Title
J Plus Asia Development Corp. vs. Utility Assurance Corp.
Case
G.R. No. 199650
Decision Date
Jun 26, 2013
A construction agreement for a Boracay condotel faced delays, leading to contract termination. CIAC ruled contractor and surety liable; CA reversed, but SC reinstated CIAC, holding contractor in default and surety fully liable under the bond.

Case Summary (G.R. No. 199650)

Facts

On December 24, 2007, the parties executed a P42 million Construction Agreement requiring completion within 365 days of notice to proceed. A 20% down payment (P8.4 million) was fully paid on January 14, 2008. Mabunay commenced work on January 7, 2008, and posted an equivalent performance bond through Utassco. By November 14, 2008, joint inspection revealed only 31.39% completion against an agreed schedule, leaving over two-thirds of the work undone.

Arbitration Proceedings and Appellate History

J Plus terminated the contract on November 19, 2008, then filed for arbitration before the Construction Industry Arbitration Commission (CIAC), claiming P8,980,575.89 in liquidated damages and P2,379,441.53 in unrecouped down payment. The CIAC awarded joint and several liability of Mabunay and Utassco for P4,469,969.90 (liquidated damages) and P2,379,441.53, plus interest, without exceeding Utassco’s P8.4 million bond, and ordered indemnity by Mabunay. The Court of Appeals reversed, holding delay was not yet demandable before the contract’s one-year term and reinterpreting the bond’s scope.

Issues

  1. Whether the Court of Appeals had jurisdiction to review a CIAC arbitral award.
  2. Whether Mabunay was in default for delayed completion entitling J Plus to liquidated damages.
  3. Whether the performance bond secured full contract performance or was limited to 20% down payment.
  4. Proper computation of interest and indemnity.

Legal Analysis on Jurisdiction and Default

Under EO 1008, as amended by RA 7902 and the 1997 Rules, CIAC awards are final and appealable to the Supreme Court via a Rule 43 petition for review to the Court of Appeals. RA 9285 does not divest this jurisdiction nor require CIAC awards to be confirmed by the RTC. Default under Articles 1169 and 1170 and Civil Code Article 1169 arises when a demandable, liquidated obligation is not fulfilled after demand. Contractual provisions and repeated notices of delay established Mabunay’s default well before expiration of the one-year term.

Interpretation of Performance Bond and Surety Liability

The bond’s recitals guarantee “full and faithful performance” of the contract, with Utassco’s liability capped at P8.4 million. Ambiguities are construed against the surety and in favor of the obligee. The bond functions as a penalty clause permitting J Plus to confiscate its proceeds upon contrac

    ...continue reading

    Analyze Cases Smarter, Faster
    Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.