Title
Casino Jr. vs. Court of Appeals
Case
G.R. No. 133803
Decision Date
Sep 16, 2005
Contractor failed to deliver full wood parquet quantity, breaching agreement; rescission upheld, damages awarded for losses incurred.

Case Summary (G.R. No. 152545)

Petitioner

Bienvenido M. Casiño, Jr. contracted to supply and install narra wood parquet (kiln dried) for a total area of 60,973 sq. ft. and a total price of P1,158,487.00; he admitted execution of the December 22, 1989 contract and receipt of the 40% downpayment.

Respondent

Octagon Realty Development Corporation contracted Casiño to supply and install the parquet for its condominium project, made the 40% downpayment (P463,394.50) and paid the first billing; later sought rescission and damages for petitioner’s alleged breach.

Key Dates

Contract executed: December 22, 1989. Delivery/completion stipulated: May 1990. Complaint filed at RTC (Pasig): October 2, 1991. RTC decision: June 2, 1994. CA decision: January 21, 1997 (initially modifying damages). CA resolution: May 20, 1998 (affirming trial court in toto). Supreme Court disposition: petition denied (reviewed under the 1987 Constitution and Rule 45).

Applicable Law

Primary statutory and doctrinal bases invoked and applied: Article 1191, Civil Code (rescission in reciprocal obligations); Articles 2199 and 2200, Civil Code (actual/compensatory damages and indemnification for loss of profits); Rule 45, Rules of Court (petition for review on certiorari). The Court applied jurisprudential standards regarding the finality of factual findings by lower courts and the limited role of this Court in Rule 45 petitions (only questions of law are reviewable).

Contractual Dispute and Pleadings

Respondent alleged that petitioner delivered only 26,727.02 sq. ft. (respondent’s figure) of the contracted 60,973 sq. ft., thereby failing to complete delivery and installation by May 1990; respondent alleged misrepresentation of qualification and financial inability on petitioner’s part and claimed damages including P912,452.39 (estimated loss on new price, unliquidated damages and cost of money) and reimbursement of P1,198,609.30 (cost paid to a replacement contractor). Petitioner countered that deliveries totaled 29,209.82 sq. ft., blamed respondent’s failure to prepare work premises and to accept deliveries, claimed unpaid billings of P105,425.68, and asserted counterclaims for rescission, payment of P597,392.90 (or in the alternative P105,425.68), various damages, and attorney’s fees.

Trial Court Findings and Judgment

The RTC found that petitioner breached the contract by failing to deliver the full quantity by the stipulated time and by making insufficient progress despite demands, and it credited respondent’s delivery figures. The trial court held that respondent validly rescinded the contract under Article 1191 and awarded actual and compensatory damages in the aggregate amount of P2,111,061.69 and attorney’s fees of P50,000.00.

Court of Appeals Proceedings and Rulings

On appeal the CA initially affirmed liability but modified the damage award (reducing it to P1,662,003.80 with legal interest from finality of judgment). After motions for reconsideration, the CA, by resolution, concluded that an item had been already factored into the trial court’s computation and therefore amended its earlier disposition to affirm the trial court in toto (restoring the P2,111,061.69 award), and imposed costs against petitioner.

Issues Raised in the Supreme Court Petition

Petitioner principally argued that: (1) the rescission declared by respondent was contrary to Article 1191 of the Civil Code; (2) the award of actual and compensatory damages (P1,662,003.80 as initially modified by the CA) was not legally justified or proven with reasonable certainty; and (3) the CA’s rulings involved grave abuse of discretion or were contrary to facts and evidence.

Supreme Court’s Review Standard and Deference to Factual Findings

The Court reiterated that on a Rule 45 petition only questions of law are reviewable; factual findings of the Court of Appeals, particularly when affirming the trial court, are binding on the Supreme Court unless they are not supported by the record or are based on a patent misunderstanding of facts. The Court found no such defect in the factual findings below and therefore declined to disturb the conclusions that petitioner breached his contractual obligations.

Rescission for Non-Performance (Article 1191) — Court’s Analysis

Applying Article 1191, the Court held that in reciprocal obligations the injured party may choose rescission if the other party fails to comply. The remedy is not available for slight or casual breaches but is proper for substantial and fundamental violations that defeat the contract’s object. The Court found petitioner’s failure to deliver and install substantially less than the contracted volume, and to do so within the agreed period despite demands, constituted a substantial breach warranting rescission. The Court also confirmed the principle that an injured party may treat a contract as rescinded extrajudicially and engage a third party to mitigate damages, though such extrajudicial termination proceeds at the party’s own risk and is subject to judicial review if contested.

Damages — Evidence and Legal Standard

The Court applied A

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.