Title
H.S. Pow Construction and Development Corp. vs. Shaughnessy Development Corp.
Case
G.R. No. 229262
Decision Date
Jul 7, 2021
HSPCDC sued SDC for unpaid construction work; SC upheld liability for incomplete tasks but deleted delay penalty, citing SDC's changes and additional works.

Case Summary (G.R. No. 229262)

Factual Background

H. S. Pow Construction and Development Corp. is a construction corporation engaged by Shaughnessy Development Corporation pursuant to a written Construction Contract to perform subdivision concrete roads, underground drainage, water distribution, and an elevated water reservoir for the Summerfield Subdivision in Taytay, Rizal, for the contract sum of P10,500,000.00. Work commenced May 21, 2002, with a contractual completion period of 180 days and no escalation clause. During performance, HSPCDC undertook variation and rework items and, at the owner’s instruction, constructed three duplex units that were not part of the original scope.

Contractual Scope and Performance

The Contract expressly described the scope as including “PROPOSED CONSTRUCTION OF SUBDIVISION CONCRETE ROADS, UNDERGROUND RCP DRAINAGE SYSTEM, WATER DISTRIBUTION AND ELEVATED STEEL WATER RESERVOIR,” and obligated the contractor to “fully and faithfully perform all labor, furnish all tools, plants, equipment, all materials supervision and all incidental related to the work package being contracted and will do all things necessary for the proper construction and completion of all work shown and described in the Contract Document.” HSPCDC reported substantial completion of the road network by March 3, 2003, and submitted progress billings, but later complained of nonpayment and presented a Summary of Account asserting a principal balance due of P2,122,704.55 comprising the main contract balance, the three duplex houses, and variation orders.

Pleadings and Counterclaims

HSPCDC filed suit for sum of money to collect P2,122,704.55, interest, attorney’s fees, litigation expenses, and exemplary damages. SDC denied liability and counterclaimed for damages and expenses allegedly incurred due to HSPCDC’s delay and abandonment, alleging unfinished well-drilling and elevated water tank works, failure to build basketball court and sidewalks shown in the plans, and failure to issue a performance bond. SDC sought P50,000.00 for completion expenses, P728,067.80 as actual damages and penalties, P200,000.00 exemplary damages, and P100,000.00 litigation costs.

Trial Court Proceedings and Decision

After trial, the RTC rendered judgment in favor of HSPCDC. The RTC ordered SDC to pay HSPCDC P44,270.94 as the amount due on the main contract, P552,829.75 for variation works, and P488,290.00 for the duplex buildings, plus ten percent attorney’s fees and costs, with interest at 12% per annum from finality. The RTC found that HSPCDC did not incur delay, attributed delay allegations to the owner’s changes and other events, and held HSPCDC liable for the variation works and duplex houses while addressing SDC’s claims for expenses in completing unfinished items.

Appeals and Positions of the Parties

Both parties appealed to the Court of Appeals. HSPCDC contended that the RTC erred in limiting recovery under the main contract and sought correction of amounts awarded. SDC argued the RTC erred in finding it liable for variation orders, in failing to find HSPCDC delayed and abandoned work, in not accounting for work included in the signed plans, and in awarding attorney’s fees not pleaded. On appeal, SDC sought damages for work it completed after HSPCDC’s alleged abandonment, including well-drilling and the elevated steel water tank, and liquidated damages for delay.

Court of Appeals Ruling

The Court of Appeals reversed and set aside the RTC decisions and rendered a new judgment ordering mutual payments. The CA awarded HSPCDC P1,581,584.80 balance under the contract and P488,290.00 for the duplex houses, and ordered HSPCDC to pay SDC P362,781.72 for well-drilling, P359,503.80 for the elevated steel water tank, and P1,050,000.00 for delay, directing offsetting pursuant to Art. 1278, Civil Code and applying six percent interest per annum from finality. The CA reasoned that many of HSPCDC’s exhibits were excluded by the trial court and that the admitted evidence and admissions warranted the CA’s award on the well and tank; it also concluded that HSPCDC breached the contractual completion term and thus was liable for liquidated damages up to the contract ceiling.

Issues Presented to the Supreme Court

HSPCDC petitioned for certiorari under Rule 45, challenging the CA’s orders that it pay SDC P362,781.72 for well-drilling, P359,503.80 for the elevated water steel tank, and P1,050,000.00 for delay. HSPCDC argued lack of liability for the well and tank because SDC allegedly failed to secure necessary permits and because disbursement proof was lacking; it also argued that owner-caused changes excused the alleged delay. SDC responded that the issues are factual and not cognizable by the Supreme Court and complained that the CA awarded more than what HSPCDC prayed for.

Standard of Review and Applicable Exceptions

The Supreme Court recalled that under Rule 45 it generally resolves questions of law and may review factual findings only under recognized exceptions, such as findings based on conjecture, manifestly mistaken inferences, misapprehension of facts, findings contrary to admissions, or where the appellate court overlooked undisputed material facts. The Court emphasized that a question of law exists where resolution depends solely on legal rules without reviewing the probative value of evidence; issues necessitating reexamination of evidence are factual.

Supreme Court’s Analysis on Well-Drilling and Elevated Tank

The Supreme Court affirmed the RTC and CA findings that HSPCDC was liable for the well-drilling and the elevated water steel tank. The Court observed that HSPCDC admitted incomplete well-drilling because the owner did not secure the NWRB permit and that the Contract placed responsibility for the water distribution and elevated steel reservoir on the contractor. The RTC had compared the cost estimates and the actual amounts SDC spent to complete the works by others and determined the amount HSPCDC owed; the CA found sufficient evidence to uphold these conclusions. Applying Art. 1167, Civil Code, the Court held that a contractor who fails to do what it is obliged to do must bear the cost of completion, and that HSPCDC’s reasons did not excuse nonperformance given the contractual undertaking to perform all work shown and described in the Contract Document. Because the factual findings of the l

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.