiveros property due to its failure to provide adequate soil protection before erosions occurred in January and February 2004. KKCA had supervisory control over excavation as per contractual addendum and failed to employ timely protective measures, calling for remedial actions only after damage. Conversely, Colorite was not liable for subcontractor WCC’s negligence as WCC was not KKCA’s employee and excavation was contractually within KKCA’s scope. The principle of estoppel cited by CIAC against Colorite was deemed erroneously applied, with Colorite’s presence in meetings insufficient to imply assumption of liability.

Scope of Excavation and Soil Protection Works

The parties’ original bid proposal excluded excavation from KKCA's responsibility, pending completion by a separate contractor. However, contractual Addendum #01 unambiguously incorporated excavation and mandatory soil protection works within KKCA’s contractual duties, including provision and maintenance of shoring, bracing, and adequate dewatering to prevent settlement and damage to adjoining properties. Contractual clarity and KKCA’s assent rendered previous exclusions inoperative.

Dispute on Sharing Restoration Costs

The Court found no valid and enforceable agreement obliging Colorite to share in restoration costs of the Hontiveros property beyond interim payments. Although the CA considered a Php700,000.00 promise by Colorite to share costs, there was insufficient evidence of a perfected contract to that effect. Hence, the original contract clause exempting Colorite from third-party liabilities remained effective. Colorite’s failure to pay the interim amount did not justify reducing liquidated damages claim by half; thus, Colorite was absolved from restoration cost sharing.

Obligations to Secure Quitclaim and Lift Hold Order

KKCA was held obligated to secure the quitclaim from the Hontiveros family and to facilitate lifting of the Hold Order issued by Makati City. These duties were necessarily implied from the contractual provision requiring KKCA to protect adjacent properties and to indemnify Colorite from third-party claims arising from construction. KKCA’s failure to obtain requisite certifications or legal clearances contributed to the prolonged project suspension and constituted negligence.

Fault for Delay and Non-Exercise of Termination Rights

While KKCA’s negligence was the proximate cause of delay, the Court also found Colorite at fault for protracted delay by failing to exercise its contractual right to terminate the contract after the maximum allowable delay lapsed and to engage another contractor. Colorite’s inactivity weighed against its claims for damages including lost rental income, as it did not mitigate consequences of delay. Nonetheless, absence of bad faith precluded award of exemplary damages or attorney’s fees to either party.

Damages and Liquidated Damages

Colorite was entitled to liquidated damages corresponding to delay from the original completion deadline (March 6, 2005) to October 2005 when property restoration concluded, plus an additional six months (April 30, 2006) to determine project continuation, totaling Php4,210,000.00. Liquidated damages serve as a penalty and need not prove actual loss, but must be equitable and not unconscionable. Extension of damages beyond this period was denied due to inaction attributable to Colorite. Claims for loss of rental income were denied for lack of evidence evidencing actual lease agreements.

Obligation to Complete Project and Contract Price Adjustment

KKCA was ordered to finish the construction project. The Court upheld the binding nature of the contract, disallowing KKCA’s arguments invoking constitutional protection against involuntary servitude, as the contract is a reciprocal one, and the parties voluntarily entered

    ...continue reading

    Analyze Cases Smarter, Faster
    Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.