Title
1st Metro Investment Corp. vs. Este Del Sol Mountain Reserve, Inc.
Case
G.R. No. 141811
Decision Date
Nov 15, 2001
FMIC granted Este del Sol a loan with excessive fees and penalties. Court ruled agreements concealed usurious interest, penalties excessive; FMIC ordered to reimburse excess interest.

Case Summary (G.R. No. 262938)

Petitioner

First Metro Investment Corporation extended financing to Este del Sol for development of a sports/resort complex and also entered into contemporaneous underwriting, supervision and consultancy agreements with the borrower.

Respondents

Este del Sol Mountain Reserve, Inc. (borrower) and its individual continuing sureties who guaranteed payment up to P7,500,000 each pursuant to separate continuing suretyship agreements.

Key Dates

  • Loan and related agreements executed: January 31, 1978.
  • Billing for fees: letters dated February 22, 1978 (deducted from first loan release).
  • First partial release of loan: February 22, 1978 (P2,382,500.00).
  • Statement of account reflecting default totals: June 23, 1980.
  • Extrajudicial foreclosure and sheriff’s sale: June 23, 1980 (FMIC highest bidder at P9,000,000).
  • Collection suit filed: November 11, 1980.
  • Trial court decision in favor of FMIC: June 2, 1994.
  • Court of Appeals reversal: November 8, 1999.
  • Supreme Court decision (affirming CA): November 15, 2001.

Applicable Law

The 1987 Constitution governs the legal framework applicable to this decision (decision date is 2001). Primary substantive provisions applied in the ruling include the Usury Law as in force at the time of contract, relevant provisions of the New Civil Code (notably Articles 1229, 1957 and 2227), and procedural rules regarding admissibility of parol evidence (Rule 130, Section 3). Central Bank Circular No. 905 (effective January 1, 1983) and its relation to the Usury Law were considered but not held to retroactively validate otherwise usurious transactions entered in 1978.

Loan and Security Terms

FMIC granted a loan to Este del Sol in the principal amount of P7,385,500.00 to finance the development project. Interest was stipulated at 16% per annum on the diminishing balance, payable in 36 equal monthly amortizations to commence at the beginning of the thirteenth month from first release. Default provisions included acceleration, a one-time 20% penalty on the amount due, interest at the highest rate permitted by law from default, liquidated damages at 2% per month compounded quarterly on unpaid balance and accrued interest plus attorney’s fees of 25% of the sum sought (minimum P20,000 if counsel were engaged). Collateral and guarantees included a real estate mortgage over two parcels (approx. 1,028,029 sq.m., TCT Nos. N-24332 and N-24356) and individual continuing suretyship agreements of the named respondents.

Underwriting, Supervision and Consultancy Agreements and Billing

Simultaneously with the loan, Este del Sol executed: an Underwriting Agreement (FMIC to underwrite on best-efforts basis 120,000 common shares for a one-time underwriting fee of P200,000; supervision fee P200,000 per annum for four years) and a Consultancy Agreement (consultancy fee stated at P332,500 per annum for four years, with first-year fee due upon signing). On February 22, 1978 FMIC billed Este del Sol P200,000 (underwriting fee), P200,000 (first-year supervision fee) and P1,330,000 (consortium-stated consultancy fee billed as a lump amount representing four years), and deducted those amounts from the first partial loan release, effectively causing the lender to recapture P1,730,000 of the loan proceeds as purported fees.

Performance of Ancillary Agreements

The Court of Appeals and the Supreme Court found that FMIC failed to perform obligations under the underwriting and consultancy agreements: FMIC did not successfully organize an underwriting/selling syndicate nor did it meaningfully supervise such a syndicate; Este del Sol’s own marketing arm sold its shares. The consultancy functions were likewise not meaningfully rendered, and the borrower’s officers were reportedly competent to handle the project without the claimed consultancy services.

Default, Account Statement and Foreclosure Sale

Because Este del Sol defaulted under the revised amortization schedule, FMIC’s statement of account as of June 23, 1980 showed total obligations of P12,679,630.98 (including accumulated interest, penalties and past-due interest at escalating rates), prompting extrajudicial foreclosure. At auction FMIC bid P9,000,000; deductions for publication (P4,964), sheriff’s fees (P15,000) and attorney’s fees (P3,168,666.75) left P5,811,369.25 applied to interest, penalties and partly to principal, leaving an unpaid principal balance of P6,863,297.73 as of June 23, 1980, which FMIC sought to recover from the borrower and sureties.

Trial Court Judgment and Subsequent Appeals

The Regional Trial Court rendered judgment in favor of FMIC, ordering joint and several liability of defendants for P6,863,297.73 plus 21% interest per annum from June 24, 1980, plus attorney’s fees (25% of the amount) and costs. Defendants’ counterclaims were dismissed. The Court of Appeals reversed, finding the ancillary fee agreements to be subterfuges to camouflage usurious interest and ruling that stipulated penalties, liquidated damages and attorney’s fees were excessive. The CA reduced the penalty and attorney’s fees (to a one-time 20% penalty on amount due and 10% attorney’s fees of the foreclosure proceeds) and ordered FMIC to reimburse Este del Sol an aggregate net amount of P971,000 based on its computations. FMIC’s motion for reconsideration in the CA was denied.

Issues Presented to the Supreme Court

FMIC’s petition for review challenged principally factual and legal conclusions of the CA, asserting among others that: the underwriting and consultancy agreements were separate and independent contracts; the CA wrongly characterized those agreements as devices to cloak usury; trial testimony and proof of services rendered were improperly disregarded; respondents had waived recovery or admitted the agreements’ validity; the CA made erroneous post-foreclosure computations; and respondents remained obligated to FMIC.

Standard of Review and Approach to Factual Findings

The Supreme Court reiterated that it is not a trier of facts and generally will not re-examine factual findings established by the trial and appellate courts. Only if findings of fact are in conflict between the trial and appellate courts or if findings are unsupported by record will the Supreme Court reweigh evidence. After reviewing the record, the Court found no reason to depart from the Court of Appeals’ factual determinations.

Central Bank Circular No. 905 and Retroactivity

FMIC argued that Central Bank Circular No. 905 (effective January 1, 1983) removed ceilings on interest rates and should retroactively validate the loan terms. The Supreme Court rejected retroactive application. It applied the elementary contract rule that the law in force at the time the contract was made governs the contract. Circular No. 905 did not repeal the Usury Law; it merely suspended its effectivity and a circular cannot repeal a statute. Therefore the Usury Law as in force in 1978 governed the transaction and Circular No. 905 could not validate otherwise usurious stipulations made in 1978.

Parol Evidence and Substance Over Form

The Court reiterated that written instruments generally constitute the best evidence of contractual terms, but the rule is subject to exceptions where written form is used as a cloak to conceal usury. Parol evidence is admissible to show that a written instrument was a device to cover usurious interest. If, from the entire transaction, a corrupt intention to evade the Usury Law is apparent, courts will not permit artful devices to cloak usury. The Court found multiple indicia (temporal coincidence of agreements, condition precedent language in the loan agreement, contemporaneous billing and deduction of

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.