Case Summary (G.R. No. 202305)
Petitioner and Respondent
COWD is a local water utility created under PD 198 and responsible for bulk water procurement. Rio Verde is a private consortium awarded the Bulk Water Supply Project contract and party to a 2004 Bulk Water Supply Agreement (BWSA) with COWD, as amended in 2005.
Key Dates
• July 11, 1973 – COWD’s creation under PD 198
• December 23, 2004 – Execution of BWSA
• January 21, 2005 – Supplemental Agreement on price‐adjustment formula
• June 27, 2007 – COWD’s findings of deviation from Model Contract
• September 23, 2008 – COA Notice of Disallowance for P132,414,165.40
• July 14, 2009 – COWD’s appeal to COA
• March 23 and May 3, 2012 – RTC orders directing arbitration
• November 11, 2021 – Supreme Court decision
Applicable Law
• 1987 Constitution – public‐contract and arbitration policies
• PD 198 (1973) – creation and governance of local water districts
• RA 876 (1953) – Philippine Arbitration Law
• RA 9285 (2004) – Alternative Dispute Resolution Act
• Special ADR Rules (A.M. No. 07‐11‐08‐SC, 2009)
• Republic Act No. 3019 – Anti‐Graft and Corrupt Practices Act
• RA 9184 – Government Procurement Reform Act
Antecedents
Following public bidding under PD 198, COWD awarded its Bulk Water Supply Project to Rio Verde. The BWSA set an initial rate of ₱10.45/m³ for a twenty‐five‐year supply. A supplemental agreement revised the price‐adjustment formula. In January 2007, Rio Verde billed at ₱11.52/m³, prompting COWD’s review and OGCC advice to reform the contract back to the public bidding Model Contract. Despite objections, COWD paid ₱132,414,165.40, leading COA to issue a Notice of Disallowance in 2008, finding Rio Verde a non‐responsive bidder.
Arbitration Agreement and Dispute
Article 19 of the BWSA provides for escalation of disputes: mutual discussion, escalation to chief executives, and final settlement by arbitration under RA 876. After price‐adjustment disagreements resurfaced in 2011, Rio Verde invoked the arbitration clause; COWD refused.
RTC Proceedings and Ruling
Rio Verde petitioned the RTC under Section 6 of RA 876 to compel arbitration. The RTC granted the petition on March 23, 2012, upheld on May 3, 2012, applying the doctrine of separability and the competence-competence principle: an arbitration clause survives even if the main contract’s validity is assailed, and arbitrators should rule first on jurisdictional issues.
Issues before the Supreme Court
- Whether certiorari properly challenges an RTC order to arbitrate under the Special ADR Rules.
- Whether the RTC gravely abused discretion by ordering arbitration despite COA’s ongoing investigation into contract validity.
- Whether COA recommendations to charge parties under RA 3019 and to seek contract nullity preclude arbitration.
Supreme Court’s Ruling on Procedural Challenge
The petition for certiorari is impermissible under the Special ADR Rules. Rule 3.11 and Rule 4.6 prohibit motions for reconsideration, appeals, or certiorari against orders referring parties to arbitration. The law mandates summary referral if a prima facie arbitration agreement exists. COWD’s direct Rule 65 petition violates policy favoring party autonomy and judicial restraint under RA 9285 and the Special ADR Rules.
Separability and Competence-Competence
The Court reaffirmed that arbitration clauses are severable from the main contract. Even alleged fraud or nullity of the BWSA does not void the arbitration agreement. Under the competence-competence principle (Rule 2.4, Special ADR Rules), the arbitral tribunal decides its own jurisdiction, including challenges to the validity of the contract and arbitration clause.
Arbitration Despite COA Investigation
COA’s audit and its finding of irregularities constitute no bar to arbitration. The doctrine of
...continue readingCase Syllabus (G.R. No. 202305)
Facts
- Republic Act–equivalent PD 198 (1973) authorized creation of local water districts; COWD was established by City Council Resolution No. 35 dated July 11, 1973
- COWD conducted public bidding for its Bulk Water Supply Project (BWSP) using a Model Contract as bidding document
- By Resolution No. 222 (December 9, 2004), COWD awarded the BWSP contract to Rio Verde Water Consortium, Inc.
- Parties executed a Bulk Water Supply Agreement (BWSA) on December 23, 2004:
• Rio Verde to supply 50,000–150,000 m³/day for 25 years at P10.45/m³ start rate - COWD Board authorized negotiation of price‐adjustment formula by Resolution No. 238 (December 20, 2004)
- Supplemental Agreement (January 21, 2005) amended Article 9 to adopt revised parametric formula
- In January 2007, deliveries began at 40,000 m³/day; Rio Verde billed at P11.52/m³ under the amended formula
- COWD’s Acting GM Batar reported discrepancies between BWSA and the Model Contract (June 27, 2007)
- OGCC Opinion No. 003 (Series 2008) advised immediate reformation to conform with Model Contract; Supplemental Agreement lacked LWUA conformity
- Despite objections, COWD paid Rio Verde P132,414,165.40 (2007 deliveries)
- COA Notice of Disallowance No. COWD-2008-51 (Sept. 23, 2008) challenged payment as Rio Verde was allegedly a non‐responsive bidder
- COWD maintained supply payments by Resolution No. 063 (July 1, 2009) citing public need
- COA FAIO Audit Observation Memorandum 2009-0019 (Nov. 9, 2009) found:
• Violation of RA 9184 bidding rules; Rio Verde lacked required audited financials and BIR registration
• BWSA and Supplemental Agreement deviated from Model Contract for undue benefit of Rio Verde
• Water rate increase of P1.46/m³ to public’s disadvantage
• Fraud in contract execution; OGCC’s view confirmed - COWD reverted to Model Contra