Title
Department of Health vs. Pascua
Case
G.R. No. 212894
Decision Date
Mar 4, 2020
DOH and JDLC disputed Fabella Hospital Project bidding; RTC ordered award to JDLC, but SC dismissed case as moot after NTP issuance and project commencement.
A

Case Summary (G.R. No. 212894)

Procurement and Bidding Antecedents

The bidding dispute related to the modernization project for Fabella Hospital. The modernization became imperative because the land occupied by Fabella Hospital was owned by Home Guaranty Corporation, requiring the hospital to transfer to a new site. The process began with the submission of approved terms of reference for Phase 1 of the project by Architect Maria Rebecca M. Penafiel of the National Center for Health Facility Development (NCHFD) of DOH to the COBAC Secretariat on February 14, 2013.

The project’s Invitation to Bid (ITB) for Phase 1 was posted on PhilGEPS on April 6, 2013, and it was published on June 4, 2013 in two national newspapers, the Philippine Star and the Philippine Daily Inquirer, and was posted in conspicuous places within DOH premises. A pre-bid conference occurred on June 11, 2013, and on June 25, 2013 the bids were opened. Out of four bidders, three were declared eligible, including JDLC. On July 1, 2013, Tokwing Construction Corporation was initially declared to have submitted the Lowest Calculated Bid. However, on July 25, 2013, the COBAC informed Tokwing Construction that it failed post-qualification because it did not submit certified true copies of the required documents.

On August 6, 2013, the COBAC sent JDLC a notice that it had submitted the Lowest Calculated Bid. After review and deliberations, COBAC resolved that JDLC submitted the second Lowest Calculated and Responsive Bid. COBAC thereafter submitted its resolution to the head of the procuring entity on December 11, 2013.

Cancellation of Procurement and Mandamus Proceedings

After the COBAC’s resolution, DOH was advised to review financing options for the modernization project. As a result of that instruction, DOH cancelled the procurement. The NCHFD informed the COBAC Secretariat of the cancellation. With the cancellation in place, JDLC filed a Petition for the Issuance of the Writ of Mandamus dated January 24, 2014 before the RTC.

After petitioners filed their Comment, JDLC filed a Motion for Leave to File and Admit Attached Amended and Supplemental Petition for Mandamus and Certiorari, with an extremely urgent application for a TRO and/or writ of preliminary injunction. The amended course of action challenged the cancellation of the procurement process and sought relief leading to an award of the project to JDLC.

RTC’s TRO and Preliminary Injunction Orders

On June 18, 2014, the RTC issued an Order granting JDLC’s application for a TRO for twenty (20) days, enjoining DOH and all persons acting for it from conducting a rebidding or awarding to a third party the infrastructure project, or any aspect thereof, or from taking acts that would render the principal issues moot and academic or prejudice JDLC’s rights. The RTC directed DOH to show cause on July 11, 2014 at 8:30 a.m. on why a writ of preliminary injunction should not be granted.

Following the TRO, on August 7, 2014, the RTC granted JDLC’s application for a writ of preliminary injunction, conditioned upon JDLC’s posting of an injunctive bond of P2,000,000.00, “to answer for all damages” that petitioners might sustain by reason of the injunction (and earlier TRO), should the court ultimately rule that the applicant was not entitled to such relief. Upon approval of the bond, the RTC issued the Writ of Preliminary Injunction on August 18, 2014.

Petitioners’ Rule 65 and Rule 45 Challenges

These injunctive issuances prompted petitioners to file G.R. No. 212894 and G.R. No. 213820, both under Rule 65. Petitioners alleged that Judge Pascua gravely abused discretion amounting to lack or excess of jurisdiction when he issued the TRO and the preliminary injunction in violation of R.A. No. 8975, which purportedly barred lower courts from issuing restraining orders or preliminary injunctions against national government infrastructure projects.

Petitioners also filed G.R. No. 213889 under Rule 45, assailing the RTC’s August 29, 2014 Decision. Petitioners insisted that their right to due process was violated because Judge Pascua did not conduct a hearing on the main case before issuing the assailed TRO and subsequent reliefs. In turn, JDLC opposed and prayed for dismissal.

Consolidation and Subsequent Developments Before the Supreme Court

On October 8, 2014, petitioners moved to consolidate the three cases, and the Court consolidated them by Resolution dated September 22, 2014. JDLC later sought reconsideration of consolidation. The Court, by Resolution dated October 17, 2016, required the parties to inform it within ten (10) days from notice of any supervening events or developments that might assist immediate disposition or render the cases moot.

Petitioners submitted a compliance dated March 16, 2017, stating that the Office of the Solicitor General had sought information from the Secretary of Health and that DOH reported no significant circumstance after COBAC Resolution No. 2014-027-A dated October 10, 2014, awarding the Design and Build of the Infrastructure Project in favor of JDLC, and after JDLC’s compliance filed on October 13, 2014. DOH added that JDLC had finalized planning and its design and that construction of Fabella Hospital had commenced.

JDLC also submitted compliance dated March 20, 2017. It informed the Court that on January 23, 2015, DOH issued a Notice to Proceed (NTP) and that on May 31, 2015 JDLC began works pursuant to the NTP. JDLC further reported an estimated accomplishment of approximately seventy percent (70%) of the project, as of the time of the compliance, and asserted that completion would proceed on schedule absent factors beyond its control. It also stated that the project budget had not been reverted and had been allotted and utilized by DOH. JDLC cited that its fifth progress billing had been endorsed for payment in the amount of PhP83,793,873.43 for accomplishment as of December 31, 2016.

JDLC also stated that on November 16, 2015, the Government Procurement Policy Board issued GPPB Resolution No. 30-2015 approving DOH’s request to resort to negotiated procurement to award Phase II to JDLC under Section 53.4 of the Revised IRR of R.A. 9184, and that on December 29, 2015 JDLC was awarded Phase II with an NTP, for a total contract amount of PhP713,868,550.65. JDLC characterized Phase II as involving construction of the second to sixth floors and noted that Phase II was being implemented simultaneously with the project subject of the petitions. JDLC argued that the Phase II award effectively recognized its eligibility and qualification, and therefore negated DOH’s claimed ineligibility concerns.

The Supreme Court’s Disposition: Mootness

The Supreme Court ruled that the petitions had become moot. It acknowledged that the reliefs sought in the petitions—(a) a determination that Judge Pascua committed grave abuse of discretion in issuing the twenty (20)-day TRO allegedly in violation of R.A. No. 8975; (b) a determination that he committed grave abuse in granting the prayer for and issuing the writ of preliminary injunction; and (c) a determination that the RTC committed reversible error in ordering petitioners to award the project to JDLC—had been overtaken by supervening events.

The Court identified those supervening events as: (one) the issuance of NTP Phase I by DOH in favor of JDLC on January 23, 2015; (two) the commencement of works on May 31, 2015; (three) JDLC’s estimated seventy percent (70%) accomplishment; and (four) the issuance of NTP Phase II in favor of JDLC for PhP713,868,550.65. The Court reasoned that because DOH issued the Notices to Proceed for Phase I and Phase II, JDLC had already commenced the modernization of the hospital. As a result, any judicial declaration regarding the legality of the TRO, the preliminary injunction, or the RTC’s later decision ordering the award would no longer serve any practical purpose or value.

The Court invoked the concept of moot and academic cases, citing Prof David v. Pres. Macapagal-Arroyo, where the Court defined a moot and academic case as one that ceases to present a justiciable controversy due to supervening events, so that a declaration would have no

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.