Title
Department of Health vs. C.V. Canchela and Associates
Case
G.R. No. 151373-74
Decision Date
Nov 17, 2005
DOH contracts void due to lack of fund certification; private firms compensated on quantum meruit basis for services rendered, preventing unjust state enrichment.

Case Summary (G.R. No. 151373-74)

Key Dates and Procedural Posture

Owner‑Consultant Agreements executed in October 1996; Agreements amended December 10, 1996. Private respondents filed their CIAC petition (Case No. 31‑98) on September 21, 1998. Sole Arbitrator rendered award March 30, 1999. Court of Appeals affirmed the arbitrator’s decision by consolidated decision dated June 28, 2000. Petition for review to the Supreme Court filed under Rule 45; Supreme Court decision reversing the Court of Appeals issued (decision date referenced in prompt).

Applicable Law and Governing Standards

Primary constitutional and statutory framework applied: 1987 Constitution (including the public‑funds principles cited in Art. VI, Sec. 29 and Art. IX‑D, Sec. 2), Presidential Decree No. 1445 (Auditing Code of the Philippines), Executive Order No. 292 (Administrative Code of 1987), Government Accounting and Auditing (GAA) Manual (Sec. 525 governing professional fees), Letter of Instructions (LOI) No. 968, COA circulars, and Executive Order No. 1008 (Construction Industry Arbitration Law) as establishing CIAC jurisdiction.

Factual Background — Contracts, Scope and Compensation

DOH entered into three substantially identical Owner‑Consultant Agreements with private respondents for architectural & engineering (A&E) design and construction supervision for three hospital projects. Original agreed consultancy fee was 7.5% of the project fund allocation (6% A&E, 1.5% full‑time construction supervision). The Agreements were witnessed by the hospitals’ chief accountants and approved by the Secretary of Health, but did not contain certificates of availability of funds issued by the proper accounting officials.

Amendment and Performance

On December 10, 1996, DOH amended the Agreements to delete “full‑time construction supervision” and replace it with “periodic visits,” thereby reducing the agreed fee to 6% of the project contract cost and specifying a payment schedule tied to stages of construction. Private respondents submitted Contract/Bid Documents and A&E design plans which DOH accepted; DOH recommended payment in accordance with the Agreements but later withheld payment, citing alleged deficiencies in respondents’ performance. Respondents demanded payment administratively and ultimately filed for arbitration under Article 12 and EO 1008.

Arbitration and Award

The CIAC appointed a Sole Arbitrator who, after hearings, found in favor of private respondents and awarded P3,492,713 for A&E services performed and accepted by DOH, with interest at 6% per annum from the award date until finality and 12% thereafter. Claims for escalation and attorney’s fees were denied.

Appellate Proceedings and Issues Raised by DOH

DOH questioned CIAC jurisdiction, alleged grave abuse of discretion by the Sole Arbitrator, and contested the monetary award’s basis. The Court of Appeals initially dismissed the DOH petition as tardy, later reinstated and consolidated related petitions, and ultimately affirmed the Sole Arbitrator’s decision. DOH elevated the matter to the Supreme Court asserting (a) prematurity for failure to obtain Secretary of Health’s decision under Article 12; (b) State immunity; and (c) that respondents were entitled only to fees based on actual contract cost or quantum meruit and not to the amount awarded.

New Argument and Procedural Considerations

On appeal to the Supreme Court, DOH, for the first time, argued that the Agreements were void ab initio for lack of the required certification of availability of funds and therefore fees could not be computed as percentages of project allocations. The Court observed that the absence of earlier invocation of that defect ordinarily constitutes a waiver; however, because public funds and constitutional prescriptions concerning their disbursement are implicated, the Court considered the fundamental legality of the Agreements despite the newness of the argument.

Legal Analysis — Requirement of Certification and Effect on Contracts

The Supreme Court analyzed controlling provisions: P.D. 1445 requires an appropriation and a certification by the proper accounting official (attached to the contract) that funds are available; EO 292 reiterates that no funds shall be disbursed without certification of availability by the chief accountant; the GAA Manual (Sec. 525) mandates that professional fees for A&E services be stipulated in fixed peso amounts rather than as percentages of project cost. The Court held that the formalities are conditions sine qua non for contracts charging public funds, and failure to comply renders government contracts void. The signatures of chief accountants as contract witnesses did not substitute for the required certification; LOI No. 968, being administrative, could not override statutory requirements.

Ruling on Agreements’ Validity and Consequences

The Supreme Court concluded that the three Owner‑Consultant Agreements were null and void ab initio for failure to comply with statutory and administrative requirements (no certificate of availability of funds) and for contravening the GAA Manual’s prohibition against percentage‑based professional fees. The Court emphasized that these were not illegality per se but statutory prohibitions that render contracts void from inception.

Remedy — Quantum Meruit and Equitable Recovery

Despite the Contracts’ nullity, the Court applied equitable principles to prevent unjust enrichment by the State. Relying on precedent allowing payment on a quantum meruit basis where the government has accepted benefits (e.g., Eslao; Royal Trust), the Court held that private respondents were entitled to reasonable compensation for services actually performed and accepted by DOH (excluding periodic‑visit su

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.