Atlas Consolidated Mining and Development Corp. vs. Progressive Labor Association
Case
G.R. No. L-27125
Decision Date
Sep 15, 1967
Atlas Consolidated Mining's appeal dismissed due to non-compliance with Rule 41, Section 6; record lacked mandatory data for timely appeal, rendering certification insufficient.

Case Summary (G.R. No. L-27125)

Procedural History and Issues Raised

The case's procedural timeline began with the dismissal order on August 31, 1966. Following this, the plaintiff filed a motion for reconsideration on September 15, 1966, which was subsequently denied on October 8, 1966. The plaintiff later submitted a notice of appeal on November 14, 1966, and the record on appeal was filed on November 19, 1966. The key issue presented in the motion to dismiss the appeal, filed by the defendants, was the plaintiff's failure to provide critical dates in the record on appeal: specifically, the date the plaintiff received notice of the dismissal and the date of the denial of the motion for reconsideration.

Requirement for Timely Perfection of Appeal

Section 6 of Rule 41 of the Revised Rules of Court stipulates that a record on appeal must contain information demonstrating that the appeal was perfected in a timely manner. The absence of such data in the appellant's record precluded the appellate court from determining whether the appeal was perfected within the required timeframe. The deficiency stemmed from failure to indicate when the notice of dismissal was received and when the notice of denial was acknowledged.

Amendments and Jurisdictional Implications

This case highlights the importance of adherence to procedural rules aimed at efficiently resolving appeals. The court underscored that the amendments instituted in the Rules of Court were designed to streamline appeal processes and eliminate delays caused by disputes over the timing of appeals. Citing previous jurisprudence, the court established that failure to comply with these rules is deemed fatal to the appeal since timely perfection of an appeal is a jurisdictional requirement.

Certification and Its Limitations

Although the appellant provided a certification from the Clerk of Court, which indicated that the appeal was filed within the prescribed period, the Supreme Court noted that such certification could not remedy the deficiencies present in the record on appeal, especially since it was submitted after the expiration of the appeal period. The court emphasized that allowing post-hoc certi