Title
EPG Construction Co., Inc. vs. Court of Appeals
Case
G.R. No. 103372
Decision Date
Jun 22, 1992
EPG Construction failed to repair defective air-conditioning units in UP Law Library despite guarantee provision, held liable for damages; corporate president absolved.

Case Summary (G.R. No. 103372)

Contractual Guarantee and Acceptance of Work

The contract between EPG Construction and UP included a guarantee clause obligating EPG to repair defects within one year from the substantial completion of the project. The guarantee also held EPG liable under Article 1723 of the Civil Code for up to 15 years if the building collapses due to defective construction or inferior materials. Upon completion, UP issued a certificate of acceptance on January 13, 1983, asserting that the work was satisfactorily completed without defects, and recommended release of the 10% retention money. Despite this, UP later reported defects in six air-conditioning units, which EPG initially agreed to repair but ultimately did not. UP then contracted a third party to fix the defect and sought reimbursement plus liquidated damages from EPG.

UP’s Certificate of Acceptance Does Not Bar Later Claims

The petitioners argued that UP’s certificate of acceptance waived the one-year guarantee and that UP was estopped from claiming defects thereafter. This argument was rejected. The Court explained that the certificate only confirmed that the building was defect-free at the time of turnover, without releasing EPG from subsequent liability under the contract. Acceptance does not relieve a contractor from liability for hidden defects unknown and not recognizable by the employer at acceptance, especially where there was an express reservation of rights during the guarantee period, as provided under Article 1719 of the Civil Code.

Defects Not Caused by Force Majeure or Maintenance Lapses

EPG claimed that the defects were due to frequent power outages (brownouts) constituting force majeure or fortuitous events, or due to UP’s failure to perform maintenance. The Court found these arguments unmeritorious. Brownouts were held not to constitute force majeure, and inspection revealed that the defects resulted from poor workmanship and defective installation of the electrical components of the air-conditioning units. Furthermore, whether the needed repairs were maintenance or actual defects was a factual question resolved by the lower courts, and there was no clear showing of error warranting reversal.

Separate Legal Personality of Emmanuel P. De Guzman

The petitioners contended that Emmanuel P. De Guzman, as President of EPG, should not be held personally liable since a corporation is a distinct legal entity separate from its officers and shareholders. The Court agreed, emphasizing the established doctrine that corporate acts are imputable to the corporation, not to its office

...continue reading

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources. AI digests are study aids only—use responsibly.