Title
H.B. Zachry Company International vs. Court of Appeals
Case
G.R. No. 106989
Decision Date
May 10, 1994
VBC sued Zachry for unpaid construction work; writ of attachment issued before valid summons. Arbitration clause deemed ambiguous; trial court retained jurisdiction.
A

Case Summary (G.R. No. 106989)

Petitioners and Respondents

Petitioners: H.B. Zachry Company International (G.R. No. 106989) and Vinnel-Belvoir Corporation (G.R. No. 107124).
Respondents: The Court of Appeals and, respectively, the opposing contractual party in each petition.

Key Dates

  • Subcontract Agreement: 17 July 1987.
  • Supplemental Agreement: 18 December 1989.
  • VBC’s formal demand and claim steps culminating: January–March 1990.
  • RTC order granting application for writ of preliminary attachment (upon bond): 21 March 1990.
  • Writ of attachment issued: 26 March 1990; attempted service and levy: 27 March 1990 (sheriff’s returns dated 29 March 1990).
  • Valid service on resident agent (Atty. Lucas Nunag): 24 April 1990.
  • Complaint filed in RTC (VBC): 20 March 1990 (Civil Case No. 90-772).
  • Court of Appeals decision: 1 July 1992 (dissolved attachment; ordered hearing on arbitration interpretation).
  • Supreme Court decision (resolution of consolidated petitions): May 10, 1994.

Applicable Law and Authorities Considered

  • 1987 Philippine Constitution (applicable because decision date is after 1990).
  • Rules of Court (Rule 57 on attachment; Rule 14 on service of summons; Rule 16 on motions to dismiss).
  • R.A. No. 876 (Arbitration Act), especially Section 7 (stay of civil action where issue is referable to arbitration).
  • Corporation Code (Section 128) on appointment of resident agent for service of summons by foreign corporations).
  • Controlling jurisprudence discussed: Sievert v. Court of Appeals; Davao Light & Power Co. v. Court of Appeals; Cuartero v. Court of Appeals; other cited precedents addressing issuance versus enforcement of writs of attachment and the consequences of defective service.

Contractual Provisions Material to the Dispute

  • Section 3 (Payment) of the Subcontract Agreement: establishes a lump-sum price of US$6,468,000 subject to equitable adjustment for substantial differences and changes (refers to Section 6 on Changes).
  • Section 27 (Disputes Procedure): contains two relevant parts:
    • 27.A: binds the subcontractor to the contractor’s obligations and to decisions under the General Contract with the owner, including final decisions of courts when related to the subcontractor’s matters; requires subcontractor to cooperate in owner-contractor disputes; provides that disputes do not excuse progress of work.
    • 27.B: provides that controversies not controlled by 27.A or other subcontract provisions are to be decided as follows: (1) contractor’s written decision is binding unless subcontractor commences arbitration within thirty (30) days; (2) appeal by subcontractor goes to arbitration under Construction Industry Arbitration Rules of the American Arbitration Association, commenced not later than thirty (30) days after contractor’s written decision; (3) agreement to arbitrate is specifically enforceable.

Factual Background

VBC performed subcontract work and, by January 1990, computed a balance allegedly due of US$1,103,000 (including a $200,000 alleged withholding and a $282,000 labor escalation adjustment from the Navy). Zachry disputed indebtedness, purportedly raised quality-of-work complaints and took over management as allegedly authorized by the subcontract. The parties executed a Supplemental Agreement (18 December 1989) setting out retention of funds, cost-to-complete procedures, allocation of costs after takeover, and negotiation participation concerning change orders. Zachry allegedly refused to provide statements of accumulated costs and refused to pay the claimed balance. VBC pursued administrative remedies and then filed suit in the RTC (20 March 1990) seeking collection and a writ of preliminary attachment over Zachry’s bank account and undelivered housing units.

Procedural History in the RTC

VBC filed Civil Case No. 90-772 and applied for preliminary attachment; the RTC issued an order (21 March 1990) granting the application upon posting of a bond and the writ of preliminary attachment issued on 26 March 1990. The sheriff’s return indicates attempted service and levy on 27 March 1990 at Zachry’s field office in Subic Bay and attempts in Manila offices; the sheriff later served the resident agent on 24 April 1990. Zachry moved to dismiss for lack of jurisdiction (contending invalid initial service) and alternatively to dismiss or suspend proceedings for failure to submit to arbitration under Section 27.B. The RTC denied the motion (19 September 1990), and denied reconsideration (9 January 1991). Zachry sought certiorari and prohibition in the Court of Appeals.

Court of Appeals Ruling

The Court of Appeals (1 July 1992) granted certiorari in part: it dissolved the writ of preliminary attachment on the ground that it was issued prior to valid service of summons and a copy of the complaint and therefore in grave abuse of discretion; it ordered the trial court to conduct a hearing to determine proper interpretation of the Subcontract’s dispute resolution provisions (i.e., whether arbitration applied). Motions for reconsideration by both parties were denied by the Court of Appeals (resolution, 2 September 1992).

Issues Presented to the Supreme Court

  • Whether issuance of the writ of preliminary attachment prior to valid service of summons and a copy of the complaint was valid.
  • Whether resort to arbitration under Section 27.B of the Subcontract Agreement was required prior to filing suit in court.

Supreme Court Analysis — Writ of Preliminary Attachment: Issuance versus Enforcement

The Supreme Court distinguished the three-stage nature of attachment practice: (1) court order granting application; (2) issuance of the writ pursuant to the order; (3) implementation/levy of the writ. Citing Davao Light (and subsequent authorities), the Court affirmed that a trial court may issue an order granting attachment and may issue a writ even before it acquires jurisdiction over the defendant’s person; such issuance is not void. However, enforcement (levy or actions affecting the defendant’s property) cannot validly bind the defendant unless the court has acquired jurisdiction over the defendant’s person — through valid service of summons or voluntary submission. Service of the writ and related documents contemporaneous with levy must be valid to effect jurisdiction and to afford the defendant the opportunity to post a counterbond or otherwise oppose attachment. The Court found:

  • The 21 March 1990 order granting the application and the 26 March 1990 issuance of the writ were valid acts by the RTC.
  • The attempted levy on 27 March 1990 did not validly bind Zachry because the service of summons at that time was not valid: Zachry, as a foreign corporation licensed to do business in the Philippines, had designated a resident agent under the Corporation Code (Atty. Lucas Nunag), and service on other persons before service on the resident agent was inefficacious. Valid service upon Zachry’s resident agent occurred only on 24 April 1990. Thus the levy of attachment on 27 March 1990 was invalid.
  • The invalidity of enforcement did not render the prior issuance void; instead, the writ could validly be served and enforced anew after valid service on the resident agent.

Supreme Court Analysis — Arbitration Provision and Trial Court Discretion

On the arbitration issue, the Supreme Court examined Section 27 of the Subcontract Agreement and noted that Section 27.B purports to require arbitration for controversies that are not controlled or determined by Section 27.A or other subcontract provisions. The Court observed that the language of Section 27.B is ambiguous as to which controversies fall within its scope, especially because Section 27.B expressly excludes controversies governed by Section 27.A or other subcontract provisions, and those excluded provisions themselves raise interpretive questions. Given this lack of "indubitability" (i.e., the ground was not manifestly certain), the trial court acted within its discretion in deferring resolution of the arbitration question and denying dismissal at the motion-to-dismiss stage. The Supreme Court concluded:

  • The Court of Appeals erred in directing the trial court to conduct an immediate hearing to interpret the subcontract’s dispute resolution clause and thereby reopened a motion the trial court had properly deferred. The proper approach is for the trial court to determine the applicabili
...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.