Title
Insular Life Assurance Co. Ltd. vs. Asset Builders Corp.
Case
G.R. No. 147410
Decision Date
Feb 5, 2004
Bidding dispute: No valid contract formed as IL failed to formally accept ABC's bid; ABC withdrew before acceptance, no breach or damages.

Case Summary (G.R. No. 181704)

Key Dates and Procedural Posture

Invitation to bid and distribution of bid documents occurred in November 1992. Bids were opened November 9, 1993; ABC submitted the lowest bid of P12,961,845.54 (readjusted to P13,000,000). Post-qualification and evaluations occurred in January–February 1994; IL prepared a Notice to Proceed and AWIA informed ABC of a pre-construction meeting in March 1994. ABC sent a letter dated April 5, 1994 declining to undertake the project. IL filed suit December 23, 1994. The Regional Trial Court dismissed IL’s complaint and awarded damages on ABC’s counterclaim. The Court of Appeals affirmed. IL’s Rule 45 petition was denied by the Supreme Court, which affirmed the lower courts and imposed costs against IL.

Applicable Law and Legal Framework

Constitutional framework: 1987 Philippine Constitution (applicable because the decision date is after 1990). Governing private-law principles: the Civil Code provisions on contracts (including consensual nature of contracts, required elements, offer and acceptance, and interpretation of contracts), and specific jurisprudential rules cited in the decision concerning offer, acceptance, counter-offer, communication of acceptance, stages of contract formation (negotiation, perfection, consummation), and estoppel. Contractual documents at issue included the Instruction to Bidders and the Bid Proposal Form, which prescribed the manner and form of acceptance and remedies for failure to execute a contract.

Undisputed Factual Background

IL invited contractor bids and furnished an Instruction to Bidders setting conditions including (a) submission of bid bonds, (b) a 60-day bid validity period subject to extension by owner, and (c) requirement that a bidder whose proposal is accepted be notified in writing and must execute the Construction Agreement within five days after receipt of Notice of Award, failing which the bid bond would be retained as liquidated damages. ABC submitted a valid bid bond and the lowest monetary proposal. AWIA and IL conducted post-qualification and recommended ABC. IL and ABC engaged in clarification and a conference where IL proposed adjusting ABC’s bid to P13,000,000 to reflect a wage increase; ABC later agreed to the readjustment. IL prepared a Notice to Proceed and AWIA scheduled a pre-construction conference; ABC attended the pre-construction meeting and a ground-breaking ceremony was held. ABC did not sign a Construction Agreement or commence work and on April 5, 1994 informed IL it could not undertake the project. IL engaged another contractor at a higher price and sought damages; ABC counterclaimed.

Central Legal Issue

Whether a valid and binding construction contract was perfected between IL and ABC such that ABC’s withdrawal constituted breach and rendered it liable for damages claimed by IL. The Supreme Court characterized this as essentially a single, controlling issue: existence of a contract.

Governing Contract Principles Applied by the Court

The Court reiterated established principles: contracts are consensual and perfected by mere consent (Article 1315 and related jurisprudence); the offer must be certain and the acceptance seasonable and absolute—any qualified acceptance is a counter-offer; the stages of a contract are negotiation (preparation), perfection (agreement on essential elements), and consummation (performance); acceptance must be communicated to the offeror when the offeror prescribes the manner of acceptance. The Instruction to Bidders explicitly required written Notice of Award to effect acceptance and fixation of execution obligations.

Application of Law to Facts — Why No Contract Was Perfected

The Court found the parties never moved beyond negotiation into perfection. IL failed to demonstrate it gave ABC the formal written Notice of Award required by its own Instruction to Bidders; therefore, the requisite communication of acceptance was not proven. IL’s internal memoranda and documents to which ABC was not privy did not substitute for the prescribed written notice. The March 14 document was a Notice to Proceed conditioned upon execution of the Construction Agreement; it did not itself constitute the required unconditional acceptance. IL’s subsequent proposal to adjust ABC’s bid to P13,000,000 constituted further negotiation and a counter-offer rather than an unconditional acceptance. ABC’s April 5, 1994 withdrawal occurred before any communicated acceptance and therefore was permissible; an offeror or offeree may revoke or withdraw an offer prior to receipt of communicated acceptance.

Treatment of the Bid Bond and Its Expiry

Although a bid bond is a customary and required accessory to secure the bid and show good faith, the Court held that the lapse of the bid bond on January 8, 1994 did not ipso facto prove expiration of the underlying bid offer. The bond is accessory and may be waived by the owner; its expiration, however, did not cure IL’s failure to comply with its own requirement of communicating acceptan

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.