Title
Busan Universal Rail, Inc. vs. Department of Transportation-Metro Rail Transit 3
Case
G.R. No. 235878
Decision Date
Feb 26, 2020
BURI challenged DOTr-MRT3's contract termination, seeking interim protection. SC upheld RTC's denial, citing RA 8975's prohibition on injunctions for gov't projects, directing arbitration.
Font Size:

Case Summary (G.R. No. 235878)

Petition Overview

  • The case involves a Petition for Review on Certiorari filed by Busan Universal Rail, Inc. (petitioner) against the Department of Transportation-Metro Rail Transit 3 (respondent).
  • The petition challenges the Orders of the Regional Trial Court (RTC) that denied the issuance of interim measures of protection, including a temporary restraining order.
  • The RTC's Orders were dated October 13, 2017, and December 11, 2017.

Contractual Background

  • The MRT3 Contract was established through negotiated procurement under Republic Act No. 9184.
  • The contract involved a Joint Venture, including Busan Transportation Corporation and others, for the maintenance and overhaul of the MRT3 system.
  • The total contract amount was P3,809,128,888.00, divided into four packages, covering maintenance, overhaul of light rail vehicles (LRVs), signaling system replacement, and additional maintenance works.

Payment Disputes

  • After initiating work under Package 1, the petitioner submitted multiple billing statements, with Billing Nos. 1 to 8 being paid.
  • Billing No. 9 was not settled due to a directive from the DOTr requiring additional documentation and withholding of payments.
  • Subsequent communications indicated ongoing disputes regarding the performance of the contract, leading to unpaid billings from Nos. 9 to 18.

Arbitration Proceedings

  • The petitioner sought to resolve disputes through mutual consultation and subsequently notified the respondent of its intention to commence arbitration.
  • A Petition for Interim Measures of Protection was filed with the RTC to maintain the status quo and prevent contract termination.
  • The RTC denied the petition, noting that the case had been referred for arbitration.

RTC's Rulings

  • The RTC ruled that it lacked jurisdiction to issue the requested interim measures based on RA 8975, which prohibits lower courts from issuing restraining orders against government infrastructure projects.
  • The RTC concluded that the issues raised were arbitrable and that the petitioner had not demonstrated a valid basis for the requested relief.

Legal Arguments

  • The petitioner argued that the RTC had the authority to issue interim measures under RA 9184 and that the arbitration clause in the MRT3 Contract should allow for such measures.
  • The respondent countered that RA 8975 explicitly prohibits lower courts from issuing injunctions against government projects, asserting that the issues were to be resolved in arbitration.

Relevant Statutory Provisions

  • RA 9184 and its Implementing Rules provide for arbitration as the mode of dispute resolution for contracts covered by the Act.
  • RA 9285 allows for interim measures of protection from courts before the constitution of an arbitral tribunal.
  • RA 8975 prohibits lower courts from issuing temporary restraining orders or injunctions against national government projects, with limited exceptions.
  • ...continue reading

Save Time. Analyze Cases Smarter.
Jur is an AI-powered legal research platform in the Philippines for case digests, summaries, and jurisprudence. AI-generated content may contain inaccuracies; please verify independently.