Title
Fressel vs. Mariano Uy Chaco Sons and Co.
Case
G.R. No. 10918
Decision Date
Mar 4, 1916
In 1914, plaintiffs delivered materials to Merritt, an independent contractor, for a building project. Defendant took possession of materials but refused payment. Court ruled no agency or privity, dismissing the case.

Case Summary (G.R. No. 10918)

Key Dates and Applicable Law

Material events occurred in 1913–1914; the decision was rendered in 1916. The constitutional and statutory framework in force was that governing the Philippine Islands under U.S. administration (the Organic Act and the statutes then applicable), together with the Philippine Code of Civil Procedure provisions cited in the complaint analysis (notably section 106 regarding construction of pleadings). The Court applied prevailing rules on demurrer, pleading construction, agency, liability of owners for contractor purchases, and the absence of statutory mechanics’ liens.

Procedural Posture

The trial court sustained a demurrer to the complaint on the ground that it did not state a cause of action. Plaintiffs declined to amend, the case was dismissed, and the plaintiffs appealed. The appeal challenges the sufficiency of the complaint to establish liability on the defendant for materials supplied to Merritt.

Material Allegations of the Complaint

  • Defendant contracted with E. Merritt to build the edifice; the contract included a clause permitting the defendant, upon certain contingencies and before completion, to take possession of the building-in-progress and "of all the materials in and about said premises acquired by Merritt."
  • In August 1914 plaintiffs delivered specified materials (value P1,381.21, listed in Exhibit A) to Merritt at the construction site; Merritt agreed to pay on September 1, 1914.
  • On August 28, 1914 the defendant purportedly took possession of the incomplete edifice and all materials on the premises, including plaintiffs’ materials.
  • Neither Merritt nor the defendant paid; plaintiffs demanded payment and, failing that, demanded return or permission to retake unused materials on September 2, 1914, which the defendant refused.
  • The complaint also alleged (paragraph 6) that Merritt acted as the defendant’s agent in acquiring the materials.

Issues Presented

  1. Whether the complaint, as pleaded, sufficiently alleges facts establishing agency, ratification, or assignment such that the defendant became liable to plaintiffs for the materials supplied to Merritt.
  2. Whether the defendant’s act of taking possession of the building and materials converted it into a successor or assignee liable to creditors of the original contractor.
  3. Whether the pleading was legally sufficient to survive a demurrer under the standards governing admissible allegations.

Standard on Demurrer and Construction of Pleadings

The Court reiterated governing rules: a demurrer admits the truth of well-pleaded, material, and relevant facts but does not admit mere conclusions, inferences, or legal conclusions drawn by the pleader. Section 106 of the Code of Civil Procedure requires liberal construction of pleadings to achieve substantial justice, but ambiguities or contradictions favor the pleader’s adversary when dismissal follows refusal to amend. The Court cited Alzua and Arnalot v. Johnson to emphasize that conclusions of law or mere inferences are not admitted by a demurrer.

Court’s Analysis — Agency Versus Independent Contractor

The Court found that paragraphs 1–5 of the complaint, when read together, demonstrated Merritt’s status as an independent contractor rather than an agent of the defendant. The allegation that Merritt “undertook and agreed with the defendant to build for the defendant a costly edifice” implies authority to do the work according to Merritt’s methods and discretion (subject only to the result), including purchasing materials from suppliers of his choice. The plaintiffs’ own averment that Merritt agreed to pay them for the materials underscores that no contractual relation existed directly between the plaintiffs and the defendant. Thus the factual allegations point strongly to independent-contractor status.

Court’s Analysis — Effect of Contractual Clause Allowing Possession

The Court held that the contractual clause permitting the defendant to take possession of an incomplete building and materials upon certain contingencies did not transform Merritt into an agent or create owner liability for Merritt’s antecedent purchases. The Court illustrated the policy result by hypothetical: if a contractor had purchased large quantities of supplies on credit, treating the owner as liable would permit the contractor and his suppliers to dictate prices and terms to the owner—an outcome the law does not endorse absent express statutory or contractual undertaking.

Court’s Analysis — Assignment/Successor Liability

The Court rejected the argument that defendant’s taking possession made it a successor or assignee automatically liable to the contractor’s creditors. In the absence of facts showing an actual assumption of the contractor’s debts, a mere physical takeover of an incomplete structure and materials does not impose liability for prior purchases made by the independent contractor. The vendor may not enforce the contract against the assignee as readily as against the assignor unless there is evidence of assignment of obligations, assumption of debt, or other legal basis for successor liability.

Court’s Analysis — Mechanics’ Liens and Statutory Context

The Court emphasized that, absent a statute creating mechanics’ liens or a similar statutory remedy, an owner is not liable for materials purchased by an independent contractor. The opinion rests on the distinction between common-law liability and statutory liens that may create an owner's liability for unpaid contractors’ or suppliers’ claims; where no such statute exists, ordinary common-law principles control.

On the Allegation of Agency as a Conclusion

Paragraph 6’s allegation that “Merritt acted as the agent for defendant in the acquisition of the materials” was characterized by the Court as a mere conclusion inconsistent with the detailed factual averments in paragraphs 1–5. Because conclusions of agenc

    ...continue reading

    Analyze Cases Smarter, Faster
    Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.