Title
Busan Universal Rail, Inc. vs. Department of Transportation-Metro Rail Transit 3
Case
G.R. No. 235878
Decision Date
Feb 26, 2020
BURI challenged DOTr-MRT3's contract termination, seeking interim protection. SC upheld RTC's denial, citing RA 8975's prohibition on injunctions for gov't projects, directing arbitration.
A

Case Summary (G.R. No. 235878)

Key Dates and Procedural Posture

Contract performance began with Monthly Maintenance (Package 1) and billings were submitted (Billing Nos. 1–8 paid; Billing No. 9 onward unpaid). Usec. Chavez issued memoranda directing withholding and requesting explanations (Nov 17, 2016; Apr 19, 2017). Petitioner invoked contractual dispute settlement and notified intent to arbitrate, later sending a Notice of Arbitration. Petitioner filed in the RTC (Oct 6, 2017) for interim measures (status quo and injunction to prevent contract termination). RTC denied relief (Oct 13, 2017) and denied reconsideration (Dec 11, 2017). The Supreme Court (Second Division) reviewed and affirmed the RTC orders, denying the petition for review on certiorari.

Contract Structure and Obligations

Total contract price: P3,809,128,888.00, divided into four packages:

  • Package 1 (maintenance, monthly fixed sums, obligation to deliver available trains),
  • Package 2 (general overhaul of 43 LRVs within 36 months),
  • Package 3 (signaling system replacement),
  • Package 4 (additional maintenance).
    Petitioner performed under Package 1 and billed monthly; disputes arose over unpaid billings and alleged failures to deliver overhauled LRVs under Package 2.

Arbitration Clause and Contractual Dispute Mechanism

The contract’s General Conditions (Clause 20) required mutual consultation, a notice of intention to commence arbitration if consultation failed, and settlement of disputes by arbitration in accordance with RA 9285 (Alternative Dispute Resolution Act of 2004). The IRR of RA 9184 (procurement law) similarly mandated arbitration for disputes arising from contracts covered by the Act and provided that arbitration provisions be included in contracts.

Relief Sought by Petitioner

Petitioner sought a temporary ex parte protection order and subsequent interim protection to: (i) enjoin respondent from terminating the MRT3 Contract and to maintain status quo including payment of the monthly maintenance fee; (ii) compel respondent to cease acts effecting termination; and (iii) require respondent to comply with the arbitration clause and proceed with arbitration under RA 9285.

RTC Rulings and Grounds for Dismissal

The RTC denied petitioner’s petition for interim measures and denied reconsideration, concluding it lacked jurisdiction under RA 8975, which prohibits lower courts from issuing TROs, preliminary injunctions, or preliminary mandatory injunctions against national government projects, including acts of termination of such projects. The RTC also found the dispute arbitrable and noted that petitioners had referred the matter to arbitration.

Statutory Interaction: RA 9285 (ARDA) v. RA 8975

RA 9285 permits parties to seek interim measures from a court prior to constitution of an arbitral tribunal (Section 28) and contemplates court-granted provisional relief in aid of arbitration. RA 8975, a special law concerning national government projects, specifically bars lower courts (except the Supreme Court) from issuing TROs or preliminary injunctions to restrain, prohibit, or compel acts including termination or rescission of national government projects or contracts. The Supreme Court examined the interplay and applied the rule that a special statute (RA 8975) governing national projects prevails over the general provisions of RA 9285 insofar as they conflict.

Precedent: Falcon and Its Application

The Court relied on Department of Foreign Affairs v. Hon. Judge Falcon (BCA case), which held that RA 9285, although general and allowing interim relief from courts, yields to the special prohibition in RA 8975 when the relief sought would enjoin or impede termination or implementation of a national government project or contract. Falcon articulated the public-interest rationale: allowing injunctions to block termination would indefinitely hinder government in providing public goods and services, and the remedy to an aggrieved private party is contractual or statutory compensation rather than injunctive interference with government projects.

Constitutional Exception and Court’s Analysis

RA 8975 contains an exception allowing injunctions only where there is extreme urgency involving a constitutional issue such that, absent injunctive relief, grave injustice and irreparable injury will result. The Court applied the 1987 Constitution (Article III, Section 1 on due process and equal protection) as the relevant const

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.