Title
Cui vs. Sun Chan
Case
G.R. No. 16224
Decision Date
Mar 27, 1921
Lessor Pedro Cui successfully rescinded lease contract after lessee Sun Chan breached clause (d) by constructing awnings without consent.

Case Summary (G.R. No. 16224)

Factual Background

The trial court found as a matter of fact that the defendant, without the permission of the plaintiff, made additions to the leased property at its rear end, consisting of two awnings. The defendant did not appeal from the judgment. The Supreme Court therefore did not need to re-examine that factual aspect of the controversy.

The Contract Clause in Dispute

The dispute turned on the meaning and legal effect of clause (d) of the lease contract, which provided: “(D) Sun Chan (the lessee) also binds himself not to make any construction upon the property without the permission of the lessor, and in case he should do so, making any improvement thereon, it shall in all cases be for the benefit of the property, without any right to ask for reimbursement for its cost.”

Trial Court’s Conclusion of Law

Although the trial court recognized that the lessee had made constructions without the lessor’s permission, it ruled, as a conclusion of law, that the lessor had no right to rescind the lease, under the terms of clause (d). The lessor’s requested rescissory relief was thus denied in the court below.

Issues Raised on Appeal

The plaintiff appealed and assigned two errors. First, he argued that the trial court erred in interpreting subdivision (d) of the first paragraph of the contract as permitting the lessee to do any work upon the property without the consent of the lessor. Second, he argued that the trial court erred in failing to find that, even if subdivision (d) permitted construction of an improvement, it did not permit construction of work detrimental to the property, such as the constructions made by the defendant.

Appellate Reasoning on Contract Breach and Rescission

The Supreme Court framed the core question as whether the lessor had the right to rescind the lease due to noncompliance with one of the contract’s clauses by the lessee. The Court reiterated a basic principle: compliance with what is lawfully agreed upon is obligatory. It further held that a breach of any condition of a lease is a recognized cause for ouster and rescission of the contract, in accordance with article 1569, case No. 3, of the Civil Code.

The Court addressed the fact that the parties did not expressly provide for rescission due to breach of the particular clause in question. It ruled that such omission did not control the resolution of the case because obligations arising from a lease are reciprocal, and article 1124 of the Civil Code governs reciprocal obligations. Under article 1124, the power to resolve the contract in case one obligor does not fulfill his part is implied. The injured party may choose between exacting fulfillment or resolving the obligation, and in either choice the injured party is entitled to damages and interest.

The Court explained that the lessor could have opted to demand fulfillment, which would have required undoing the unauthorized work and restoring the property to its original condition. However, once the lessor instituted the rescissory action, the Court reasoned that it was required to decree the resolution sought, absent legal causes justifying a different result or a fixed term.

Treatment of Clause (d) and the Civil Code on Penalty-Style Stipulations

The Court adverted to the possibility that the preceding clause of the contract might constitute an obligation with a penal clause, but it expressly stated it would not decide that point. Even assuming the obligation bore a penal character, the Court held that the penalty—whose object is to secure compliance—cannot generally serve as a defense to leave the principal obligation unfulfilled. It invoked article 1153 of the Civil Code, under which the creditor may, at his option, exact fulfillment of the principal obligation or the payment of the penalty.

By applying the Civil Code principles on reciprocal obligations and rescission, the Court rejected the trial court’s conclusion that clause (d) prevented rescission even after unauthorized construction. It treated the lessee’s breach of the contractual restriction on construction without permission as sufficient ground for resolution under the Civil Code framework for leases.

Ruling and Disposition

The Supreme Court declared that the appellant (the lessor) had the right to rescind the lease contract. Accordingly, it reversed the judgment appealed from and declared the contract resolved. The Court stated that the

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.