Title
Asian Construction and Development Corp. vs. MERO Structures, Inc.
Case
G.R. No. 221147
Decision Date
Sep 29, 2021
FCCC contracted Asiakonstrukt for a project; MERO supplied materials. Payment disputes arose; MERO sued. SC ruled no novation, upheld MERO’s claim despite corporate name change.

Case Summary (G.R. No. 221147)

Key Dates and Procedural Posture

Relevant transaction dates in 1998: Construction Agreement between FCCC and Asiakonstrukt (Mar. 16, 1998); MERO’s Materials Only Proposal (Mar. 16, 1998) accepted by Asiakonstrukt (Mar. 17, 1998); bill of lading dated Apr. 5, 1998 evidencing shipment; Asiakonstrukt’s proposal to FCCC dated Jun. 16, 1998; FCCC approval dated Jun. 17–18, 1998. MERO’s final demand dated Sept. 21, 2000 and demand to be paid by FCCC dated Oct. 13, 1999; Asiakonstrukt’s response dated Nov. 8, 1999. MERO filed suit Feb. 21, 2002. RTC decision July 19, 2011; CA decision Feb. 18, 2015 (Resolution denying reconsideration Oct. 21, 2015); Supreme Court decision denying the petition (Sept. 29, 2021).

Applicable Law and Legal Authorities

Constitutional framework: 1987 Philippine Constitution (applicable due to decision date after 1990). Governing substantive law: Civil Code provisions on extinguishment and modification of obligations (Articles 1231, 1291–1293 cited in the decision). Controlling jurisprudence applied includes Nacar v. Gallery Frames (for tempering stipulated interest) and Garcia v. Llamas (for discussion of novation), and Arco Pulp and Paper Co. v. Dan T. Lim (cited on novation requirements).

Factual Background and Contracts

Two primary written instruments governed the transaction: (1) the Construction Agreement (FCCC — Asiakonstrukt, Mar. 16, 1998) and (2) MERO’s Materials Only Proposal (Mar. 16, 1998), accepted by Asiakonstrukt (Mar. 17, 1998). MERO’s proposal set the price for the spaceframe at US$570,000 with payment terms (20% upon award, remainder via letter of credit; shipping contingent on confirmation). MERO shipped the spaceframe (bill of lading Apr. 5, 1998). Asiakonstrukt thereafter sought and received FCCC’s approval for Asiakonstrukt to design, supply and install the flag structure using MERO’s spaceframe, subject to conditions including compliance with audit rules and certification by MERO.

Correspondence, Attempts at Direct Collection, and Payment Refusals

From March 1998 onward MERO repeatedly sought payment from Asiakonstrukt. After FCCC’s board approval and discussions about financing via NDC, Asiakonstrukt informed MERO (Jun. 18, 1998) that FCCC awarded the contract and would pay MERO after FCCC’s payment of materials. MERO continued demands, and on Oct. 13, 1999 MERO asked to be paid directly by FCCC; Asiakonstrukt responded Nov. 8, 1999 stating it interposed no objection to such direct collection. Despite these exchanges and MERO’s attempts to secure assistance from government agencies, payment was not obtained and FCCC’s new president indicated lack of knowledge of a contract between MERO and FCCC.

Trial Court Findings and Relief (RTC)

MERO filed a complaint for sum of money (Feb. 21, 2002). The RTC found in favor of MERO and against Asiakonstrukt and FCCC (but dismissed the complaint against NDC for lack of evidence). The RTC ordered Asiakonstrukt to pay the equivalent in pesos of US$570,000 (P25,650,000 at an exchange rate used by the court), imposed 6% legal interest per annum from date of decision and 12% per annum from finality until paid, and recognized MERO’s right to be reimbursed from FCCC without pronouncement as to costs. The RTC rejected Asiakonstrukt’s claim that a written agreement existed imposing 18% annual interest because the document asserting 1.5% monthly interest lacked signatures of the defendants and therefore was not a binding written stipulation.

Court of Appeals Ruling

Both MERO and Asiakonstrukt appealed. The CA denied both appeals but modified the RTC’s interest award. The CA found that, contrary to the RTC, there was a written stipulation as to 18% annual interest between MERO and Asiakonstrukt, yet applied the Court’s equitable tempering authority (per Nacar) and adjusted the interest treatment: 12% per annum applied from date of default (March 31, 1998) until June 30, 2013, and thereafter 6% per annum until fully paid. The CA agreed with the RTC in holding Asiakonstrukt accountable and treating the letters as insufficient to effect novation or extinguish Asiakonstrukt’s obligation.

Issues Raised in the Petition for Review

Asiakonstrukt’s principal assignments of error to the Supreme Court were: (1) that the CA erred in not treating MERO’s Oct. 13, 1999 letter and Asiakonstrukt’s Nov. 8, 1999 response as a new written contract effecting novation so that MERO would collect directly from FCCC, thereby extinguishing Asiakonstrukt’s obligation; and (2) that the CA erred by failing to exclude Novum Structures LLC (a foreign respondent after conversion) as a party because MERO had allegedly transferred interest or changed status.

Supreme Court Analysis on Novation and Extinguishment

The Supreme Court denied the petition. It held there was no new contract or novation arising from the exchanged letters. The Court applied Civil Code principles: novation requires either an express declaration that the old obligation is extinguished or that the old and new obligations are incompatible on every point (Articles 1291–1293). The Court reiterated the requisites of novation (previous valid obligation; agreement to a new contract; extinction of the old contract; a valid new contract) and cited Garcia v. Llamas on express versus implied novation and the need for creditor consent where substitution or subrogation is concerned. The Court found: (a) the letters did not unequivocally state extinguishment of Asiakonstrukt’s obligation; (b) the letters merely showed Asiakonstrukt’s non-objection to MERO attempting to collect from FCCC, which is not incompatible with Asiakonstrukt’s continuing obligation; and (c) FCCC’s consent was absent — a necessary component if substitution or subrogation were intended — because FCCC was not party to those letters. Consequently, the obligation of Asiakonstrukt to MERO remained valid and enforceable.

Allocation of Risk and Liability Between Contractor and Project Owner

The Supreme Court emphasized that Asiakonstrukt, as the primary contractor who subcontracted a component to MERO, assumed the risk of FCCC’s nonpayment. The fulfillment of FCCC’s obligation to Asiakonstrukt was not shown to be a condition precedent to Asiakonstrukt’s obligation to pay MERO. Therefore Asiakonstrukt remained the primary obligor to MERO; FCCC and NDC could not be held primarily liable based on the record

...continue reading

Analyze Cases Smarter, Faster
Jur helps you analyze cases smarter to comprehend faster, building context before diving into full texts. AI-powered analysis, always verify critical details.