Title
Engineering and Machinery Corporation vs. Court of Appeals
Case
G.R. No. 52267
Decision Date
Jan 24, 1996
A 1962 contract for an air-conditioning system led to a 1971 lawsuit over hidden defects, with the court ruling the contract was a "piece of work," subject to a ten-year prescriptive period, and holding the contractor liable despite prior acceptance and payment.
A

Case Summary (G.R. No. 52267)

Procedural History

Trial court: Court of First Instance of Rizal, Branch II (Civil Case No. 14712) — decision finding petitioner failed to install items required by the contract and deviated from specifications, ordering payment for rectification plus damages, attorney’s fees and costs. Court of Appeals: affirmed the trial court’s decision. Supreme Court: petition for review on certiorari under Rule 45; petition denied and the Court of Appeals decision affirmed.

Facts Found by the Courts Below

Petitioner undertook fabrication and installation of an air‑conditioning system, supplying materials, labor and tools. After re‑possession in 1971 private respondent learned from NIDC employees of system defects and commissioned a technical evaluation which concluded the system could not maintain the required room temperature (76°F ± 2°F) and listed numerous defects and omissions from the contract specifications (including missing dampers, lack of fresh air provisions, unsuitable compressors, corroded parts and absence of several specified components). The trial court credited these findings and held that omissions and deviations materially reduced the system’s operational effectiveness, necessitating auxiliary window units.

Issues Presented

  1. Whether the contract for fabrication and installation was a contract of sale or a contract for a piece of work.
  2. If a contract for a piece of work, what prescriptive period governs actions for breach or for remedies related to defects.
  3. Whether acceptance of the work and payment of the contract price precluded liability for defects alleged by private respondent.
  4. Whether the alleged defects were patent and discoverable at acceptance or hidden and therefore actionable later.

Parties’ Contentions

Petitioner argued: (a) acceptance of the work and full payment extinguished liability; (b) defects, if any, were apparent and should have been discovered earlier; (c) prescription of six months under Article 1571 (by reference to Articles 1566 and 1567 on warranty against hidden defects) applies. Private respondent contended that the contract was one for a piece of work governed by Article 1713 et seq., that the action was for breach of the written contract and thus timely under the ten‑year prescriptive period for actions upon written contracts (Article 1144), and that factual questions (acceptance, discoverability of defects) had been correctly decided by the lower courts.

Governing Legal Provisions Recognized by the Court

  • Article 1713 (contract for a piece of work): contractor binds himself to execute a work for a price; contractor may furnish materials.
  • Article 1714: where contractor furnishes the material and delivers the produced thing, the contract is also governed by rules on warranty of title and hidden defects.
  • Article 1715: contractor’s obligation to execute work with agreed qualities and without defects; employer may require remedy or replacement, and if contractor fails, employer may have defects removed at contractor’s cost.
  • Articles 1561 and 1566 (warranty against hidden defects in sale): vendor’s responsibility for hidden defects and exceptions for patent defects or where vendee is an expert.
  • Article 1571 and related articles (prescriptive period for redhibitory action): six months as to certain implied warranties; however, express warranties govern when provided.
  • Article 1389 (general rule on rescission): four‑year prescriptive period where applicable.
  • Article 1144: actions upon a written contract prescribe in ten years.

Nature of the Contract — Court’s Determination

The Court adopted the lower courts’ finding that the transaction was a contract for a piece of work rather than a sale. The decisive criterion was that the petitioner’s business was not the sale of manufactured air‑conditioning systems off the shelf; instead petitioner fabricated and installed systems according to particular plans and specifications provided by customers. The court emphasized that where the object would not have existed but for the order, the contract is for a piece of work.

Characterization of the Action and Applicable Prescription

Although the contract was a piece of work and Articles 1714–1715 apply, the Court analyzed the nature of the claim and concluded the complaint was not principally a redhibitory action enforcing warranties against hidden defects but a suit for breach of the written contract alleging failure to comply with particular specifications and omitted installations. Because the action is for breach of a written contract and Article 1715 contains no specific prescriptive period, Article 1144 (ten‑year prescriptive period for actions upon a written contract) governs. The contract (September 10, 1962) and the filing of the complaint (May 8, 1971) placed the action well within the ten‑year period; consequently, it had not prescribed.

Acceptance, Discoverability of Defects, and Liability

The Court accepted the lower courts’ factual determinations that the defects and deviations from specifications were not apparent at the time of delivery and acceptance and that private respondent, being not an expert, could not by simple inspection

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.