Title
Supreme Court
Dupasquier vs. Ascendas Corp.
Case
G.R. No. 211044
Decision Date
Jul 24, 2019
A dispute over an MOU's arbitration clause and due diligence L/C, with the Supreme Court ruling the clause expired upon MOU lapse, declaratory relief was proper, and summary judgment appropriate.

Case Summary (G.R. No. 211044)

Relevant Agreements and Contractual Provisions

The MOU provided for a Closing Date defined as two calendar weeks after the signing of the Memorandum of Agreement (MOA), but not later than March 31, 2007. The parties intended the MOA to supersede the MOU upon execution. A key security instrument was the Due Diligence Letter of Credit (L/C) in the amount of US$1,000,000, to be delivered by Ascendas to The Net Group within five business days upon the signing of the MOU. Clause 5 of the MOU stipulated the conditions under which The Net Group might draw on the Due Diligence L/C, serving as liquidated damages should Ascendas fail to sign the MOA without justifiable cause. The MOU included an Arbitration Clause in Clause 14, specifying that any dispute arising out of or in connection with the MOU would first be negotiated in good faith and, failing resolution within 30 days, referred to arbitration under the rules of the United Nations Commission of International Trade Law, to be held in Hong Kong with the English language.

Events Leading to Litigation

Despite due diligence carried out by Ascendas, the MOA and Definitive Agreements were not signed by March 31, 2007, nor was there any written agreement extending the Closing Date. The Net Group subsequently declared the MOU lapsed as of April 1, 2007, indicating willingness to continue negotiations on a voluntary, non-exclusive basis. Ascendas, however, maintained that the MOU had not expired, alleging The Net Group caused delays, and threatened compulsory arbitration. In response, The Net Group filed a petition for declaratory relief with an application for a temporary restraining order (TRO), seeking judicial declaration that the arbitration clause was no longer effective post-lapse of the MOU and that they were entitled to the US$1,000,000 Due Diligence L/C.

Procedural History and Court Decisions

The Regional Trial Court (RTC) in Makati City granted a TRO in favor of The Net Group and, upon summary judgment, declared Ascendas could not compel arbitration and ruled The Net Group was entitled to the Due Diligence L/C. Ascendas appealed to the Court of Appeals (CA), which reversed the RTC decision. The CA applied the doctrine of separability, holding the arbitration clause remained operative even if the MOU expired, barring the RTC from exercising jurisdiction. The CA also viewed The Net Group’s petition as procedurally improper, arguing that declaratory relief was unavailable given the alleged breach of the MOU. A motion for reconsideration at the CA was denied by a majority, prompting The Net Group to file a petition before the Supreme Court.

Interpretation of the Arbitration Clause and Contractual Effectivity

The Supreme Court applied Article 1370 of the Civil Code, emphasizing that when contractual terms are clear and unambiguous, their literal meaning governs. The MOU’s Effectivity Clause expressly stated that the MOU would lapse or terminate upon the occurrence of certain events—specifically, the failure to execute the MOA by March 31, 2007—except for the Confidentiality Clause, which was to survive. Because the parties expressly limited the MOU’s effective period, including its provisions, the Court held the Arbitration Clause was likewise time-limited and ceased to have effect with the lapse of the MOU. The Court distinguished this case from earlier precedents upholding the separability doctrine by highlighting the presence of an explicit termination provision regarding the Arbitration Clause. Hence, the manifest intent of the parties was that the arbitration clause would not survive the MOU’s expiration.

Application of the Separability Doctrine

While the separability doctrine generally provides that an arbitration agreement is distinct and may survive invalidity or termination of the main contract, the Court clarified that this is subject to the parties’ express agreement. Here, the parties explicitly indicated which provisions would survive the MOU's termination. Drawing guidance from foreign jurisprudence, specifically the Rhode Island Supreme Court’s ruling in Radiation Oncology Associates, the Court recognized that the explicit termination date and survival clause control over any broad arbitration language. Therefore, the arbitral forum was not a mandatory condition precedent once the MOU lapsed without extension or renewal.

Nature and Entitlement to the Due Diligence Letter of Credit

The Court analyzed the Due Diligence L/C’s nature as per the MOU’s provisions, examining Clauses 4 and 5 alongside the Transaction Timeline. It identified two plausible interpretations: (1) The Due Diligence L/C would be drawn only if Ascendas failed to sign the MOA without justifiable cause, constituting liquidated damages; or (2) Ascendas could opt not to sign, enabling The Net Group to draw the L/C, with this sum serving as remuneration for conducting due diligence rather than a penalty. The Court favored the latter interpretation based on the parties’ contractual language, the purpose of the L/C as remuneration for allowing audit access, and the structure of the MOU’s timeline. It likened this to the concept of reverse break-up fees in mergers and acquisitions, which serve as compensation where the buyer withdraws from the deal.

Declaratory Relief’s Appropriateness and Jurisdiction

Contrary to the CA’s ruling, the Supreme Court found The Net Group’s petition for declaratory relief proper. The petition did not allege an actual breach but sough


...continue reading

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources. AI digests are study aids only—use responsibly.