Title
Floro vs. Llenado
Case
G.R. No. 75723
Decision Date
Jun 2, 1995
Floro allowed Llenado temporary use of his subdivision roads; barricade led to legal dispute over easement rights. Courts ruled no valid easement contract, denied compulsory easement, awarded Floro damages for property use.

Case Summary (G.R. No. 75723)

Key Dates and Procedural Posture

February 1983: verbal permission granted by Floro to Llenado to use Road Lots 4 and 5. April 7, 1983: Floro barricaded Road Lot 5. April 13, 1983: complaint for easement of right of way filed (Civil Case No. 6834‑M) with prayer for preliminary mandatory injunction. July 15, 1983: trial court issued preliminary mandatory injunction subject to bond. October 16, 1984: trial court dismissed complaint and awarded damages to Floro on counterclaim. February 11, 1986: Court of Appeals reversed, ordering creation of compulsory easement and awarding damages to Llenado while requiring Llenado to pay indemnity to Floro. Subsequent motions, partial execution pending appeal, and restraining order followed. Petition for review under Rule 45 was granted; decision date of the Supreme Court was June 2, 1995, applying the 1987 Constitution as the governing charter.

Legal Issues Presented

(1) Whether a valid voluntary contract of easement (right of way) was created by the verbal permission given by Floro to the Llenados. (2) Whether the Llenados, as owner/developer of a subdivision, could compel imposition of a compulsory easement of right of way over the existing roads (Road Lots 4 and 5) of the adjacent Floro Park Subdivision instead of developing the access road shown in their duly approved subdivision plan.

Governing Law and Standards of Review

Constitutional basis: 1987 Philippine Constitution applies (decision in 1995). Statutory and regulatory sources relied upon: Civil Code provisions on legal easement (Articles 649 and 650), Articles 2224–2225 on temperate damages, and Presidential Decree No. 957, Section 29 (developer duty to secure, develop and maintain right of way to public road). Standard of appellate review: Rule 45 confines the Supreme Court ordinarily to errors of law; however, established exceptions permit review of Court of Appeals’ findings of fact when certain conditions (e.g., grave abuse of discretion, findings manifestly mistaken, conflicts with trial court findings) exist — the Court found such an exception here and examined the factual record.

Voluntary Easement: Factual and Legal Findings

The Court found no perfected voluntary contract of easement. The parties admitted that usage in March 1983 was by Floro’s verbal tolerance while Floro’s lawyer would prepare documentation; the Llenados themselves testified that terms were to be drafted and no compensation had been agreed or paid. Floro’s later imposition of conditions (allegedly requiring security, roadway improvements at Llenado’s expense, planting, payment of street lighting, construction of a bridge) was contested and rejected by Orlando as onerous. The Court applied precedent (Dionisio v. Ortiz) and concluded that mere tolerance or a temporary oral allowance, without agreement on essential terms (notably compensation), does not constitute a valid voluntary easement.

Compulsory Easement: Legal Requirements and Burden

To establish a compulsory (legal) easement under Articles 649 and 650, the dominant estate owner must prove: (1) the tenement is surrounded by other immovables and has no adequate outlet to a public highway; (2) payment (or prepayment) of proper indemnity; (3) the isolation was not due to acts of the dominant estate’s proprietor; and (4) the claimed right of way is at the point least prejudicial to the servient estate, and, insofar as consistent, the shortest route. The burden to prove these prerequisites rests squarely upon the party claiming the legal easement.

The Ipapo Access Road and the Adequacy of Outlets

The Court emphasized that the approved subdivision plans of Emmanuel Homes (later Llenado Homes) — submitted to and approved by the Human Settlement Regulatory Commission (HSRC) — showed an access road across the Ipapo riceland. HSRC testimony established that the access road need not be paved but the developer must secure consent and develop the right of way; approval was conditioned upon showing a right of way clearance from Ipapo. The Llenados adopted the Emmanuel Homes plan, retained the Ipapo access in their Consolidation Subdivision Plan, applied for and received licenses permitting development, and later sought amendments. The existence of that planned right of way meant the Llenado subdivision was not without an alternative outlet, and thus the first prerequisite (no adequate outlet) was not satisfied.

Failure to Prepay or Seek Fixing of Indemnity

Article 649 requires payment of proper indemnity; judicial precedent clarifies that prepayment means delivery of proper indemnity or at least a prayer within the action seeking judicial fixing of the indemnity when voluntary agreement fails. The Court found that Llenado’s complaint did not pray for judicial fixing of the indemnity, nor did he present proof of compliance with this requisite. Failure to seek or secure indemnity precluded satisfaction of the second prerequisite.

Causation of Isolation and Developer’s Own Acts

The Court found that the isolation of the Llenado Homes Subdivision resulted from the acts or omissions of the subdivision owner/developer. Evidence showed the Ipapo right of way was procured (by earlier owner) and retained in the approved plan but not developed into even a dirt road. The Court considered the applicant’s failure to develop the planned access road — despite the relative absence of cultivation on the Ipapo riceland and presence of only an adobe fence — as a voluntary choice to avoid inconvenience and expense. Because the alleged lack of access derived from the dominant owner’s own conduct, the third prerequisite was not met.

Necessity Versus Mere Convenience; Public Policy Considerations

The Court reiterated controlling jurisprudence that compulsory servitudes require real necessity, not mere convenience. Prior cases (e.g., Ramos v. Gatchalian, Rivera v. IAC, Costabella) were cited to show that an alternative outlet, even if inconvenient or undeveloped, will ordinarily defeat a request for a compulsory easement. The Court also cautioned against permitting a practice whereby developers include fictitious access provisions in subdivision plans to secure approval and later abandon development, then seek compulsory easements over neighboring properties — a result contrary to the purpose of PD No. 957 to protect subdivision buyers and to require owners/developers to develop access shown in approved plans.

Rejection of New Evidence Considered by Court of Appeals

The Court held that the Court of Appeals erred in considering a July 3, 1985 letter from Marcial Ipapo (asserting non-co

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.