Title
Cagayan de Oro City Water District vs. Pasal
Case
G.R. No. 202305
Decision Date
Nov 11, 2021
COWD awarded Rio Verde a bulk water supply contract, later disputed by COA for non-compliance with procurement laws. Despite COA's fraud findings and recommendations for criminal charges, the Supreme Court upheld arbitration, citing separability of the arbitration clause and judicial restraint.
A

Case Summary (G.R. No. 202305)

Factual Background

Pursuant to Presidential Decree No. 198, the City Council created COWD and conducted public bidding for the design, construction, operation, maintenance, and management of a Bulk Water Supply Project using a Model Contract included among bid documents. By Board Resolution, COWD awarded the BWSP contract to Rio Verde, which then executed the Bulk Water Supply Agreement dated December 23, 2004 and a Supplemental Agreement dated January 21, 2005 providing a parametric water price adjustment formula.

Contract Performance and Dispute

Rio Verde began supplying bulk water in January 2007 at about 40,000 cubic meters daily and billed COWD at P11.52 per cubic meter pursuant to Article 9 as amended, whereas the Model Contract rate was P10.45 per cubic meter. COWD officials discovered substantial deviations of the BWSA from the Model Contract and secured an opinion from the Office of the Government Corporate Counsel advising reformation to conform to the Model Contract.

Audit Findings and Administrative Actions

The Commission on Audit issued ND No. COWD-2008-51 disallowing disbursements of P132,414,165.40 for payments to Rio Verde, finding Rio Verde a non-responsive bidder and the award lacking basis. A COA Special Audit Team and its FAIO issued an Audit Observation Memorandum and a report finding violations of RA 9184, deviations from the Model Contract that favored Rio Verde, an increased water rate disadvantageous to consumers, and recommendations to initiate civil and criminal actions including invocation of RA 3019.

Interim Contractual Conduct and Further Requests

Despite audits, COWD continued water procurement and paid Rio Verde. Later, COWD and Rio Verde agreed to adhere to the Model Contract and Rio Verde charged P10.45 per cubic meter. Rio Verde later requested a water price adjustment to P13.1461 per cubic meter effective April 2011; COWD denied the request and Rio Verde sought to resolve the dispute by arbitration, but COWD did not respond.

Proceedings Before the Regional Trial Court

Rio Verde filed S.P. 2011-190, a petition to compel arbitration under Section 6 of RA 876, invoking Article 19 of the BWSA which provides for amicable settlement and, failing that, arbitration, and which designates enforcement and forum-selection provisions. COWD opposed, asserting that the ongoing COA investigation constituted a prejudicial question and that the validity of the BWSA was not arbitrable.

Rulings of the Trial Court

By Order dated March 23, 2012, the RTC-Branch 38 granted Rio Verde’s petition and ordered COWD to submit to arbitration pursuant to Article 19. The trial court applied the doctrine of separability to treat the arbitration clause as independent of the main contract and invoked the principle of competence-competence to justify judicial restraint in invalidating arbitration clauses. The court noted COWD’s motion for reconsideration, which it merely noted in its May 3, 2012 order.

The Present Petition and the Parties’ Contentions

COWD invoked certiorari seeking nullification of the RTC orders and urged the Supreme Court to exercise plenary review, emphasizing novel legal questions and public interest because a government entity was being compelled to arbitrate while COA’s investigation into the contract’s validity was pending. COWD argued that (one) COA’s examination presented a prejudicial question that should be resolved before arbitration; (two) the doctrine of separability did not apply because the entire contract, including the arbitration clause, was under audit and allegedly procured by fraud; and (three) public interest barred arbitration under the questionable contract. Rio Verde defended the RTC disposition and contended that the doctrine of prejudicial question was inapposite and that the arbitration clause compelled referral.

Issues Presented

The Supreme Court framed the principal issues as: (one) whether the RTC’s directive to arbitrate may be challenged by the present petition for certiorari; (two) whether the trial court gravely abused its discretion in ordering arbitration despite the COA investigation; and (three) whether COA’s recommendation to file criminal charges and to seek nullity of the BWSA precluded arbitration.

Ruling of the Supreme Court

The Supreme Court dismissed the petition and affirmed the RTC orders dated March 23, 2012 and May 3, 2012. The Court held that the petition contravened the Special Rules of Court on Alternative Dispute Resolution and the policy favoring arbitration under RA 9285, and that the trial court did not gravely abuse its discretion in compelling arbitration despite COA’s ongoing examination.

Legal Basis and Reasoning

The Court reasoned that Section 6 of RA 876 limits the trial court’s inquiry to whether a written agreement to arbitrate exists and, if so, to summarily direct arbitration. The Special ADR Rules prohibit attacking a court’s prima facie determination referring parties to arbitration through motions for reconsideration, appeal, or certiorari until the arbitral tribunal rules on its jurisdiction or an award is rendered; the rules implement the principle of competence-competence and require judicial restraint. The Court emphasized that arbitration agreements are to be liberally construed in favor of arbitration and that the doctrine of separability renders the ar

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.