Case Summary (G.R. No. 169095)
Factual Background
Heunghwa Industry Co., Ltd. secured a contract with the Department of Public Works and Highways to construct the Roxas‑Langogan Road in Palawan. DJ Builders Corporation entered into a subcontract with Heunghwa to perform earthwork, sub‑base course and box culvert work for the amount of Php113, 228, 918.00. The subcontract contained an arbitration clause. The subcontractor alleged nonpayment and on January 19, 2000 filed a complaint in the RTC for breach of contract and collection of sum of money. Heunghwa answered, counterclaimed for Php24,293,878.60, and averred respondent caused work stoppage and that Heunghwa could not collect from the DPWH due to respondent’s poor performance.
Referral to CIAC and Early CIAC Proceedings
On September 27, 2000 the parties, through counsel, filed a Joint Motion to Submit Specific Issues To The Construction Industry Arbitration Commission, specifying five issues for arbitration: manpower and equipment standby time; unrecouped mobilization expenses; retention; discrepancy of billings; and price escalation for fuel and oil usage. The RTC granted the motion the same day. Thereafter, petitioner filed an urgent manifestation seeking referral of additional matters. Respondent filed a Request for Adjudication with CIAC on October 24, 2000. Petitioner thereafter manifested abandonment of the referral and announced pursuit of the RTC action. CIAC issued an order on November 27, 2000 directing respondent to move for dismissal of the RTC case insofar as the referred issues were concerned, but CIAC later modified that posture in its January 8, 2001 order and directed dismissal only with respect to the five specified issues.
Further Procedural Conflict Between the RTC and CIAC
A sequence of motions and orders followed in both forums. Petitioner moved in the RTC on February 22, 2001 to withdraw the referral, alleging lack of authorization by its counsel. The RTC issued a Resolution on May 16, 2001 granting the motion to recall. Respondent moved for reconsideration and later filed a Motion to Dismiss in the RTC which the RTC granted on July 16, 2001 without prejudice to petitioner’s counterclaim. Petitioner sought reconsideration. CIAC intermittently suspended and resumed proceedings, denied petitioner’s motions to dismiss, and set a preliminary conference and hearings in early 2002. On March 13, 2002 the RTC issued a resolution declaring the July 16, 2001 dismissal “without force and effect” and set the case for hearing. CIAC on March 22, 2002 denied petitioner’s motion to dismiss and held it had jurisdiction. The conflicting orders produced parallel petitions for certiorari to the Court of Appeals: petitioner’s CA‑G.R. SP No. 70001 and respondent’s CA‑G.R. SP No. 71621.
Issues Presented to the Supreme Court
Petitioner raised three principal assignments of error: (A) the CA erred in finding procedural infirmities because petitioner filed certiorari without first filing a motion for reconsideration with CIAC and because a denial of a motion to dismiss is interlocutory and not certiorariable; (B) the CA erred in confirming CIAC’s jurisdiction over the dispute and misapplied National Irrigation Administration v. Court of Appeals; and (C) the CA erred in refusing to remand the case to CIAC to allow petitioner to present evidence in the interest of justice.
Parties’ Contentions
Heunghwa Industry Co., Ltd. contended that the CA improperly dismissed its petition on procedural grounds, that the denial of its motion to dismiss by CIAC amounted to lack or excess of jurisdiction or patent grave abuse of discretion and was therefore certiorariable, and that CIAC lacked jurisdiction because the arbitration clause did not designate CIAC and because the counsel who joined the referral lacked authorization. Heunghwa sought a remand to permit presentation of evidence if required. DJ Builders Corporation maintained that CIAC had original and exclusive jurisdiction by virtue of the arbitration clause and the parties’ referral, that petitioner’s participation and the joint referral estopped it from denying CIAC jurisdiction, and that CIAC properly proceeded under its rules despite petitioner’s non‑participation.
Ruling of the Court of Appeals
The Court of Appeals denied petitioner’s petitions on both procedural and substantive grounds. Procedurally, the CA observed that petitioner did not file a motion for reconsideration of CIAC’s March 22, 2002 order and thus failed to afford the CIAC a chance to correct alleged error, and it held that denial of a motion to dismiss, being interlocutory, is generally not the proper subject of certiorari. Substantively, the CA found that CIAC had jurisdiction: the subcontract contained an arbitration clause, the parties had jointly moved to refer specific issues to CIAC, and petitioner’s contention as to lack of authorization of its counsel was immaterial because the agreement to submit disputes to arbitration vested jurisdiction in CIAC.
Supreme Court Disposition
The Supreme Court denied the petition for review on certiorari under Rule 45 for lack of merit and affirmed the August 20, 2004 Decision and August 1, 2005 Resolution of the Court of Appeals in CA‑G.R. SP Nos. 70001 and 71621. The Court ordered double costs against petitioner.
Legal Reasoning and Application of Precedent
The Supreme Court analyzed first the procedural contention. It reiterated the rule that a petition for certiorari ordinarily should be preceded by a motion for reconsideration, and it recognized exceptions where the issue is purely one of law, where public interest or urgency is involved, or where the same questions were already squarely and exhaustively considered below. The Court agreed that the principal issue—whether CIAC or the RTC had jurisdiction over the construction dispute—was a question of law and that the exception to the reconsideration rule applied. On the substantive contention, the Court recalled the narrow circumstances under which an interlocutory order may be assailed by certiorari: when the issuing tribunal acted without or in excess of jurisdiction, when there was patent grave abuse of discretion, or when appeal would be inadequate and not speedy. The Court held that CIAC did not act without jurisdiction nor commit patent grave abuse of discretion in denying petitioner’s motion to dismiss.
Basis for CIAC Jurisdiction
The Supreme Court concluded that CIAC possessed original and exclusive jurisdiction under Executive Order No. 1008 over construction disputes where the parties agreed to submit such disputes to arbitration. The Court applied the doctrine in Philrock, Inc. v. Construction Industry Arbitration Commission and National Irrigation Administration v. Court of Appeals, and it emphasized the amendment to the CIAC Rules that deems an arbitration clause in a construction contract or a submission to arbitration to constitute an agreement to submit the controversy to CIAC jurisdiction irrespective of any reference to another arbitral body. The Court therefore held that the mere presence of the arbitration clause in the subcontract vested CIAC with jurisdiction ipso facto and rendered subsequent consent superfluous. The Court found the RTC’s vacillations and later attempts to recall did not divest CIAC of jurisdiction once jurisdiction had attached.
On Authorization of Counsel, Participation, and Estoppel
The Supreme Court addressed petitioner’s argument that its counsel lacked
...continue reading
Case Syllabus (G.R. No. 169095)
Parties and Posture
- HEUNGHWA INDUSTRY CO., LTD. was a Korean corporation doing business in the Philippines and was the petitioner before the Court.
- DJ BUILDERS CORPORATION was a Philippine corporation and was the respondent before the Court.
- The dispute arose from a subcontract for earthwork, sub base course and box culvert for the Roxas-Langogan Road project with an agreed price of Php113,228,918.00.
- Respondent filed an action for breach of contract and collection on January 19, 2000 before the Regional Trial Court (RTC), Puerto Princesa, Branch 51, docketed as Civil Case No. 3421.
- The subcontract contained an arbitration clause providing that controversies between contractor and subcontractor shall be settled by arbitration.
- Parties filed a joint motion on September 27, 2000 to submit five specified issues to the Construction Industry Arbitration Commission (CIAC) for arbitration, which the RTC granted.
- Petitioner sought review by petition for certiorari under Rule 45, Rules of Court, seeking to set aside the August 20, 2004 Decision and August 1, 2005 Resolution of the Court of Appeals in CA-G.R. SP Nos. 70001 and 71621.
Key Facts
- Respondent increased its CIAC claim by filing a revised complaint raising the amount from Php23,391,654.22 to Php65,393,773.42.
- Petitioner filed an amended answer asserting breach by respondent and lodged a counterclaim for Php24,293,878.60.
- Petitioner subsequently manifested that it was abandoning submission to CIAC and disputed counsel authorization to agree to arbitration.
- CIAC issued orders denying petitioner’s motions to dismiss and setting the case for conference and hearing, and it directed respondent to file a request for adjudication.
- The RTC vacillated between referring issues to CIAC, recalling its referral order, granting a dismissal without prejudice, and later declaring that dismissal "without force and effect" and setting the case for hearing.
- Petitioner and respondent filed separate petitions for certiorari in the Court of Appeals challenging CIAC and RTC orders, and the CA consolidated the petitions.
- CIAC rendered an award on September 27, 2002 granting respondent Php31,119,465.81, and the CA later denied petitioner’s petitions and motions for reconsideration.
Procedural History
- The RTC initially referred five specific issues to CIAC on September 27, 2000 and issued an order granting the referral the same day.
- CIAC denied petitioner’s motion to dismiss on March 5, 2001 and set a preliminary conference for April 10, 2001, which it later suspended and reset.
- The RTC granted respondent’s motion to dismiss without prejudice on July 16, 2001 and later recalled that order on March 13, 2002, thereby reinstating Civil Case No. 3421.
- CIAC issued an order on March 22, 2002 denying petitioner’s motion to dismiss and asserting jurisdiction over the referred issues.
- Petitioner filed a petition for certiorari with the Court of Appeals on April 5, 2002 while respondent filed another on July 5, 2002, and the CA consolidated both petitions.
- The Court of Appeals issued its decision on August 20, 2004 and denied reconsideration on August 1, 2005, both of which the Supreme Court reviewed in this petition.
Issues Presented
- Whether petitioner’s failure to file a motion for reconsideration of the CIAC March 22, 2002 order was fatal to its petition for certiorari.
- Whethe