Title
Heirs of Dimao vs. National Grid Corporation of the Philippines
Case
G.R. No. 254020
Decision Date
Mar 1, 2023
NGCP expropriated land in 1978; heirs sought compensation in 2014. SC ruled no entitlement to land value, only improvements, under C.A. No. 141’s 60-meter easement. Deposit refund ordered.
A

Case Summary (G.R. No. 254020)

Key Dates and Procedural Posture

Relevant factual and procedural milestones included: construction of the Baloi-Agus 2 138kV Transmission Line (BATL) in 1978; TRANSCO assumption of NPC transmission functions pursuant to R.A. No. 9136; NGCP’s assumption of TRANSCO’s management in 2009; NGCP’s expropriation filing (August 15, 2014); NGCP deposit with Land Bank of the Philippines of P1,756,400.00 (equal to the BIR zonal value); writ of possession issued September 2, 2014 and possession taken September 25–26, 2014; petitioners’ answer and demand for P113,552,000.00 (October 1, 2014); RTC Decision (April 16, 2018) granting expropriation and awarding P49,622,050.00; CA Decision (July 26, 2019) affirming expropriation but deleting the additional award of P47,865,650.00; petition for review to the Supreme Court resolved in the decision under discussion.

Applicable Law and Constitutional Basis

The decision was resolved under the 1987 Constitution, specifically Article III, Section 9 (no taking of private property for public use without just compensation). Statutory framework and authorities invoked include Commonwealth Act No. 141 (Public Land Law) §112 (right-of-way on patent lands), Presidential Decree No. 635 (amendment to §112), R.A. No. 9136 (EPIRA), R.A. No. 9511 (granting NGCP franchise and expressly authorizing NGCP to exercise eminent domain subject to legal limitations), R.A. No. 8974 and R.A. No. 10752 (laws facilitating acquisition of right-of-way), and civil law principle of solutio indebiti (Art. 2154, Civil Code).

Factual Background and Expropriation Proceedings

NPC constructed BATL in 1978. NGCP instituted expropriation over a portion of Lot No. 104 in 2014 to clear and maintain the transmission line right-of-way, deposited P1,756,400.00 (BIR zonal value) with LBP, and was granted a writ of possession by the RTC. Petitioners demanded a much larger amount as just compensation and the parties failed to settle, prompting the appointment of commissioners and adjudication of compensation.

RTC Ruling and Award

The RTC declared NGCP had lawful right to take 11,460 sq. m. of the subject lot, directed NGCP to deposit the deficiency over the initial deposit (P47,865,650.00) for a total just compensation of P49,622,050.00, and ordered annotation of the decision on the title and issuance of tax declaration in NGCP’s name for the expropriated portion. NGCP’s motion for partial reconsideration was denied, and NGCP appealed to the Court of Appeals.

Court of Appeals Ruling and Modification

The CA affirmed the RTC’s recognition of NGCP’s right to expropriate but deleted the additional award of P47,865,650.00. The CA relied on §112 of C.A. No. 141 to the effect that free-patent lands are subject to a 60-meter right-of-way for government and public or quasi-public enterprises, allowing compensation only for improvements. The CA also noted the BATL’s construction in 1978 and the fact that petitioners’ predecessor acquired title only in 2012, concluding petitioners could not claim actual loss attributable to the 1978 taking. The CA further found no evidentiary basis for compensation for preexisting improvements as of 1978.

Issues Presented to the Supreme Court

The Supreme Court framed the central issues as: whether petitioners are entitled to just compensation; and, if so, what the correct reckoning date for computing just compensation is. Petitioners challenged the validity and applicability of C.A. No. 141 §112, asserted that newer statutes (R.A. No. 8974 and R.A. No. 10752) superseded §112, contended the taking occurred only when NGCP filed suit in 2014 (not 1978), asserted continuous possession since 1955 (free patent issuance), and urged that NGCP’s internal valuation of improvements (P62,822,899.00) should control. NGCP defended application of §112, asserted its franchise and R.A. No. 9511 authorize eminent domain, maintained the taking occurred in 1978, and alleged that many improvements were planted after NGCP assumed operation and some were maliciously planted.

Legal Principles on Eminent Domain and Reckoning Point

The Court reiterated that eminent domain is a sovereign power that may be delegated by statute to government agencies or quasi-public entities, and that such delegation must be rooted in law and exercised within its limits. Under prevailing doctrine, just compensation is measured as the full and fair equivalent of the property taken and is determined as of the earlier of the date of actual taking or the filing of the complaint. The Court reviewed jurisprudence holding that the installation of transmission lines and the consequent permanent burdens on land constitute a taking at the time of construction and that owners are entitled to compensation measured at that time.

Application to the Present Case — Date of Taking

Applying these principles, the Court concluded the taking occurred in 1978 when the BATL was constructed and NGCP’s predecessor entered and devoted the land to public use, permanently affecting beneficial enjoyment. Petitioners themselves treated 1978 as the reckoning point in their pleadings by demanding interest and rents from that year; the existence of the line since 1978 was stipulated and corroborated by the commissioners’ report and RTC findings. Because petitioners were not the registered owners at the time of construction, they cannot claim just compensation measured from 1978.

Application of C.A. No. 141 §112 and Patent Status

The Court held §112 of C.A. No. 141 applicable to lands derived from a free patent, which subjects such lands to a right-of-way not exceeding 60 meters for public and certain quasi-public uses, allowing damages only for improvements. Petitioners’ title stems from a homestead (free) patent issued in 2012; thus the area traversed by the BATL (30 meters wide) fell within the 60-meter right-of-way. The Court found that petitioners’ free patent application constituted an acknowledgment of the land’s public nature and noted that mere long possession does not convert public land to private ownership for purposes of compensation. The Court also stressed that collateral attack on a presumptively valid statute (§112) is impermissible absent direct invalidation.

Interaction with R.A. Nos. 8974 and 10752

The Court r

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.