Title
Flavio K. Macasaet and Associates, Inc. vs. Commission on Audit
Case
G.R. No. 83748
Decision Date
May 12, 1989
Petitioner entitled to 7% of escalation costs as part of "final actual project cost" per contract terms, despite no additional work performed.
A

Case Summary (G.R. No. 83748)

Petitioner

Flavio K. Macasaet & Associates, Inc. sought payment of an additional professional fee equal to seven percent (7%) of an escalation sum of P3,148,198.26 that PTA paid to the main contractor (Supra Construction Company) after project completion. The petitioner’s claimed additional amount was P219,302.47.

Respondents

Philippine Tourism Authority (PTA) refused the additional payment, contending that the price escalation reflected increased material costs and did not entail additional work by the petitioner. The Commission on Audit (COA) affirmed denial on the ground that, absent a showing that extra services were rendered, allowance of the claim would amount to an improper overpayment.

Key Dates

  • Contract execution: 15 September 1977 (originally with Flavio K. Macasaet personally, later with petitioner corporation).
  • PTA denial of additional payment: 3 July 1985.
  • Administrative endorsements and COA decision occurred prior to the petition to the Supreme Court.
  • Supreme Court decision: May 12, 1989 (proceeding under the 1987 Constitution provision invoked by the parties).

Applicable Law

  • Section 7, Article IX, 1987 Constitution (right to bring certiorari from decisions, orders, or rulings of each Commission).
  • Civil Code provisions invoked by the Court: Article 1370 (literal meaning of agreements controls when terms are clear) and Article 1159 (obligations arising from contracts have the force of law between the parties and must be performed in good faith).
  • Contractual provisions forming the basis of petitioner’s claim: Article IV and Article V (defining professional fee as seven percent of actual construction cost and prescribing schedule of payments culminating in computation on the “final actual project cost”) and Article VI (dealing with change orders and additional compensation for extra work).

Contractual Provisions Relevant to the Dispute

  • Article IV: the designer’s professional fee is seven percent (7%) of the actual construction cost.
  • Article V: establishes a schedule of partial payments during design stages calculated on a reasonable estimated construction cost; paragraph 5 requires payment of the balance upon completion and acceptance, “computed on the final actual project cost.”
  • Article VI: addresses additional compensation only where the Authority orders a major change in planning/engineering after designs are completed and such change results in additional work.

Factual Background and Payments

PTA made periodic payments to petitioner in accordance with the schedule in Article V. Upon project completion, PTA paid what it considered the balance of the professional fee. Subsequently, PTA paid the main contractor an additional P3,148,198.26 as escalation for increased construction material costs. Petitioner then claimed seven percent (7%) of that escalation amount as additional professional fees (P219,302.47). PTA denied the claim on the ground the escalation did not represent additional work by petitioner and thus did not trigger extra compensation under Article VI.

Claim and Administrative Determinations

Petitioner sought reconsideration administratively and then before COA. COA denied the claim, reasoning that absent a showing of extra or additional services rendered by petitioner, allowing the claim would result in overpayment to the prejudice of the government. Petitioner then filed a petition for certiorari with the Supreme Court.

Legal Issue

Whether the price escalation paid to the contractor should be included in the “final actual project cost” for purposes of computing the balance of the petitioner’s professional fee under the contract, thereby entitling petitioner to an additional seven percent.

Parties’ Contentions

  • Respondents: The professional fee had been fully paid; petitioner rendered no additional architectural services beyond those contracted, so no further fee is due. Article VI governs additional compensation for additional work and was not implicated.
  • Petitioner: The contractual language (Article IV and the final clause of Article V) ties the professional fee to the “actual construction cost” and directs the balance to be computed on the “final actual project cost,” so any post-contract adjustments to the project cost (including escalations) must be included in the final basis for computing the fee; entitlement does not depend on additional services.

Court’s Contractual Interpretation

The Court emphasized the plain meaning of the contract terms. Article IV defines the fee as seven percent of the “actual construction cost,” while Article V(5) requires that the balance be computed on the “final actual project cost.” The Court construed these terms as intentionally broader and sequential: periodic payments are based on a “reasonable estimated construction cost,” but the ultimate adjustment is to be made on the “final actual project cost,” which contemplates the totality of costs as finally determined. The Court held that “final actual project cost” logically includes escalation costs that alter the ultimate contract price, even if those costs do not reflect additional work by the designer.

Relevance of Article VI

Article VI concerns additional compensation for major changes in planning or engineering that result in additi

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.