Case Summary (G.R. No. 235878)
Petition Overview
- The case involves a Petition for Review on Certiorari filed by Busan Universal Rail, Inc. (petitioner) against the Department of Transportation-Metro Rail Transit 3 (respondent).
- The petition challenges the Orders of the Regional Trial Court (RTC) that denied the issuance of interim measures of protection, including a temporary restraining order.
- The RTC's Orders were dated October 13, 2017, and December 11, 2017.
Contractual Background
- The MRT3 Contract was established through negotiated procurement under Republic Act No. 9184.
- The contract involved a Joint Venture, including Busan Transportation Corporation and others, for the maintenance and overhaul of the MRT3 system.
- The total contract amount was P3,809,128,888.00, divided into four packages, covering maintenance, overhaul of light rail vehicles (LRVs), signaling system replacement, and additional maintenance works.
Payment Disputes
- After initiating work under Package 1, the petitioner submitted multiple billing statements, with Billing Nos. 1 to 8 being paid.
- Billing No. 9 was not settled due to a directive from the DOTr requiring additional documentation and withholding of payments.
- Subsequent communications indicated ongoing disputes regarding the performance of the contract, leading to unpaid billings from Nos. 9 to 18.
Arbitration Proceedings
- The petitioner sought to resolve disputes through mutual consultation and subsequently notified the respondent of its intention to commence arbitration.
- A Petition for Interim Measures of Protection was filed with the RTC to maintain the status quo and prevent contract termination.
- The RTC denied the petition, noting that the case had been referred for arbitration.
RTC's Rulings
- The RTC ruled that it lacked jurisdiction to issue the requested interim measures based on RA 8975, which prohibits lower courts from issuing restraining orders against government infrastructure projects.
- The RTC concluded that the issues raised were arbitrable and that the petitioner had not demonstrated a valid basis for the requested relief.
Legal Arguments
- The petitioner argued that the RTC had the authority to issue interim measures under RA 9184 and that the arbitration clause in the MRT3 Contract should allow for such measures.
- The respondent countered that RA 8975 explicitly prohibits lower courts from issuing injunctions against government projects, asserting that the issues were to be resolved in arbitration.
Relevant Statutory Provisions
- RA 9184 and its Implementing Rules provide for arbitration as the mode of dispute resolution for contracts covered by the Act.
- RA 9285 allows for interim measures of protection from courts before the constitution of an arbitral tribunal.
- RA 8975 prohibits lower courts from issuing temporary restraining orders or injunctions against national government projects, with limited exceptions. ...continue reading
Case Syllabus (G.R. No. 235878)
Case Background
- The case revolves around a Petition for Review on Certiorari under Rule 45 with an application for the issuance of a Status Quo Order and/or Preliminary Mandatory Injunction.
- Busan Universal Rail, Inc. (petitioner) challenges the Orders dated October 13, 2017, and December 11, 2017, issued by Branch 105 of the Regional Trial Court (RTC) in Quezon City.
- The RTC denied the petitioner's request for interim measures of protection against the Department of Transportation (DOTr)-Metro Rail Transit (MRT) 3 (respondent).
Antecedents of the Case
- The MRT3 Contract, resulting from a negotiated procurement under Republic Act No. (RA) 9184, involves a Joint Venture including Busan Transportation Corporation, Edison Development and Construction, Tramat Mercantile, Inc., TMICorp, Inc., and Castan Corporation.
- The total value of the MRT3 Contract is P3,809,128,888.00, divided into four packages:
- Package 1: Maintenance of the MRT3 system (P1,962,000,000.00).
- Package 2: General overhaul of 43 light rail vehicles (P907,369,561.81).
- Package 3: Total replacement of the MRT3 signaling system (P888,000,000.00).
- Package 4: Additional maintenance works (P51,759,326.19).
- The petitioner submitted multiple billing statements, but Billing No. 9 was not settled due to requests for additional documentation from the DOTr.
- Following communications regarding potenti...continue reading