Title
Camp John Hay Development Corp. vs. Charter Chemical and Coating Corp.
Case
G.R. No. 198849
Decision Date
Aug 7, 2019
Dispute over non-delivery of studio units as payment for painting services; CIAC upheld jurisdiction, awarded monetary value and attorney's fees due to breach.

Case Summary (G.R. No. 198849)

Petitioner and Respondent

• Petitioner: Camp John Hay Development Corporation
• Respondent: Charter Chemical and Coating Corporation

Key Dates

• January 2001 – Contractor’s Agreement executed
• 2003 – Completion of painting works by respondent
• May 30, 2005 – Issuance of Final Inspection and Acceptance Certificate
• June 12, 2008 – Request for arbitration filed with Construction Industry Arbitration Commission (CIAC)
• March 30, 2009 – CIAC Final Award
• May 13, 2011 – Court of Appeals Decision affirming CIAC award
• September 30, 2011 – CA Resolution denying motion for reconsideration
• November 23, 2011 – Supreme Court Petition filed
• August 7, 2019 – Supreme Court promulgation

Applicable Law

• 1987 Philippine Constitution (case decided post-1990)
• Article 1191 (rescission of reciprocal obligations) and Article 1197 (fixing of period) of the Civil Code
• Executive Order No. 1008 (Construction Industry Arbitration Law) as integrated into Republic Act No. 9285 (Alternative Dispute Resolution Act of 2004)
• Article 2208 (attorney’s fees) of the Civil Code

Contract Formation and Terms

Under the Contractor’s Agreement, respondent would perform painting works for a total contract price of ₱15,500,000, inclusive of two studio-type units as partial payment. The agreement allowed respondent to select the units and offset their value against the contract price but did not specify a turnover date.

Offsetting Scheme and Unit Selection

Respondent chose Units 102 and 104 in the second phase of Camp John Hay Suites. The contract price was subsequently reduced to ₱13,239,734.16; petitioner paid ₱7,339,734.16 in cash, leaving a balance of ₱5,900,000 to be settled by transfer of the two units.

Construction and Payment History

Respondent completed painting in 2003. Petitioner belatedly issued a Final Inspection and Acceptance Certificate on May 30, 2005. Respondent repeatedly demanded execution of deeds of sale and delivery of titles in September 2004 and April 2005.

Delays in Completion

Despite pro-forma contracts to sell executed in June 2005 promising delivery “within a reasonable period,” the overall Camp John Hay Suites project was delayed by force majeure, mutual delays with the Bases Conversion and Development Authority (BCDA), and successive amendments to the project timeline (2003, 2008), pushing completion beyond 2012.

Demand for Transfer and Arbitration Filing

In August 2007, respondent demanded unit transfer or payment of ₱6,996,517.48. Upon receiving no satisfactory response, it filed a Request for Arbitration before the CIAC on June 12, 2008, invoking the arbitration clause in the Contractor’s Agreement.

CIAC Final Award

On March 30, 2009, the CIAC ordered petitioner to pay respondent:

  1. ₱5,900,000 (monetary equivalent of the two units);
  2. ₱590,000 (attorney’s fees, 10% of unit value).
    It declined to fix a delivery period under Article 1197, noting the reciprocal nature of the contract.

Court of Appeals Decision

The Court of Appeals, in its May 13, 2011 Decision, affirmed the CIAC award, holding that:
• The arbitration clause remained binding despite subsequent contracts to sell.
• A definite completion timeline could be inferred from the 2003 BCDA memorandum.
• Petitioner was already in delay when respondent demanded transfer in August 2007.

Issues in the Supreme Court Petition

  1. Whether the CIAC had jurisdiction despite a dispute resolution clause in the contracts to sell.
  2. Whether rescission under Article 1191 was proper, or whether a period should have been fixed under Article 1197.
  3. Whether the award of attorney’s fees was proper.

Jurisdiction of the CIAC

The Supreme Court held that under Executive Order No. 1008 and the Alternative Dispute Resolution Act, the mere existence of an arbitration clause in a construction contract confers original and exclusive jurisdiction on the CIAC. The pro-forma contracts to sell did not supersede the primary Contractor’s Agreement or remove the dispute from CIAC’s ambit.

Rescission under Article 1191

Because petitioner failed to deliver the agreed units after respondent fully performed in 2003, the reciprocal obligation was breached. Article 1191 grants the injured party the choice of rescission or specific performance; here, rescission was warranted in the absence of just cause to fix a compliance period.

Fixing of the Period under Article 1197

Article 1197 allows courts to fix a period only if it can be inferred that the parties intended one. Given the years of delay predating and postdating the Contractor’s Agreement, no reasonable justif

    ...continue reading

    Analyze Cases Smarter, Faster
    Jur helps you analyze cases smarter to comprehend faster—building context before diving into full texts.