Case Summary (G.R. No. 220832)
Key Dates and Documentary Milestones
ASEAN Single Window Protocol signed December 20, 2006; PNSW 1 completed October 2010. DBM-PS issued Request for Expression of Interest on October 15, 2014. Notice of Highest Rated Bid (HRB) and Invitation to Negotiate issued April 13, 2015; contract negotiation commenced April 17, 2015. Commissioner Lina appointed April 23, 2015; he wrote his May 6, 2015 letter requesting discontinuance of procurement. DBM-PS issued Notice of Cancellation on May 7, 2015. Private respondent’s reconsideration filed May 22 and denied by BOC on July 31, 2015. RTC issued TRO July 28, 2015 and Omnibus Order with writ of preliminary injunction on August 24, 2015. Supreme Court decision affirmed the RTC order and dismissed the petition on February 28, 2018.
Applicable Statutory and Regulatory Framework
Primary statutes and rules applied: Republic Act No. 9184 (Government Procurement Reform Act) and its Implementing Rules and Regulations (IRR), in particular Section 38 (period for action on procurement activities) and Section 41 and Section 41.1 (reservation clause and justifiable grounds for rejecting bids). Jurisdictional basis for the RTC’s original power to issue writs derives from Section 21 of Batas Pambansa Blg. 129. The 1987 Constitution is the relevant constitutional framework for judicial authority because the decision was rendered in 2018.
Nature and Objective of the PNSW 2 Project
The PNSW 2 project was an IT consulting-services procurement aimed at integrating existing electronic and mobile customs systems and PNSW 1 into a single, paperless, electronic customs processing and single-window system. The project scope included design, implementation, operation, maintenance and consulting services and was classified in bidding documents as consulting services governed by RA No. 9184 and its IRR. Approved budget for contract: P650 million.
Bidding Sequence, Shortlisting and Alleged Irregularities
Prospective bidders included the Omniprime–Intrasoft joint venture (private respondent) and E-Konek & ILS & FS JV (whose largest shareholder was Commissioner Lina). Evaluation and shortlisting were delayed by an interview of private respondent’s project team members requested by a former deputy commissioner, an interview that was not required by law or regulation. DBM-PS later issued the HRB notice and invited negotiation with private respondent as highest-rated bidder; financial negotiation processes followed.
Cancellation by the Head of the Procuring Agency
Upon his appointment, Commissioner Lina sent a May 6, 2015 letter asking that the procurement be discontinued pursuant to Section 41(c) of RA No. 9184 (reserve right to reject bids for justifiable reasons). Acting on that letter, DBM-PS Executive Director Syquia issued a Notice of Cancellation dated May 7, 2015, aborting the bidding process. Private respondent’s administrative motion for reconsideration was denied, and it filed an original action in the RTC seeking certiorari and mandamus and praying for injunctive relief to prevent cancellation and compel continuation of procurement.
RTC Relief: Temporary Restraining Order and Omnibus Order
The RTC issued a TRO on July 28, 2015 and, by Omnibus Order of August 24, 2015, granted a writ of preliminary injunction. The court (a) denied the petitioners’ motion to dismiss; (b) enjoined petitioners from implementing Lina’s May 6 letter and Syquia’s May 7 Notice of Cancellation; (c) enjoined petitioners from initiating any alternate procurement for the same purpose; (d) ordered petitioners to proceed with signing the contract and issuing Notice to Proceed to private respondent; and (e) required the private respondent to post an injunction bond of P500,000.
Petition to the Supreme Court and Issues Presented
BOC and DBM-PS filed a petition for certiorari under Rule 65 contesting the RTC’s Omnibus Order and alleging grave abuse of discretion by the respondent judge in issuing the injunction. The primary issues addressed by the Supreme Court were (1) whether the petition was procedurally proper given the absence of a motion for reconsideration and the direct resort to the Supreme Court instead of intermediate remedies, and (2) whether the RTC judge gravely abused his discretion in granting injunctive relief.
Procedural Ruling: Failure to Exhaust or Invoke Ordinary Remedies; Hierarchy of Courts
The Supreme Court held the petition procedurally infirm for failure to first file a motion for reconsideration in the RTC to allow correction of the trial court’s decision. Certiorari under Rule 65 requires, except in concrete, compelling, and valid circumstances, a prior motion for reconsideration of the challenged order. Petitioners’ bare allegation that the case raised pure questions of law did not justify bypassing the required motion. The Court also stressed the doctrine of hierarchy of courts; although the Supreme Court has concurrent certiorari jurisdiction with the Court of Appeals and RTC, direct resort is permitted only when special or compelling reasons exist. Petitioners failed to show such reasons, rendering the petition dismissible on procedural grounds.
Substantive Ruling: Standard for Grave Abuse of Discretion
On the merits, the Supreme Court confirmed that certiorari lies only when a lower court acts with grave abuse of discretion—arbitrary, despotic, or in contemplation of law. The Court found no grave abuse by the respondent judge in issuing the Omnibus Order and WPI. The RTC’s exercise of injunctive power rested on legal and factual considerations recognized in jurisprudence and the Rules of Court governing preliminary injunctions.
RTC Jurisdiction to Issue Writs and Applicability of RA No. 8975
The Court affirmed the RTC’s original jurisdiction to issue writs under Section 21 of BP 129. Petitioners’ contention that RA No. 8975 (which limits TROs and preliminary injunctions in infrastructure projects) applied was rejected because PNSW 2 was a consulting-services procurement and not an “infrastructure project” or civil-works component as contemplated by RA No. 8975. The Court relied on the bidding documents’ classification of the project as consulting services and precedent distinguishing civil-works components from non-civil-works IT components.
Private Respondent’s Rights under RA No. 9184: Section 38 and Deemed Approval
The Court emphasized private respondent’s entitlement under RA No. 9184 and its IRR once declared the highest-rated bidder: Section 38 mandates that the procurement process from bid opening to award shall not exceed three months and provides that inaction by the head of the procuring entity within the prescribed period results in the contract being deemed approved. In this case, more than three months had passed without appropriate action, and DBM-PS’s inaction coupled with subsequent cancellation effectively triggered the deemed-approval principle favoring private respondent.
Reservation Clause under Section 41 and Its IRR: Limits on Cancellation
Although Section 41(c) reserves to the head of the procuring entity the right to reject bids or cancel bidding for justifiable grounds, Section 41.1 of the IRR qualifies those grounds (changes in feasibility, project no longer necessary, or funding withheld/reduced). The Court found that Commissioner Lina’s stated ground—an intent to conduct “a thorough review” of project details—did not constitute a justifiable reason under the IRR. Director Syquia’s Notice of Cancellation lacked evidentiary support that conditions had materially changed or that
...continue readingCase Syllabus (G.R. No. 220832)
Parties
- Petitioners: Bureau of Customs (BOC), represented by Commissioner Alberto D. Lina; Department of Budget and Management-Procurement Service (DBM-PS), represented by Executive Director Jose Tomas C. Syquia.
- Respondents before the RTC: Hon. Paulino Q. Gallegos in his capacity as Presiding Judge, Regional Trial Court, Manila, Branch 47; the purported Joint Venture of Omniprime Marketing, Inc. and Intrasoft International, Inc., represented by Annabelle A. Margaroli (private respondent).
- Appellate disposition: Petition for certiorari under Rule 65 filed by petitioners in the Supreme Court challenging RTC Omnibus Order dated August 24, 2015.
Antecedent Facts: International and Project Background
- ASEAN Protocol and national commitment:
- On December 20, 2006, ASEAN member-countries, including the Philippines, signed the Protocol to Establish and Implement the ASEAN Single Window (ASW Protocol).
- Under the ASW Protocol, member-countries agreed to develop and implement National Single Windows (NSW) based on international standards and trade facilitation best practices.
- Philippine NSW project phases:
- Phase One of the Philippines’ NSW project (PNSW 1) commenced in 2009 and was completed in October 2010.
- Phase Two, the PNSW with Enhanced Customs Processing System project (PNSW 2), was undertaken thereafter.
- Description and objectives of PNSW 2:
- Official project title: Selection of System Integrator for Design, Implementation, Operation and Maintenance of Integrated Enhanced Customs Processing System and National Single Window for the Government of the Philippines: Component I: Design, Implementation, Operation and Maintenance of Enhanced Customs Processing System for the Bureau of Customs (BOC); and Component II: Development and Operationalization of PNSW 2 Project for the Government of the Philippines for the Bureau of Customs (Public Bidding No. 14-082).
- Nature: an information technology project intended to integrate the existing Electronic to Mobile Customs System and PNSW 1 into a single system covering existing BOC electronic/mobile functionalities.
- Purpose: to achieve fully electronic, paperless, man-contact-free processing of Customs transactions; allow single submission of data by traders; enable BOC single and synchronous processing and a single decision-making point for customs release and cargo clearance.
Procurement and Pre-Bid Proceedings
- Funding and procurement steps:
- Funds sourced from appropriations in the General Appropriations Act for calendar years 2010 and 2012.
- DBM-PS, as the procuring entity for BOC, issued a Request for Expression of Interest (RFEI) on October 15, 2014 inviting prospective bidders for eligibility screening and shortlisting for competitive bidding.
- Approved total budget for the contract: P650 million.
- Bidders and shortlisting:
- Among bidders submitting eligibility documents: (1) Joint Venture of Omniprime Marketing, Inc. and Intrasoft International, Inc. (private respondent), and (2) E-Konek & ILS & FS JV, whose biggest shareholder is Commissioner Lina.
- Announcement of shortlist and Highest Rated Bid (HRB) was delayed due to interviews of private respondent’s Project Team Members requested by former Deputy Commissioner Primo Aguas; the interview was not required by law or regulation.
- After evaluation, DBM-PS Bids and Awards Committee issued on April 13, 2015: a Notice of HRB and an Invitation to Negotiate to private respondent as the highest bidder.
- Financial proposal and contract negotiation with private respondent commenced on April 17, 2015.
Administrative Acts that Prompted Litigation
- Appointment and administrative decisions:
- Commissioner Alberto D. Lina was appointed as BOC Commissioner on April 23, 2015.
- Commissioner Lina wrote a letter dated May 6, 2015 to DBM-PS Executive Director Jose Tomas C. Syquia requesting discontinuance of the procurement process of PNSW 2 in reliance on Section 41(c) of R.A. No. 9184 (Reservation Clause allowing rejection for justifiable and reasonable grounds).
- Acting on Lina’s letter, Director Syquia issued a Notice of Cancellation on May 7, 2015 aborting the bidding process for the PNSW 2 project.
- Administrative remedies pursued by private respondent:
- Private respondent filed a Motion for Reconsideration dated May 22, 2015 against the Notice of Cancellation.
- Petitioners (BOC) denied the motion in a Resolution dated July 31, 2015.
- Private respondent thereafter filed a Petition for Certiorari and Mandamus with Prayer for TRO/WPPI/WPMI before the RTC, seeking annulment of Director Syquia’s Notice of Cancellation, and commanding petitioners to continue with contract signing and issuance of Notice to Proceed.
- Private respondent also sought injunctive relief to restrain petitioners from withholding or reducing appropriation or returning funds so as not to render any eventual judgment ineffectual.
RTC Proceedings, TRO and Omnibus Order
- Initial RTC relief:
- RTC issued a Temporary Restraining Order (TRO) in favor of private respondent on July 28, 2015.
- Omnibus Order of August 24, 2015 (dispositive portion summarized):
- Denied petitioners’ Motion to Dismiss.
- Granted private respondent’s application for issuance of a Writ of Preliminary Injunction (WPI).
- Enjoined petitioners from implementing: (a) Commissioner Lina’s May 6, 2015 letter aborting the competitive bidding, and (b) Director Syquia’s May 7, 2015 Notice of Cancellation, while the case was pending.
- Enjoined petitioners from initiating any other procurement, sourcing of funds, or conducting any procurement to replace or upgrade the present customs system subject of the bid.
- Ordered petitioners to continue with the remaining procurement process—specifically, to sign the contract and issue the Notice to Proceed to private respondent.
- Ordered private respondent to post an injunction bond of P500,000.00 in cash, answerable to damages petitioners may suffer.
- Ordered petitioners to file their Comment pursuant to Section 6, Rule 65 of the Revised Rules of Court.
- Writ issuance:
- RTC issued the writ of preliminary injunction on August 26, 2015.
Petition to the Supreme Court: Relief Sought and Principal Issue
- Petitioners’ action:
- Petitioners filed a petition for certiorari under Rule 65 in the Supreme Court, dispensing with a motion for reconsideration in the court a quo.
- Principal issue presented:
- Whether Judge Paulino Q. Gallegos gravely abused his discretion when he issued the Omnibus Order and the injunctive writ (i.e., whether issuance of WPI and related orders constituted grave abuse).
Supreme Court Disposition: Summary
- Outcome:
- The petition fails; dismissed.
- The RTC Omnibus Order dated August 24, 2015 is affirmed in toto.
- The case is remanded to the RTC for immediate resolution of the main petition in Civil Case No. 15-134333.
- Concurrence:
- Decision authored by Justice Tijam; Chief Justice Sereno (Chairperson), and Justices Leonardo‑De Castro, Del Castillo, and Jardeleza concurred.
Procedural Aspect: Motion for Reconsideration and Hierarchy of Courts
- Rule 65 procedural requireme