Case Summary (G.R. No. 172077)
Factual Background
Sometime in 1972, BISUDECO was established in Himaao, Pili, Camarines Sur. In the same year, it constructed the disputed road, approximately seven meters wide and 2.9 kilometers long. Petitioner claimed that, by reason of BISUDECO’s use of the road for hauling and transporting sugarcane to and from its mill site, the road became indispensable to sugar milling.
Petitioner asserted that BISUDECO constructed the road pursuant to an alleged agreement with landowners whose ricefields the road traversed. The purported terms were that BISUDECO would employ the children and relatives of the landowners in exchange for the construction. Petitioner further contended that, through prolonged and continuous use, BISUDECO acquired a right of way, and that such right of way was acquired by BAPCI when it purchased BISUDECO’s assets on October 30, 1992.
Initiation of the Civil Action and Early Court Orders
On April 19, 1993, BAPCI filed a complaint against the respondents alleging that, on March 27, 1993 and April 3, 1993, respondents unjustifiably barricaded the disputed road by placing bamboos, woods, placards, and stones across it, preventing petitioner and other sugar planters’ vehicles from passing through. Petitioner prayed that respondents be permanently restrained from barricading and from obstructing free passage.
In an Order dated April 19, 1993, the RTC directed respondents and those acting with them to cease and desist from placing barricades on the disputed road. On July 21, 1993, the RTC issued a Writ of Preliminary Injunction ordering respondents to desist from constructing barricades across the road.
Respondents’ Defense and Petitioner’s Alternative Theory
Respondents denied that they had entered into any agreement with BISUDECO regarding the construction and use of the disputed road. They alleged that BISUDECO surreptitiously and without their knowledge and consent constructed the road on their properties and intermittently and discontinuously used it for hauling sugarcane despite repeated protests. Respondents also claimed they tolerated BISUDECO because BISUDECO was then a government-owned and controlled corporation and because the country was under Martial Law. They further denied that the road had become a public road, emphasizing that no public funds were used for its construction and maintenance.
Petitioner amended its complaint and, as an alternative cause of action, invoked Article 649 of the New Civil Code, seeking a compulsory easement of right of way upon payment of proper indemnity. Respondents replied, arguing that an alternative road existed—a route from the sugarmill to the Maharlika Highway at Barangay Romero, Bula, Camarines Sur—purportedly only about fifteen kilometers away, and therefore a more appropriate right of way.
RTC Decision: Permanent Injunction and Indemnity; No Agreement Proven
On June 25, 1997, the RTC rendered its decision. It declared the writ of preliminary injunction against the defendants, their agents, representatives, and those acting with them, permanent and perpetual. It nevertheless held that petitioner failed to present concrete evidence proving an agreement between BISUDECO and respondents for the construction of the disputed road. It also ruled that petitioner did not acquire the right by prescription.
Despite rejecting petitioner’s theory of acquisition through agreement and prescription, the RTC found petitioner entitled to a compulsory easement of right of way under Article 649, upon payment of proper indemnity to respondents. The RTC ordered petitioner to pay the owners of the lots affected by the road specified in the dispositive portion, and it declared that, upon full payment, petitioner would become the absolute owner of the road in question.
CA Proceedings and Modification of the RTC Ruling
Both parties filed motions for reconsideration in the RTC, which were denied on September 24, 1997. The parties then appealed to the CA.
On August 24, 2005, the CA issued a decision that modified the RTC ruling. The CA deleted specific awards of indemnity to Clara Padua and Prudencio Benosa, Jr., and reversed the portion of the RTC decision declaring that petitioner would become the absolute owner of the disputed road upon full payment of indemnity. The CA held instead that the owners of the servient estate in the easement of right of way would retain ownership of the affected lands in accordance with Art. 630 of the Civil Code. In all other respects, the CA affirmed the RTC.
The CA sustained the RTC’s factual determination that there was no conclusive proof of an agreement between BISUDECO and respondents. It also reiterated that an easement of right of way is discontinuous and cannot be acquired by prescription. It maintained that petitioner was entitled to a compulsory easement of right of way upon payment of proper indemnity but corrected the ownership consequence by keeping ownership with the servient estate owners.
On March 28, 2006, the CA denied the motions for reconsideration, prompting petitioner’s Supreme Court petition.
Procedural Issue on the Remedy: Rule 65 Instead of Rule 45
At the outset, the Supreme Court addressed the procedural posture. Petitioner denominated the petition as one under Rule 65 though it sought to set aside CA’s decision and resolution. The Court held that the proper remedy should have been a petition for review under Rule 45, since the assailed dispositions were final rulings of the CA.
Nonetheless, the Supreme Court considered the petition as one under Rule 45 in the interest of substantial justice, because it was filed within the reglementary period and because petitioner did not allege grave abuse of discretion amounting to lack or excess of jurisdiction by the CA.
The Parties’ Contentions in the Supreme Court
Petitioner assigned multiple errors, centered on five themes: first, it claimed the CA erred by not finding that BISUDECO and respondents had forged an agreement for constructing the disputed road; second, it argued that principles of prescription, laches, and estoppel should bar respondents from asserting ownership rights; third, it contended the CA disregarded the road’s alleged classification as a barangay road; fourth, it argued that indemnity should be valued at the time of construction; and fifth, it invoked unjust enrichment.
Existence of the Alleged Agreement: Failure of Proof; Hearsay and Circumstantial Evidence Insufficient
In relation to the first error, petitioner argued that there was an agreement, supported by both circumstantial evidence and alleged public knowledge. The Supreme Court emphasized that petitioner bore the burden of proving the existence of the agreement because the easement of right of way, as characterized by the CA as discontinuous, could be acquired only by title.
The CA had explained that an easement of right of way is typically a discontinuous easement because its use is in intervals and depends on the act of man. Under Article 622, discontinuous easements may be acquired only by virtue of a title. Since petitioner conceded it had no direct evidence of the agreement, the question was whether the circumstantial evidence sufficed.
The RTC and CA both found that it did not. The RTC noted that petitioner’s witnesses relied on commonly known information, sources not presented in court, and statements from persons not personally involved in concluding the alleged agreement. The CA agreed that petitioner’s evidence was not conclusive. It held that the circumstances cited by petitioner were susceptible to diverse interpretations. It also found that petitioner’s testimonies were largely hearsay, because the witnesses did not have personal knowledge by direct participation or presence when the agreement was concluded.
The Supreme Court sustained these concurrent factual findings. It held that petitioner’s inability to prove an agreement undermined the theory that it acquired the easement by title grounded on agreement, and it refused to disturb the CA’s factual conclusions, particularly because the CA had affirmed the RTC’s factual findings.
Acquisition by Prescription: Discontinuous Easement; No Re-examination of Controlling Doctrine
Petitioner sought to revisit Costabella Corporation v. Court of Appeals, which held that a right of way is discontinuous and cannot be acquired by prescription. Petitioner attempted to argue that recognized authorities support acquisition by prescription, contending that continuity is not absolute and that intervals do not defeat prescription.
The Supreme Court declined to re-examine Costabella. It instead relied on Bogo-Medellin Milling Co., Inc. v. Court of Appeals, which involved an easement of right of way in the form of a railroad track. That case had clarified the legal distinction: easements are continuous or discontinuous based on the manner of exercise, not on the presence of apparent physical signs. A right of way is discontinuous because it is exercised only if and when a person passes or sets foot on another’s land. The presence of physical indications, such as tracks or a paved road, renders the easement apparent but does not convert it into a continuous easement.
Applying this reasoning, the Court held that the road in dispute remained a discontinuous easement. Accordingly, Article 622 required that it be acquired only by title, not by prescription. The Court thus rejected petitioner’s prescription argument, even if the road had been improved and maintained over many years.
Laches and Estoppel: Equity Cannot Override Article 622; No Showing of Estoppel
Petitioner also invoked laches and estoppel. It asserted that BISUDECO’s use had been peaceful and continuous for almost two decades without protest, and therefore respondents should be barred from later obstructing access.
The CA had rejected the laches theory, reasoning that Article 622 is categorical: discontinuous easements require title. It explained that laches, as an equitable doctrine,
...continue reading
Case Syllabus (G.R. No. 172077)
Parties and Procedural Posture
- Bicol Agro-Industrial Producers Cooperative, Inc. (BAPCI) filed a Petition for Review on certiorari assailing the Court of Appeals (CA) Decision and Resolution in CA-G.R. CV No. 59016.
- The petition sought to set aside the August 24, 2005 Decision and the March 28, 2006 Resolution of the CA.
- The petition was denominated under Rule 65 even though it challenged a CA decision, prompting the Court to treat the petition as one under Rule 45 in the interest of substantial justice.
- The Court relied on the doctrine distinguishing Rule 65 and Rule 45, and held that the availability of an appeal barred resort to certiorari.
- The Court nonetheless considered the petition under Rule 45 because it was filed within the reglementary period and did not raise allegations of grave abuse of discretion or lack of jurisdiction by the CA.
- The controversy arose from an action in the Regional Trial Court (RTC) of Pili, Camarines Sur, which declared a perpetual restraint on barricading the disputed road and awarded indemnity under the Civil Code.
- The RTC’s judgment was modified by the CA, which deleted some indemnity awards, reversed the RTC’s declaration of ownership upon full payment, and affirmed the grant of a compulsory easement of right of way subject to indemnity.
- The Supreme Court ultimately denied the petition and affirmed the CA.
Key Factual Background
- In 1972, Bicol Sugar Development Corporation (BISUDECO) was established in Himaao, Pili, Camarines Sur.
- In the same year, BISUDECO constructed the disputed road, measuring approximately seven meters wide and two point nine kilometers long.
- The disputed road served BISUDECO’s sugar milling operations by hauling and transporting sugarcane to and from its mill site (Pensumil).
- On October 30, 1992, BAPCI acquired the assets of BISUDECO.
- On March 27, 1993 and April 3, 1993, respondents allegedly barricaded the disputed road using bamboos, woods, placards, and stones.
- BAPCI alleged that BISUDECO constructed the road pursuant to an agreement with landowners along the road’s path.
- BAPCI claimed the road’s construction and prolonged use resulted in a right of way that BISUDECO acquired and that BAPCI inherited when it bought BISUDECO’s assets.
- Respondents denied that they entered into any agreement with BISUDECO and alleged that BISUDECO surreptitiously constructed the road without their knowledge or consent.
- Respondents further asserted that they merely tolerated BISUDECO’s use because BISUDECO was a government-owned and controlled corporation during Martial Law, and because the road allegedly became public without public funds.
- Respondents also claimed that, except for Edmundo and Perfecto Obias, they were actual tillers whose rights derived from Presidential Decree No. 27 (PD 27).
- The litigation included complaints-in-intervention by sugarcane planters, but the text indicates that the intervenors did not join BAPCI in the Supreme Court petition.
Trial Court Proceedings
- The RTC issued an initial Order dated April 19, 1993 directing respondents to cease and desist from placing barricades on the disputed road.
- The RTC also issued a writ of preliminary injunction dated July 21, 1993 ordering respondents to desist from constructing barricades across the road.
- In its Decision dated June 25, 1997, the RTC declared the preliminary injunction permanent and perpetual against respondents and those acting for them.
- The RTC found that BAPCI failed to present concrete evidence proving an agreement between BISUDECO and respondents for the construction of the disputed road.
- The RTC ruled that BAPCI did not acquire the right of way by prescription.
- Despite the lack of proof of an agreement and the rejection of prescription, the RTC held that BAPCI was entitled to a compulsory easement of right of way under Article 649 of the New Civil Code, upon payment of proper indemnity.
- The RTC awarded indemnity to named affected landowners and ruled that after full payment, BAPCI would become the absolute owner of the road in question.
- The RTC denied costs and imposed legal interest from finality until full payment of indemnity.
- Both parties moved for reconsideration, with BAPCI challenging the valuation as excessive and respondents challenging the declaration of entitlement and the damages aspects.
- The RTC denied both motions on September 24, 1997.
Court of Appeals Ruling
- The CA partly granted BAPCI’s appeal by deleting specific indemnity awards to Clara Padua and Prudencio Benosa.
- The CA also reversed and set aside the RTC’s pronouncement that BAPCI would become the absolute owner of the disputed road upon full payment of indemnity.
- The CA clarified that the affected owners of the servient estate in the easement of right of way retained ownership over the lands affected, consistent with Article 630 of the Civil Code.
- The CA affirmed the RTC’s finding that BAPCI failed to provide conclusive proof of an agreement between BISUDECO and respondents.
- The CA held that an easement of right of way is discontinuous and therefore cannot be acquired by prescription.
- The CA sustained the RTC’s grant of a compulsory easement of right of way upon payment of proper indemnity.
- The CA deleted the indemnity awards to Prudencio Benosa and Clara Padua on the ground that Benosa never claimed ownership of any portion and Padua was not a party in the proceedings below.
- The CA denied subsequent motions for reconsideration, leading to BAPCI’s petition before the Supreme Court.
Issues Raised
- BAPCI argued that the CA erred in not finding that a forged agreement existed between BISUDECO management and respondents for road construction.
- BAPCI contended that the CA failed to consider prescription, laches, and estoppel as bars to respondents’ claims.
- BAPCI asserted that the CA erred in disregarding the classification of the disputed road as a barangay road.
- BAPCI argued alternatively that the indemnity valuation should be based on the land value in 1974 when the road was constructed rather than in 1994.
- BAPCI invoked the principle of unjust enrichment in an attempt to justify compensation or relief at respondents’ expense.
Supreme Court Standard of Review
- The Court reiterated the gen