Title
Bricktown Development Corp. vs. Amor Tierra Development Corp.
Case
G.R. No. 112182
Decision Date
Dec 12, 1994
Bricktown Development canceled contracts due to Amor Tierra's unpaid installments; SC upheld rescission but refunded partial payment with interest.

Case Summary (G.R. No. 112182)

Petitioner

Bricktown Development Corporation (also styled in the records as Multinational Realty Development Corporation) executed two Contracts to Sell and a Supplemental Agreement; it relied on the contracts’ cancellation/rescission clauses to terminate the agreements for nonpayment and sought to retain payments as liquidated damages and pursue counterclaims.

Respondent

Amor Tierra Development Corporation entered into the Contracts to Sell and Supplemental Agreement as purchaser; it made partial payments totaling P1,334,443.21, engaged in negotiations with the seller, later demanded refund or assignment of unencumbered lots, and filed suit after the seller declared cancellation.

Key Dates

  • March 31, 1981: Execution of two Contracts to Sell (Exhs. A and B) and Supplemental Agreement (Exh. C).
  • Payment schedule in contracts: initial payment P2,200,000.00 (due March 31, 1981), subsequent installments due June 30, 1981 and December 31, 1981, and balance by assumption of mortgage or cash.
  • October 12, 1981: Seller’s Notice of Cancellation (Exh. D) advising purchaser of right to cure within 30 days from receipt.
  • September 26, 1983: Purchaser’s demand for refund or assignment (Exh. E).
  • November 18, 1983: Filing of the complaint by purchaser in the trial court.
  • Appeals and final resolution by the Supreme Court (decision rendered December 12, 1994).

Applicable Law

1987 Philippine Constitution (applicable because the decision date is 1994). Civil Code provisions relevant to delay/default, notably Article 1169 (text reproduced in the record). Contract law principles invoked: autonomy of contracts, binding force of perfected contracts, obligation of parties to act in good faith, and the contractual stipulation permitting rescission and forfeiture as liquidated damages where applicable. Precedential authorities cited in the decision include Roque v. Lapuz and Agustin v. Court of Appeals regarding the effect of nonpayment in contracts to sell.

Factual Summary

Petitioners sold 96 lots to respondent for P21,639,875.00 under a payment schedule; respondent paid only P1,334,443.21 (less than the stipulated initial downpayment of P2,200,000.00). Supplemental Agreement required additional interest payments. Between execution and attempted cancellation the parties engaged in prolonged negotiations about modifying the deal (including proposals to divide lots or assign lots corresponding to amounts already paid), but no novation or definitive modification was concluded. Petitioner sent a Notice of Cancellation on October 12, 1981 for nonpayment; purchaser thereafter demanded refund in 1983 and filed suit when the demand was not honored.

Procedural History

The trial court, after receiving evidence, declared the Contracts to Sell and the Supplemental Agreement rescinded; ordered refund to the purchaser of P1,334,443.21 with 12% interest per annum starting November 18, 1983 (date of filing), awarded P25,000.00 attorney’s fees, dismissed petitioner’s counterclaim, and imposed costs against petitioners. The Court of Appeals affirmed the trial court in toto. Petitioners elevated the case to the Supreme Court.

Issues Presented to the Supreme Court

Petitioners argued that the Court of Appeals erred by: (1) finding that petitioners’ acts and conduct delayed performance and estopped them from cancelling; (2) concluding that petitioners were unjustified in rescinding the contracts; (3) holding that cancellation required a positive act giving the purchaser a 60‑day grace period under the contracts; and (4) failing to enforce forfeiture of payments (P1,378,197.48) as liquidated damages under the contract terms.

Court’s Analysis — Contractual Autonomy and Binding Force

The Court reiterated the foundational principle that perfected contracts have the force of law between the parties and must be performed in good faith; parties may stipulate terms provided they do not contravene law, morals, or public policy. The Court accepted that factual findings of the trial court, as affirmed by the Court of Appeals, are binding in this petition and proceeded to analyze the case on that factual basis.

Court’s Analysis — Grace Period, Article 1169, and Validity of Cancellation

The contracts contained a clause (Paragraph 15) granting the purchaser a 60‑day grace period for overdue installments, with actual cancellation to take effect only after 30 days from receipt of notice of cancellation. The Court characterized a contracted grace period as a right of the debtor that, when unconditionally conferred, becomes operative ipso facto upon failure of payment at maturity. Consequently, Article 1169 (which generally makes delay dependent on judicial or extrajudicial demand unless expressly otherwise provided) was held not to be relevant where the contract itself establishes a specific grace period. On this basis the Court concluded that petitioner corporation acted within its contractual right to rescind the contracts for nonpayment.

Court’s Analysis — Forfeiture, Equity, and Effect of Parties’ Conduct

Although the seller’s cancellation was legally valid, the Court examined whether complete forfeiture of payments as liquidated damages should be permitted. The trial court and the Court of Appeals found extensive, ongoing negotiations between the parties after the contracts’ execution; the purchaser never took actual possession of the lots, and the seller did not dispose of the lots during negotiations. The appellate court found that the seller’s conduct and proposed counteroffers led the purchaser reasonably to believe that a new or modified agreement might be entered into, and that there was no malice or bad faith on the purchaser’s part in suspending payments. Considering these factual findings and the overarching principle of good faith in contractual relations, the Supreme Court determined that it would be unconscionable to allow the seller to retain all payments as forfeited amounts.

Court’s Holding and Relief Granted

The Supreme Court affirmed the courts below

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.