Title
D.M. Ragasa Enterprises, Inc. vs. Banco De Oro, Inc.
Case
G.R. No. 190512
Decision Date
Jun 20, 2018
Bank pre-terminated lease, forfeited deposit as penalty; Ragasa denied unpaid rentals due to automatic termination, no unjust enrichment proven.

Case Summary (G.R. No. 171821)

Facts: merger, pre-termination, and demand

Following bank mergers, the bank closed the branch occupying the subject premises and sent Ragasa a notice of pre-termination dated May 28, 2001, effective June 30, 2001. Ragasa demanded payment for unexpired rentals (July 1, 2001 to Jan. 31, 2003) totaling P3,146,596.42. The bank replied that its only liability was forfeiture of the security deposit under item 8(m). The bank vacated the premises June 30, 2001. Ragasa filed suit on March 11, 2002 for collection of the unexpired rentals and damages.

RTC ruling

The Regional Trial Court found for Ragasa and awarded (1) P3,146,596.42 representing monthly rentals for July 1, 2001 to Jan. 31, 2003; (2) 3% penalty of monthly rental for each month of delay; (3) 14% per annum interest on the full amount due; (4) attorney’s fees of P30,000; and (5) costs. The RTC held the bank could not unilaterally pre-terminate an unambiguous five‑year lease lacking a pre‑termination clause, thus remaining liable for the rentals for the remaining term.

Court of Appeals ruling

The Court of Appeals reversed and dismissed the complaint, holding that the bank’s breach (pre‑termination) triggered the contract’s automatic termination under item 8(p) and that the applicable contractual remedy for breach of the lease term was forfeiture of the security deposit under item 8(m). The CA found that awarding both the unexpired rentals and penalties would amount to unjust enrichment.

Issues presented on review

Ragasa’s petition raised, inter alia, whether: (1) the CA erred in applying Articles 1170 and 1308; (2) the CA erred in holding item 8(m) (forfeiture of deposit) rather than item 8(n) (3% penalty) was the applicable penalty clause; (3) the CA erred in concluding the contract had been terminated; and (4) the CA erred in finding unjust enrichment.

Contract interpretation and autonomy

The Supreme Court reaffirmed the principle that contracts are the law between the parties and that valid stipulations are binding so long as they are not contrary to law, morals, good customs, public order or public policy. Where contract terms are clear, their literal meaning controls. The Court analyzed the use of the term “Term/TERM” in the contract and concluded that “Term” in item 8(m) refers to the lease period (the five‑year duration), consistent with other usages in the contract.

Breach and automatic termination

The Court found that the bank breached the contractual “Term” by pre‑terminating and vacating the premises June 30, 2001. Because the contract contains an express automatic termination provision (item 8(p) providing that breach of the contract’s provisions shall mean termination), the lease was automatically terminated upon the bank’s breach. Given this automatic rescission provision, Ragasa could not elect to force continuation of the lease and instead was limited to claiming damages arising from the breach.

Nature and legal effect of item 8(m)

Item 8(m) (“The full deposit shall be forfeited … upon non‑compliance of the Term … and cannot be applied to Rental”) was analyzed as a penal clause (liquidated damages) accessory to the principal lease obligation. The Court reviewed the nature, purposes (coercive, liquidatory, punitive) and classifications of penal clauses and applied Article 1226: generally a penal clause substitutes for indemnity and interest unless there is a stipulation to the contrary or certain exceptions apply (e.g., debtor refuses to pay the penalty or is guilty of fraud). The Court deemed item 8(m) conventional and primarily compensatory, but read together with item 10 it produces additional consequences.

Joint application of items 8(m) and 10 — complementary and cumulative penalty

The Court construed items 8(m) and 10 together. Item 10 provides that in litigation arising from noncompliance the aggrieved party shall be paid “no less than P15,000 for attorney’s fees, and other damages that the honorable court may allow,” and that unpaid accounts bear 14% interest. Construed jointly, items 8(m) and 10 constitute a complementary and cumulative penal clause — i.e., the forfeiture of deposit (item 8(m)) is coupled with the possibility of additional damages, attorney’s fees (minimum P15,000), litigation costs, and interest as provided in item 10. The Court concluded that item 10 supplies the “stipulation to the contrary” in Article 1226 that allows recovery of damages in addition to the penal clause.

Limitation on recovery — mitigation and proof of damages

Although the contract permits recovery beyond the forfeited deposit, the Court stressed that Ragasa bore the burden to prove “other damages” it actually suffered. The bank vacated the premises, making the premises available for re‑lease as of July 1, 2001; Ragasa elected not to lease and presented no evidence of attempts to mitigate or of lost rentals. Citing Article 2203 (duty to mitigate), the Court held Ragasa f

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.