Title
Supreme Court
Board of Investments vs. SR Metals, Inc.
Case
G.R. No. 219927
Decision Date
Oct 3, 2018
BOI withdrew SR Metals' tax holiday for alleged non-compliance; SC upheld CA, ruling withdrawal lacked basis as SR Metals met registration terms.

Case Summary (G.R. No. 219927)

Procedural Posture and Applicable Law

The case arose from respondent’s application for registration as a new producer of beneficiated nickel silicate ore under non-pioneer status, with the corresponding grant of an Income Tax Holiday (ITH) incentive per the Omnibus Investment Code (Executive Order No. 226). The BOI later withdrew this incentive, prompting respondent to file a Petition for Review with the Court of Appeals (CA), which ruled in favor of the respondent. The BOI then elevated the case to the Supreme Court under Rule 45 of the Rules of Court, invoking the 1987 Philippine Constitution as the basis for the decision since the case was decided in 2018.

Factual Background

Respondent filed its application for registration on April 3, 2008, which BOI approved on June 4, 2008, granting the ITH incentive for 2008-2012. Subsequently, on August 31, 2010, the Sangguniang Bayan of Tubay requested cancellation of respondent’s registration, alleging that respondent was not operating a beneficiation plant as represented but instead directly shipping unprocessed ore via open-cut mining, contrary to its Certificate of Registration. Certifications from local government offices confirmed the alleged lack of industrial buildings or processing plants registered under respondent’s name.

BOI’s Action on Withdrawal of Incentive

On April 11, 2011, BOI notified respondent of the cancellation request and directed submission of a reply. Respondent responded asserting compliance with its registration terms, clarifying it was registered as a producer of beneficiated ore—not as a beneficiation plant itself—and that local government consultation was not required under the 2007 Investment Priorities Plan (IPP). On February 12, 2012, BOI resolved to withdraw the ITH incentive on grounds of non-compliance with the 2007 IPP and specific project conditions, including failure to establish another line or beneficiation plant and failure to infuse new investment in fixed assets. Respondent’s motion for reconsideration was denied by BOI on July 30, 2013, citing late filing and insufficient grounds.

Court of Appeals’ Ruling

The CA ruled on December 4, 2014, that respondent was entitled to the ITH incentive. It found:

  • The 2007 IPP did not require constructing a beneficiation plant for incentive qualification.
  • Respondent had infused new investments in fixed assets, submitted progress reports, and adhered to the project timetable.
  • BOI’s withdrawal was therefore without basis.
  • Respondent was denied due process as BOI failed to (a) inform respondent of a formal investigation, (b) base the withdrawal on the grounds in the Sangguniang Bayan Resolution, and (c) properly consider respondent’s motion for reconsideration. The CA annulled and set aside BOI’s withdrawal of incentives. Its denial of BOI’s motion for reconsideration was affirmed on August 11, 2015.

Petitioner’s Arguments on Appeal to the Supreme Court

BOI claimed:

  • ITH is a privilege requiring compliance with IPP conditions.
  • Respondent failed to fulfill commitments to build a beneficiation plant and invest heavily in fixed assets.
  • Respondent’s actual operations differed from its application representations.
  • Respondent was afforded due process through notices and the opportunity to present evidence.

Respondent’s Counterarguments

Respondent challenged:

  • The authority of the BOI Officer-in-Charge to sign the petition’s verification and certification of non-forum shopping.
  • BOI’s failure to attach certain pleadings from the CA proceedings.
  • The substantive withdrawal of the ITH incentive was baseless, citing compliance with the IPP, including substantial investment and project reporting.
  • The absence of a requirement to physically construct a beneficiation plant; the equipment assembled sufficed.
  • The withdrawal violated due process under BOI’s Revised Rules of Procedure on Cancellation.

Supreme Court’s Ruling on Procedural Issues

  • The authority of BOI’s Officer-in-Charge (OIC Halili-Dichosa) to file the petition and sign the verification was upheld, reasoning that such authority should be resolved in favor of government service efficiency, especially since she acted in an official capacity.
  • The failure to attach all pleadings filed before the CA did not warrant dismissal; the Court determined that material portions were sufficiently included and the entire record was elevated later, consistent with Rule 45 procedural provisions.
  • Respondent was afforded due process as it was informed of allegations via letter, given time to reply and submit evidence, and allowed to seek reconsideration; strict formalities in administrative procedural rules were relaxed in favor of substantial justice.

Supreme Court’s Ruling on the Merits

  • Respondent’s application described itself as a new producer of beneficiated nickel silicate ore based on a newly adopted beneficiation process but did not explicitly represent building a beneficiation plant.
  • Neither the BOI Project Approval Sheet, Certificate of Registration, nor the 2007 IPP imposed a requirement for physical construction of a beneficiation plant or any new physical structure as a condition precedent to ITH entitlement.
  • Even assuming a commitment to build a beneficiation plant, this did not necessitate a building but could refer to an assemblage of equipment performing beneficiation processes.
  • Respondent proved ownership and use of substantial machinery and equipment (e.g., mobile process screen, power screen, mobile crusher, loaders, backhoe, trucks) forming a beneficiation plant operation.
  • Evidence showed significant investments amounting to over Php1.15 billion in equipment and facilities.
  • Respondent submitted progress reports and was issued a Certificate of Good Standing by BOI.
  • The BOI’s withdrawal was therefore unsupported by substantial evidence and contrary to factual findings.

Legal Principles Affirmed

  • Factual findings of administrative agencies are respected but may be overturned when unsupported by substantial evidence.
  • Due process in administrative cancellations emphasizes the opportunity to be heard and to present evidence rather than stringent procedural technicalities.
  • The interpretation of terms and conditions of fiscal incentives by the administering agency must be guided by clear stipulations, not by su

...continue reading

Analyze Cases Smarter, Faster
Jur is a legal research platform serving the Philippines with case digests and jurisprudence resources.