Title
ECE Realty and Development, Inc. vs. Herdez
Case
G.R. No. 212689
Decision Date
Aug 6, 2014
Buyer paid for 30 sqm condo, received 26 sqm; developer failed to deliver on time, sold unit to third party. Buyer reimbursed with 6% interest, attorney’s fees awarded.

Case Summary (G.R. No. 212689)

Factual Background

Respondent alleged that ECE and Emir Realty and Development Corporation (EMIR) were involved in the condominium development and marketing of Harrison Mansion. Under the parties’ arrangement, ECE and EMIR promised to deliver to respondent a 30-square meter condominium unit referred to as Unit 808.

Respondent paid a reservation fee of P35,000.00 on July 22, 1997, and on August 2, 1997, he paid P104,063.65 to complete the downpayment. The Contract to Sell dated November 5, 1997 stated a projected occupancy or readiness date of December 31, 1999. Respondent claimed that ECE and EMIR failed to deliver Unit 808 by December 31, 1999, despite his having already paid a total of P452,551.65.

Respondent further asserted that he later discovered the unit measured only 26 square meters, instead of 30 square meters as contracted. He requested a corresponding reduction in price of P120,000.00, computed using the contracted price per square meter of P30,000.00. ECE and EMIR instead demanded that he settle all amortizations in arrears with interest.

Respondent also alleged that in 2005 he learned that ECE and EMIR had sold Unit 808 to a third party.

HLURB Complaint and Requested Relief

Respondent filed his HLURB complaint seeking orders against EMIR and ECE to accept the balance of the unit’s price after deducting P120,000.00, without interest. He likewise sought various forms of damages and attorney’s fees. In the alternative, if Unit 808 was no longer available, respondent requested reimbursement of P452,551.65, plus legal interest.

Defenses Raised by ECE and EMIR; Cancellation Theory

In their Answer with Counterclaim, ECE and EMIR sought dismissal for lack of cause of action and prayed for the dismissal of EMIR because it allegedly had no contractual relations with respondent. They claimed that respondent unjustifiably refused to accept turnover of Unit 808 and that he had been issued a Grace Period Notice stating that he was in arrears on monthly amortizations, but he allegedly allowed the grace period to lapse without settling past-due amortizations.

ECE and EMIR invoked Republic Act No. 6552 and asserted that ECE was compelled to cancel respondent’s contract to sell. They also sought exemplary damages, attorney’s fees, and litigation expenses.

Administrative Findings: HLURB-Regional Office and HLURB Board of Commissioners

On May 12, 2008, the HLURB-Regional Office ordered ECE and EMIR to reimburse respondent P452,551.65, plus legal interest from the filing of the complaint. It also awarded respondent P50,000.00 as moral damages, P50,000.00 as attorney’s fees, and P50,000.00 as exemplary damages.

ECE and EMIR appealed to the HLURB Board of Commissioners, which, in its Decision dated January 23, 2009, upheld the Regional Office ruling but dropped EMIR as a defendant.

OP Review and CA Affirmance with Modification

ECE appealed to the OP. The OP dismissed ECE’s appeal in a Decision dated January 10, 2011, and on July 5, 2011, it denied ECE’s motion for reconsideration.

ECE then elevated the controversy to the Court of Appeals, insisting that the OP erred in affirming the rescission-related relief and refund with legal interest from the filing of the complaint, together with moral and exemplary damages and attorney’s fees. ECE argued that respondent did not ask for rescission and refund due to delayed delivery but only sought a reduction in price. ECE also argued that interest could be imposed only from the time the judgment becomes final. It further denied bad faith and claimed the damages and attorney’s fees were excessive.

The Court of Appeals affirmed the OP decision with modification. The CA directed ECE to refund respondent P452,551.65 plus six percent (6%) interest per annum starting September 7, 2006, and twelve percent (12%) interest per annum from the time the judgment becomes final and executory until fully paid. The CA later deleted the award of moral and exemplary damages, finding no bad faith on ECE’s part, but it sustained the award of attorney’s fees of P50,000.00 pursuant to Article 2208 (2) of the Civil Code, reasoning that ECE’s act or omission compelled respondent to litigate.

In sustaining the refund obligation, the CA relied on Section 23 of P.D. No. 957, which provides that payments made by a buyer in a condominium or subdivision project shall not be forfeited when the buyer, after due notice, desists due to the owner’s failure to develop within the agreed period. The CA treated the facts as falling squarely within that provision because ECE failed to deliver Unit 808 on or before December 31, 1999, and the unit was also found to be smaller than promised. The CA noted that ECE’s own evidence showed that Unit 808 was ready for inspection only on June 28, 2002, or about two and a half years after the agreed delivery date.

On interest, the CA cited Eastern Shipping Lines, Inc. v. Court of Appeals and Fil-Estate Properties, Inc. v. Spouses Go, concluding that the refunded amount was not a loan or forbearance of money, goods, or credit, and therefore applied interest in line with the Civil Code and the established guidelines.

Issues Presented to the Court

ECE maintained before the Court that the CA and OP erred in: sustaining the refund of respondent’s payments; imposing interest from the filing of the complaint; awarding attorney’s fees; and deleting or maintaining certain damages. The principal challenge carried through to the Supreme Court focused heavily on the propriety of the interest rate and the timing of the accrual of interest, especially after finality of judgment.

Legal Basis and Reasoning of the Court

The Court affirmed the CA decision with modification, but it reduced the interest imposed after finality from twelve percent (12%) to six percent (6%).

The Court anchored its ruling on Article 2209 of the Civil Code, which states that when an obligation consists in the payment of a sum of money and the debtor incurs delay, the indemnity is the stipulated interest, and in the absence of stipulation, the legal interest is six percent (6%) per annum. The Court held that there was no doubt that ECE incurred delay in delivering the condominium unit, thus justifying the award of interest to respondent from the filing of the complaint.

The Court then applied the guidelines laid down in Eastern Shipping Lines, Inc. v. Court of Appeals. Under those rules, the twelve percent (12%) rate applies only to loans or forbearance of money, goods, or credit, or judgments involving such loan or forbearance; in contrast, where the obligation breached does not constitute a loan or forbearance, legal interest may be imposed at the rate of six percent (6%) per annum on the amount of damages awarded, and the interest runs from the time the claim is made judicially or extrajudicially once the demand is established with reasonable certainty, but if not reasonably ascertainable, from the date of judgment.

The Court also discussed the doctrinal clarification in Sunga-Chan, et al. v. Court of Appeals, et al. and reiterated that Central Bank Circular No. 416’s twelve percent (12%) rate applied only in cases involving loan or forbearance, whereas transactions involving damages arising from default in obligations, or money judgments not involving loan or forbearance, fall under Article 2209 and its six percent (6%) interest. The Court emphasized that upon finality, the legal interest rate should be determined according to the nature of the obligation and the governing rate.

The Court recognized that Central Bank Circular No. 416, together with later adjustments, had resulted in the twelve percent (12%) interim rate from finality until satisfaction in earlier jurisprudence, but it noted that the current regulatory framework had reverted the rate for loan or forbearance and judgments, in the absence of an express contract, back to six percent (6%). Specifically, the Court cited

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.