Title
H.S. Pow Construction and Development Corp. vs. Shaughnessy Development Corp.
Case
G.R. No. 229262
Decision Date
Jul 7, 2021
HSPCDC sued SDC for unpaid construction work; SC upheld liability for incomplete tasks but deleted delay penalty, citing SDC's changes and additional works.

Case Summary (G.R. No. 24804)

Contract and Project Scope

– September 2001 contract for P10,500,000.00, inclusive of materials, labor, bonds, VAT, with no escalation clause.
– Scope: subdivision concrete roads, underground drainage, water distribution, elevated steel water reservoir.
– Work to start within 10 days of notice and permit release; complete within 180 days.
– Actual start: May 21, 2002.

Variation Orders and Additional Works

– HSPCDC performed approved variation orders worth P552,829.75.
– At SDC President’s instruction, HSPCDC built three duplex units (P488,290.00) outside original scope.
– Completion of all roads: March 3, 2003.

Initial Billing and Demand

– Progress billing (Jan 10–Mar 3, 2003): P766,556.46.
– Unpaid; HSPCDC sent letters (Mar 26, 2003; Nov 11, 2003) demanding total due P2,122,704.55 (main contract P1,081,584.80; variations P552,829.75; duplex P488,290.00).
– Filed suit April 4, 2005 for sum of money, interest, attorney’s fees, litigation expenses, exemplary damages.

RTC Decision

– October 29, 2010: Judgment for HSPCDC—P44,270.94 (main contract balance), P552,829.75 (variations), P488,290.00 (duplex), 10% attorney’s fees, 12% annual interest from finality.
– Denied SDC’s counterclaims for expenses, damages, exemplary damages, litigation costs.
– November 18, 2011: RTC denied HSPCDC’s motion for partial reconsideration.

CA Decision

– August 16, 2016: Reversed and set aside RTC; ordered:

  1. SDC to pay HSPCDC P1,581,584.80 (contract balance) and P488,290.00 (duplex).
  2. HSPCDC to pay SDC P362,781.72 (well‐drilling), P359,503.80 (elevated water tank), and P1,050,000.00 (delay), with set‐off under Civil Code art. 1278 and 6% interest.
    – Excluded variation orders for lack of written authorization; upheld denial of basketball court claim; deleted attorney’s fees for lack of bad faith.
    – January 11, 2017: CA denied motions for reconsideration.

Issues on Review

  1. Whether HSPCDC should pay SDC P362,781.72 (well‐drilling) and P359,503.80 (water tank).
  2. Whether HSPCDC should pay P1,050,000.00 for delay.

Rule on Supreme Court Review

Under Rule 45 and the 1987 Constitution, the Court resolves questions of law. Factual findings will not be disturbed if supported by substantial evidence and not based on conjecture, misapprehension, or conflict with undisputed facts.

Liability for Well‐Drilling and Water Tank

– Both RTC and CA found HSPCDC failed to finish well‐drilling and steel water tank.
– HSPCDC admitted non‐completion despite contract obligating full performance of “water distribution and elevated steel water reservoir.”
– Pursuant to Civil Code art. 1167, defaulting contractor bears cost of completion by another.
– Substantial evidence (cost estimates, receipts, admissions) supports SDC’s claim.
– Holding




...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.